Bares v. Quincy Sanitary District

275 P.2d 827, 128 Cal. App. 2d 530, 1954 Cal. App. LEXIS 1502
CourtCalifornia Court of Appeal
DecidedNovember 4, 1954
DocketCiv. No. 8435
StatusPublished
Cited by1 cases

This text of 275 P.2d 827 (Bares v. Quincy Sanitary District) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bares v. Quincy Sanitary District, 275 P.2d 827, 128 Cal. App. 2d 530, 1954 Cal. App. LEXIS 1502 (Cal. Ct. App. 1954).

Opinion

VAN DYKE, P. J.

This action arises out of a contract under which appellant, a licensed general contractor, undertook to construct a sewage treatment plant for the respondent, Quincy Sanitary District. At the same time, but through other contractors, the district was constructing a sewage collection system.

The complaint contained four counts. The first was in common count form, alleging that appellant furnished materials and rendered services to respondent in “the sum of $141,614.60” and had been paid only $115,364. Recovery of the balance was prayed for. The second count pleaded a written contract to construct a sewage treatment plant and certain accessory installations. The plans, specifications and contract documents were incorporated by reference. It was alleged the work had been done and that certain extra services had been performed, so that the total thus earned amounted to $141,614.60, of which $115,364 had been paid. Recovery of the balance was asked. A third count repeated the entire second count and contained these additional allegations: That one Kennedy was the district engineer for the project and the agent of the district; that he had prepared the plans and specifications and working drawings and that in doing so he made surveys, drawings, cuts, profiles and estimates, but had negligently estimated the quantity of excavation required to be 2,000 cubic yards and the quantity of imported fill required to be 5,700 cubic yards, whereas the actual amount of excavation necessary was 4,752 cubic yards and the necessary amount of fill 9,954 cubic yards; that during the course of the work the appellant had discovered the error and called it to the attention of Kennedy who then ordered appellant to make the excavations and to provide the fill required for completion of the job, notwithstanding the fact that the amounts required exceeded the specifications and estimates; that appellant complied with the order of the engineer and on completion of the project rendered a statement for the extra yardage of excavation and fill at the prices plaintiff had under the written contract engaged to excavate and fill; that the amounts and prices were agreed to by respondent; [532]*532that the ordered excavation and fill computed at the said prices totaled $11,885. The fourth count contained these allegations: That on December 15, 1949, Kennedy had negligently and in violation of appellant’s rights under his contract ordered him to cease work on the job, which order he obeyed; that as a result of this interference and the onset of winter storms which prevented resumption of labor, appellant had been forced to install pumps to protect the installations already in place at a cost of $482; that he had suffered damage to his access road leading to the job site in the sum of $600 and had been unable for a considerable time to remove heavy equipment from the job for use elsewhere, so that he lost its rental value in the sum of $5,588.

To these pleadings respondent answered, asserting that appellant had performed services and furnished materials under his contract to the value of $129,729.60, and no more, and that he had been paid in full. The allegations as to extra quantities of excavation and fill, damage negligently caused by the engineer and wrongful interference were all denied.

The trial court, sitting without a jury, heard the cause and rendered judgment in favor of respondent district. Specifically, it found that there had been no extra services; that though Kennedy had prepared plans and specifications for the work and had made surveys, drawings, cuts, profiles and estimates, yet appellant had not, in submitting his bid, relied thereon; that on the contrary appellant had examined the location before bidding, had familiarized himself with the plans, specifications and local conditions at the site and, having checked the plans and specifications, surveys, drawings, cuts, profiles and estimates had assumed all responsibility for any errors or omissions contained therein; that Kennedy had not been negligent in estimating the quantities of excavation and fill required and that in point of fact the estimates of 2,000 cubic yards of excavation and 5,700 yards of imported fill were the amounts reasonably required for the job; that the plaintiff had actually excavated the additional quantities alleged and had put in place the additional quantities of fill; that these additional quantities were necessitated by reason of the negligent manner in which appellant did the work; that there was no error in respect to either excavation or 'fill required by the contract; that appellant had not called Kennedy’s attention to any such error; that Kennedy had not ordered any more ex[533]*533cavation or fill than the contract itself required and that respondent had justly refused to pay appellant’s claim for any extra quantities. As to the work stoppage, the court found it had been ordered by the district’s engineer on account of the incidence of winter storms and freezing temperatures and that the cessation order was in line with proper engineering practices under the circumstances, was made with the consent and approval of appellant and hence that respondent had incurred no obligations to appellant for any extra costs resulting from the stoppage.

At the beginning of the trial, counsel for the appellant informed the court that they wanted to amend the complaint to bring into the issues a claim that Kennedy had negligently and also fraudulently concealed from appellant certain conditions at the site of the work and through such wrongful acts had, after appellant had been declared the low bidder, induced him to consent to a change in the location of the plant to be built; that Kennedy had represented the new site to be more advantageous, both to the district and to appellant, and that, relying upon these representations and being ignorant of the concealments, appellant had accepted the site change and agreed to perform the contract for the price bid; that in truth the new site was so affected by adverse water conditions under the surface that in order to construct it at all appellant had to install an expensive well point system to rid the site of water and had incurred in so doing extra expense exceeding $21,000. Counsel also asked leave to bring into the issues a claim that during the construction of the work Kennedy had relocated a sewer line being constructed by the other prime contractor so that it ran under a sedimentation tank that appellant was building, causing him to idle a part of his ereAV during the period when he had to cease work on the tank and contiguous units to enable Kennedy to correct his error by having the other contractor reconstruct the line and bypass the tank, all of which caused further damage to appellant. The trial court ruled that the complaint could not at that time be amended, but that appellant’s proof as to these issues would be taken and if, in the opinion of the court, at the close they had made a case on these matters, then the court would grant leave to appellant to amend to conform to such proof. Motion to so amend made at the close of the evidence, however, was denied by the trial court.

[534]*534Appellant puts the questions involved as follows :

“Is plaintiff contractor who was awarded a job which consisted of a lump sum for specified general work and also a unit price figure per cubic yard for dirt excavation and fill, for which latter the quantities were only estimated, entitled to recover:
‘11.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bohman v. Berg
356 P.2d 185 (California Supreme Court, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
275 P.2d 827, 128 Cal. App. 2d 530, 1954 Cal. App. LEXIS 1502, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bares-v-quincy-sanitary-district-calctapp-1954.