Barry Young v. Bailey Elliott Construction, Inc.

CourtCourt of Appeals of Texas
DecidedSeptember 25, 1996
Docket03-95-00630-CV
StatusPublished

This text of Barry Young v. Bailey Elliott Construction, Inc. (Barry Young v. Bailey Elliott Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barry Young v. Bailey Elliott Construction, Inc., (Tex. Ct. App. 1996).

Opinion

Young

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN



NO. 03-95-00630-CV



Barry Young, Appellant



v.



Bailey Elliott Construction, Inc., Appellee



FROM THE DISTRICT COURT OF TRAVIS COUNTY, 200TH JUDICIAL DISTRICT

NO. 94-08594, HONORABLE JOE B. DIBRELL, JUDGE PRESIDING



This is an appeal by appellant Barry Young from a judgment of the trial court in favor of appellee Bailey Elliott Construction, Inc. ("Bailey Elliott"). The trial court awarded $31,013.08 in actual damages to Bailey Elliott as a result of the fraud practiced upon it by Young, stemming from Young's failure to secure a performance and payment bond. The court further awarded $46,450 in exemplary damages to Bailey Elliot, which included an award for appellate attorneys' fees. Young appeals this judgment in seventeen points of error. We will affirm the judgment of the trial court.



BACKGROUND

Because Young challenges the sufficiency of the evidence supporting the award of exemplary damages, we set forth the facts in detail. See Transportation Ins. Co. v. Moriel, 879 S.W.2d 10, 31 (Tex. 1994). In December 1993, Bailey Elliott entered into a general construction contract with MetalOptics, Inc. under which Bailey Elliott would act as a general contractor for the construction of a 54,000 square foot building that would serve as MetalOptics' offices and its air conditioning assembly and manufacturing space. During the process of bidding the project out to various subcontractors and suppliers, Bailey Elliott awarded the subcontract to erect the steel as well as some additional work to Custom Construction, whose principal was Ken Urban but in which Barry Young was also involved. At some point, Urban informed Bailey Elliott that he could not perform the subcontract.

Mr. Elliott of Bailey Elliott then met with Barry Young and John Hanna and discussed awarding this subcontract to Young Erectors, Inc., a corporation that Young and Hanna were attempting to form. Elliott told them that Bailey Elliott would award the subcontract to erect the steel for the MetalOptics building to Young Erectors provided it would secure a release from Ken Urban as well as provide a performance and payment bond. (1) Young and Hanna told Elliott that Young Erectors would agree to get a bond if Bailey Elliott entered into a contract with it.

Elliott believed that Young fully intended that Young Erectors would get a bond. This was the only conversation Elliott had with Young until after Young Erectors abandoned the MetalOptics project. After this meeting, Elliott did have two conversations with Hanna in which Hanna again indicated that Young Erectors would agree to get a bond in the future.

Elliott then prepared the contract and sent it to Young Erectors. Young signed the contract on behalf of Young Erectors and returned it to Elliott, who then signed it in the name of Bailey Elliott on March 31, 1994. Lynn Brantley, the corporate secretary of Young Erectors, was in charge of obtaining the performance and payment bond. In attempting to do so, Brantley called several bonding companies, including Time Insurance Agency ("Time"). Time required a financial statement from the individuals or company seeking the bond, and, because Young Erectors had no financial statement, Young furnished his personal financial statement to Time. Additionally, Time notified Brantley that, before agreeing to issue a bond, it would require that Young sign a personal indemnity agreement. Meanwhile, in response to a phone call concerning the application for the bond, Time told a representative of Bailey Elliott that Young Erectors had been approved for the bond. Young, however, never signed a personal indemnity agreement, and a bond was never issued. During this time, Lynn Brantley handled all contacts with Time concerning the bond, and Young never personally spoke with anyone from Time.

Under the subcontract, Bailey Elliott was to pay Young Erectors $34,286 upon satisfaction of its contractual obligations. Young Erectors began work on the MetalOptics building on April 4, 1994, but Young decided that Young Erectors should stop work on the project on April 14, 1994. According to Hanna, Young Erectors had completed 90 percent of the steel erection and 30 percent of the miscellaneous work under the subcontract. Elliott, however, testified that Young Erectors completed less than 40 percent of the total work.

