Barney Coal Co. v. Davis

55 So. 1023, 1 Ala. App. 595, 1911 Ala. App. LEXIS 306
CourtAlabama Court of Appeals
DecidedJune 6, 1911
StatusPublished
Cited by8 cases

This text of 55 So. 1023 (Barney Coal Co. v. Davis) is published on Counsel Stack Legal Research, covering Alabama Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barney Coal Co. v. Davis, 55 So. 1023, 1 Ala. App. 595, 1911 Ala. App. LEXIS 306 (Ala. Ct. App. 1911).

Opinion

WALKER, P. J.

The original complaint in this case alleged that plaintiff entered into a contract with defendant to dig a slope or entry and aircourse in defendant’s mine, and undertook to show a breach of the contract by the defendant by its refusal to let plaintiff proceed further with the work, whereby plaintiff was deprived of the opportunity of earning profits which, it was alleged, he could have realized if he had been permitted to contiue the work under the contract. The demuxTer to the complaint suggested a deficiency in it, in that it failed to allege that, at the time the defendant refused to let plaintiff proceed further with the work, he was able, willing, and ready to carry out and perform his part of the contract.

It hardly is necessary to have recourse to the rule for construing a pleading most strongly against the pleader to read the averment of the complaint in this case as to the plaintiff’s readiness and willingness to carry out his part of the contract sued on as showing no more than that at some time since the work was stopped by [598]*598the defendant there has been snch readiness and willingness on the pant of the plaintiff. That averment conld be sustained by evidence showing no more than that, at some time subsequent to the date of defendant’s refusal to let plaintiff proceed further with the work, and before the suit was brought, the plaintiff became ready and willing to carry out his part of the contract, though at the time the work was stopped he was not ready or able to proceed further with it. It was not a breach of the contract by the defendant to stop the Avork, if at the time it was done the plaintiff was not ready or able to prpceed further with the work called for by the contract. In failing to show that such was the case, the complaint failed to show a breach by the defendant of the cdntract sued on.

A party, seeking to recover on the breach of a contract containing mutual and dependent covenants or stipulations, must aver and prove his own offer and readiness and ability to perform, and that the other party has failed to perform on his part.—Sayre v. Wilson & Ingram, 86 Ala. 151, 5 South. 157; Union Refining Co. v. Barton, 77 Ala. 148; Raudabaugh v. Hart, 61 Ohio St. 73, 55 N. E. 214, 76 Am. St. Rep. 361, and note; 3 Page on Contracts, § 1470. The ground of demurrer referred to pointed out wher,eia the complaint failed to show a breach by the defendant of the contract sued on, and the demurrer should have been sustained.

Reversed and remanded.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Finklea v. Garrick
147 So. 677 (Alabama Court of Appeals, 1932)
Hamilton v. O'Rear
141 So. 565 (Supreme Court of Alabama, 1932)
Lide v. Birmingham Electric Battery Co.
115 So. 689 (Alabama Court of Appeals, 1927)
Sloss-Sheffield Steel & Iron Co. v. Payne
68 So. 359 (Supreme Court of Alabama, 1915)
Moss v. King
65 So. 180 (Supreme Court of Alabama, 1914)
Birmingham Railway, Light & Power Co. v. Pratt
64 So. 510 (Alabama Court of Appeals, 1914)
Greek-American Produce Co. v. Pappas
63 So. 799 (Alabama Court of Appeals, 1913)
Barney Coal Co. v. Davis
62 So. 985 (Alabama Court of Appeals, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
55 So. 1023, 1 Ala. App. 595, 1911 Ala. App. LEXIS 306, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barney-coal-co-v-davis-alactapp-1911.