Barge & Co. v. City of Atlanta

288 S.E.2d 98, 161 Ga. App. 675, 1982 Ga. App. LEXIS 1978
CourtCourt of Appeals of Georgia
DecidedFebruary 1, 1982
Docket62676
StatusPublished
Cited by4 cases

This text of 288 S.E.2d 98 (Barge & Co. v. City of Atlanta) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barge & Co. v. City of Atlanta, 288 S.E.2d 98, 161 Ga. App. 675, 1982 Ga. App. LEXIS 1978 (Ga. Ct. App. 1982).

Opinion

McMurray, Presiding Judge.

On June 17, 1976, Barge and Company, Inc. entered into a contract with the City of Atlanta, Georgia, as owner, for the construction of the Bolton Road pumping station and service building. The contract was a voluminous document consisting of some 233 pages and provided, among many other things, for extra work and changes in the work. No claims for any extra work or materials were to be allowed, “unless the work is ordered in writing by the Owner or its Engineer, acting officially for the Owner.” It further provided that any extra work or cost was to be done “in pursuance of a written order of the Engineer, as aforesaid, and the claim presented with the first estimate after the changed or extra work is done.” (Emphasis supplied.) Under the authority of the engineer, we find that his decision “shall be final and conclusive, except as otherwise expressly provided herein. In case any questions shall arise between the parties hereto relevant to said contract or specifications, the determination or decision of the Engineer shall be a condition precedent to the right of the Contractor to receive any money or payment for work under this contract affected in any manner or to any extent by such question.” In regard to payment for the extra work performed by the contractor same must be “authorized by the Engineer and approved by the Owner,” to be paid as agreed upon “in written change orders signed by the Contractor, Engineer and Owner before such work is done. All extra work shall be subject to all other conditions of the contract.” (Emphasis supplied.) “Contractor” is defined as the individual, firm or corporation selected by the owner as the successful bidder; “Owner,” as the corporate body designated in the contract, the City of Atlanta; and “Engineer,” as being the engineer selected by the owner for the performance of all engineering services in connection with the design and construction of the work and his duly authorized representatives.

We are concerned here with an item known as Change Order No. 3 for reimbursement for delays in the amount of $40,000 and to increase the time of completion from 450 consecutive calendar days (shown in another place as.495 days) to a new contract time of 945 days. This change order was prepared on a City of Atlanta form and executed by the contractor and by the architect/engineer. A letter was prepared by the engineer for this construction project explaining the reasons for the need for the change order due to delays caused by others and due to the encounter of a 42 inch water main requiring relocation of tunneling with a cost breakdown as to the reasons therefor caused by the delay. After the acceptance of the building and *676 the operation of a pumping station on a permanent basis a final billing was presented to the city for the amount of $80,000, covering retainage of $40,000 and the change order in the amount of $40,000 for reimbursement of the numerous project delays set forth in the change order. The “semi-final payment of $40,000” was eventually received by Barge. Barge now contends it was owed interest on the final payment on the original contract and another $40,000 on the change order, together with interest. Two officials of the City of Atlanta (the field engineer and the chief of the construction management division) eventually approved the change order which had been arrived at by negotiation. However, it does not appear that other officials of the city such as the Mayor, the Commissioner of Finance, the Director of the Bureau of Purchasing and Real Estate, and the Commissioner of the Department of Environment and Streets, ever signed for the owner, the City of Atlanta. The service building was completed in February 1978 but the pumping station itself could not be turned over to the city until another contractor brought in the sewer line for connection to the pumping station, and a period of about four months elapsed during which this hookup delayed the final completion of the pumping station.

Eventually Barge and Company, Inc., after obtaining no satisfaction from the city with reference to the failure to pay the claimed $40,000 change order and also in failing to pay on time the retainage of $40,000 which it contended was due at the expiration of 30 days after completion of the work, and the city did not pay same until one year later, brought an action against the city seeking the $40,000 authorized by the change order, including interest at 1 1/2% per month from August 28,1978, until paid in full by the city, as well as interest at 11/2% per month from August 28,1978, to November 8, 1979, for the loss of use of the final payment on the original contract during that period of time. It amended its complaint to add a Count 2 based on quantum meruit for the additional work it had performed but had received no payment.

The city answered, inter alia, admitting in general the facts set forth above with reference to entering into the contract for the construction of the pumping station and service building, the completion of all construction on August 28,1978, at which time the city began to have the full use of the entire project but otherwise denied the claim of the plaintiff.

The case proceeded to trial and resulted in a verdict for the plaintiff against the city in the amount of $11,388.91 “in payment of services rendered as caused by the delay of the original contract (includes interest on the principal amount of $9,633.00 at an annual rate of 9%).” The judgment was in the amount of $11,388.91. *677 Plaintiff appeals. Held:

1. It is noted here that this case proceeded to trial based upon separate counts and seeking first a sum due plus interest by reason of a change order to the original contract. In addition, the plaintiff in a separate count sought the value of its work based upon quantum meruit. Another issue in the case was one in which the plaintiff sought interest on the retainage of $40,000 under the written contract which was not paid in accordance with the contract for more than a year after it was allegedly due. The jury awarded the sum of $11,388.91 in payment of services rendered “as caused by the delay of the original contract.” This award by the jury may have been under the so-called change order or it may have been rendered on the basis of quantum meruit. The jury also recited therein that it included interest on the principal amount of $9,633, “at an annual rate of 9 %.” We proceed to consideration of the sufficiency of the evidence as complained of in the enumerations of error based upon the above facts in this case:

(a) In DeKalb County v. Scruggs, 147 Ga. App. 711 (1), 712 (250 SE2d 159); and DeKalb County v. PMS Constr. Co., 148 Ga. App. 413, 414 (4), 419 (251 SE2d 334), reversed on other grounds in PMS Constr. Co. v. DeKalb County, 243 Ga. 870 (257 SE2d 285), s. c. 151 Ga. App. 63, 64 (258 SE2d 730), it has been held that a county as a unit of government may not be sued in quantum meruit for a governmental unit may be sued only when made so by statute, and when it deals with others it must be by written contract and not on a quantum meruit basis. However, it is noted here that in PMS Constr. Co. v. DeKalb County, 243 Ga.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lufthansa Systems Infratec GmbH v. Wi-Sky Inflight, Inc.
894 F. Supp. 2d 677 (E.D. Virginia, 2012)
Joseph Camacho Associates, Inc. v. Millard
315 S.E.2d 478 (Court of Appeals of Georgia, 1984)
City of Saint Marys v. Stottler Stagg & Associates, Inc.
292 S.E.2d 868 (Court of Appeals of Georgia, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
288 S.E.2d 98, 161 Ga. App. 675, 1982 Ga. App. LEXIS 1978, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barge-co-v-city-of-atlanta-gactapp-1982.