Barnett v. Concrete Placing Co.

120 So. 2d 628, 1960 Fla. App. LEXIS 2541
CourtDistrict Court of Appeal of Florida
DecidedMay 19, 1960
DocketNo. 59-427
StatusPublished
Cited by3 cases

This text of 120 So. 2d 628 (Barnett v. Concrete Placing Co.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barnett v. Concrete Placing Co., 120 So. 2d 628, 1960 Fla. App. LEXIS 2541 (Fla. Ct. App. 1960).

Opinion

MILLEDGE, STANLEY, Associate Judge.

This case deals with the duty of a subcontractor to credit undesignated payments received from a general contractor to the particular debt owed by the debtor when the ultimate source of the payment is the owner of land having a general contractor for the erection of improvements, since the owner; by virtue of the mechanic’s lien law, is a statutory surety on the contractor’s debt to the sub-contractor on the same job.

The appellants, the Barnetts, contracted with Snyder Enterprises, Inc., on October 2, 1957, to build a swimming pool at their home for $3,673.75. Snyder, shortly afterward, entered into a sub-contract with Concrete Placing Co. to do a part of the work for $1,856 plus an incidental cost determinable only after the work was finished. This was not an isolated transaction between Snyder and Concrete. Concrete had one general ledger account with Snyder in which they debited Snyder with each sub-contract (including the present one) showing the location of each job. By an initial payment of $1,000 at date of the general contract and by subsequent payments on October 16 and October 31, 1957, Barnett paid Snyder a further sum of $1,-973.55 and on October 31 Concrete credited Snyder with $856, making a total then received from Snyder during October of $1,856, the amount of the sub-contract. Concrete did not place either payment to [630]*630the Barnett job but simply entered a gen-'' eral credit to the account of Snyder.

Before the Barnett job started Snyder’s, shaky financial condition was . known to Concrete. ' As a matter of fact, Snyder-soon took bankruptcy. In September, 1957, Snyder had a meeting with some of its creditors including Concrete to whom Snyder owed several thousand dollars on old jobs. As to what transpired at the meeting there is conflict in the evidence. According to Snyder, Concrete put his company on a “pay as you go basis,” that is, as jobs were commenced and completed they would be paid for before another job was commenced. Concrete’s testifying officer said' that the billing arrangement was not changed but that Snyder was “to pay on their old account an amount equal to or greater each month 'than the amount of work that we did in any month. In other-words, they were not getting further behind and were to catch up as they went along.” Payments by Snyder were to be. applied “to the oldest due account.” According to this, old accounts were' to be credited with money received by Snyder on new accounts instead of applying them on the new sub-contract accounts, leaving concrete free to file lien claims against any unwary owners ignorant of the peculiarities of the Mechanic’s Lien Law and so, in the eyes of the lien law, foolish' enough to trust the general contractor. A few jobs, like the Barnett’s, would remove the deficit of the entire Snyder account, merely by Snyder paying the amount of each sub-contract with the owner’s money and then proceeding against the owner for the same account: After three or four owners were forced to pay double, the accounts of Snyder and Concrete- would balance. During the time the Barnett job was in progress there were no other jobs between Concrete and Snyder and- during the month of October Concrete got no money from Snyder except on -the Barnett job and with Barnett’s money. Presumably the supply of “Barnetts” was not sufficient to save-Snyder from' bankruptcy or perhaps the clever arrangement of the creditors’ conference was not put in operation soon-enough. Where could Snyder get the money to pay Concrete for new jobs not. to say the “catching up,” as it was euphemistically called, except from new owners? The question is purely rhetorical.

As already noted, Barnett paid Snyder the full amount of the general contract. In fact he paid Snyder $1,000 when this contract was executed, and the circumstance that this act of faith was done before the sub-.contract was made (or at least the record requires this assumption) was. to prove unfortunate for him, as will shortly be noticed. Snyder gave Barnett a release of lien but he did not give a sworn statement that all claims for labor and. material had been paid. Barnett did not require a bond or hold back final payment until possible lien claims had been disposed of. . So even though Concrete filed no cautionary notice it is in a fine position so far as the terms of the mechanic’s lien law is concerned.

Concrete filed its claim of lien and then, brought suit to foreclose. The owners answered that they had paid. A final decree for the entire amount of the sub-contract, with all costs, was entered for the subcontractor and against the owners. From, this decree the owners appealed.

Were the question an open one it would', seem that on equitable principles, the surety has a right to have a payment from a-principal to his creditor with funds derived from the surety (who is also debtor to the principal in the same transaction) credited to the debt affecting the surety and' that this right should not depend on the circumstances as the creditor knew or-should have known them, but simply on the respective positions of the parties. This. is the conclusion reached in the following cases: Sioux City Foundry & Mfg. Co. v. Merten, 174 Iowa 332, 156 N.W. 367, L.R. A.1916D, 1247; Townsend v. Caple, 193 Ark. 297, 99 S.W.2d 258 (even when contractor directed payment to the prejudice-[631]*631of the surety); Lee v. Storz Brewing Co., 75 Neb. 212, 106 N.W. 220; Merchants’ Ins. Co. v. Herber, 68 Minn. 420, 71 N.W. 624; Williams v. Willingham-Tift Lumber Co., 5 Ga.App. 533, 63 S.E. 584, 585. The case last cited said that “what is here held is not in conflict with the general rule of law that a creditor has the right, in the absence of directions by the debtor to apply a payment on account to the oldest open item on the account. This is the rule as between the creditor and the debtor. But, where the rights of third persons are involved, the law will make the credit according to principles of justice and equity. It will not permit the money of one man to be used in the payment of the debt of another man, or declare a lien on the property of the man who has paid in full for all the materials furnished to improve his property, and thus relieve from a lien the property of the man who still owes for the material that was used to improve his property. Under the facts the plaintiff had lost the right to a lien on the property of the defendants, * * * and a verdict to the contrary should not have been directed.” Under the above group of cases knowledge or notice of the sub-contractor, materialman or laborer, is not important. The equitable right of the surety, who furnished the money, does not depend on what the sub-contractor knows or should know. No positions are changed; no right relinquished or remedy foregone or even postponed when the equities are adjusted when the true source of payment is discovered. The size of the principal debt remains the same after adjustment. The difference is that the surety is exonerated and the creditor must look to his debtor instead of collecting a second time from the surety.

There are cases which hold exactly the opposite, i. e., that the existence of a surety makes no difference and the transaction is treated as if he did not exist. The creditor, whoever he is, may apply payment to whatever debt he chooses unless the debtor has directed application. By refusing to distinguish between totally different situations such cases have no persuasiveness, and as we are not bound by them no further reference to them is necessary.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lyman Lumber of Wisconsin, Inc. v. Thompson
405 N.W.2d 708 (Court of Appeals of Wisconsin, 1987)
Carolina Lumber Co. v. Grose
16 Fla. Supp. 185 (Duval County Circuit Court, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
120 So. 2d 628, 1960 Fla. App. LEXIS 2541, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barnett-v-concrete-placing-co-fladistctapp-1960.