From the date when the contract was executed until April 14, 1994, when work was stopped on the project, Young Erectors incurred several debts that went unpaid. Aztec Crane Corporation ("Aztec") and Walter's Crane Service, Inc. ("Walter's") filed mechanic's liens against the MetalOptics property; Aztec in the amount of $11,822.60 and Walter's in the amount of $3,857.50. Kennedy Welding Supply and Equipment Corporation ("Kennedy") also filed a lien against the MetalOptics property in the amount of $340.40, but that lien was released and Kennedy was dismissed as a party to this suit in connection with a settlement before trial. Odyssey Management Company, Inc. ("Odyssey"), another creditor of Young Erectors, served written claims totaling $18,417 upon Bailey Elliott but did not perfect a mechanic's lien against the MetalOptics property. At Bailey Elliott's instruction, MetalOptics did not pay these creditor's claims. The total amount of the liens exceeded the total amount of the Young Erectors subcontract.

Bailey Elliot's general construction contract with MetalOptics was a cost-plus contract with a guaranteed maximum price. Bailey Elliott was to be reimbursed for all the costs in constructing the building, so long as the costs plus Bailey Elliott's $80,000 fee did not exceed the guaranteed maximum price of $1,919,000. The contract provided that, if there was any savings in the cost of constructing the building, Bailey Elliott and MetalOptics would share in that savings with Bailey Elliott receiving one-third of the savings and MetalOptics receiving two-thirds. The contract had a liquidated damages clause providing a penalty of $750 per day for each day of construction on the project after 150 days. Similarly, the contract had a $500 per day bonus clause for early completion. Accordingly, Bailey Elliott hired Jett Enterprises ("Jett") and Quality Steel Erectors ("Quality") to complete the work on the project, paying the two companies a total of $46,779.84 to do so. Even after paying Jett and Quality, there remained a savings of about $34,000 on the project.

On July 14, 1994, Bailey Elliott filed suit against Young, Hanna, Young Erectors, Aztec, Walter's, Kennedy, and Odyssey. Then, on August 2, 1994, Young filed a petition for bankruptcy on behalf of Young Erectors.



DISCUSSION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aluminum Co. of America v. Bullock
870 S.W.2d 2 (Texas Supreme Court, 1994)
Gentry v. Credit Plan Corporation of Houston
528 S.W.2d 571 (Texas Supreme Court, 1975)
Allison v. Simmons
306 S.W.2d 206 (Court of Appeals of Texas, 1957)
Alamo National Bank v. Kraus
616 S.W.2d 908 (Texas Supreme Court, 1981)
Sharp v. Broadway National Bank
784 S.W.2d 669 (Texas Supreme Court, 1990)
Warehouse Partners v. Gardner
910 S.W.2d 19 (Court of Appeals of Texas, 1995)
Henry S. Miller Co. v. Bynum
836 S.W.2d 160 (Texas Supreme Court, 1992)
Gallagher v. Bintliff
740 S.W.2d 118 (Court of Appeals of Texas, 1987)
Catalina v. Blasdel
881 S.W.2d 295 (Texas Supreme Court, 1994)
McLendon v. McLendon
862 S.W.2d 662 (Court of Appeals of Texas, 1993)
Transportation Insurance Co. v. Moriel
879 S.W.2d 10 (Texas Supreme Court, 1994)
Gee v. Liberty Mutual Fire Insurance Co.
765 S.W.2d 394 (Texas Supreme Court, 1989)
Spoljaric v. Percival Tours, Inc.
708 S.W.2d 432 (Texas Supreme Court, 1986)
Morris v. Short
902 S.W.2d 566 (Court of Appeals of Texas, 1995)
Best v. Ryan Auto Group, Inc.
786 S.W.2d 670 (Texas Supreme Court, 1990)
T.O. Stanley Boot Co. v. Bank of El Paso
847 S.W.2d 218 (Texas Supreme Court, 1993)
Castleberry v. Branscum
721 S.W.2d 270 (Texas Supreme Court, 1986)
Cavnar v. Quality Control Parking, Inc.
696 S.W.2d 549 (Texas Supreme Court, 1985)
Central Power & Light Co. v. Bullock
696 S.W.2d 30 (Court of Appeals of Texas, 1984)
Motsenbocker v. Potts
863 S.W.2d 126 (Court of Appeals of Texas, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Barry Young v. Bailey Elliott Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/barry-young-v-bailey-elliott-construction-inc-texapp-1996.