Bardwell v. Ziegler

28 P. 360, 3 Wash. 34, 1891 Wash. LEXIS 117
CourtWashington Supreme Court
DecidedOctober 29, 1891
DocketNo. 304
StatusPublished
Cited by11 cases

This text of 28 P. 360 (Bardwell v. Ziegler) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bardwell v. Ziegler, 28 P. 360, 3 Wash. 34, 1891 Wash. LEXIS 117 (Wash. 1891).

Opinions

The opinion of the court was delivered by

Dunbar, J.

By written contract between the parties; plaintiffs agreed to furnish defendant certain materials to be used in finishing a building in Spokane; certain of the materials to be furnished on board the cars at Minneapolis, on or before the 15th day of December, 1889, and certain other materials, to wit, the doors and paneled wainscoting and stairs, on or before the first day of January, 1890, and this provision occurs in the contract:

“And the second party, for and in consideration of the first party’s completely and faithfully executing the aforesaid work, and furnishing all the material therefor, so as to fully cany out this contract and design, according to its true spirit, meaning and intent, and by and at the times mentioned, and to the full and complete satisfaction of H. Preusse, superintendent, does hereby agree to pay,” etc., etc.

It is provided in the contract that the materials shall he furnished according to the plans and specifications and drawings, which are declared to be a part of the contract. The [38]*38contract provides for damages in case of the failure of the plaintiffs to furnish the material by the time specified. The doors, wainscoting and stairs were not delivered for some six weeks after the time specified, and by reason of said delay defendant claims damages and seeks to recoup upon plaintiffs in the sum of fifteen hundred dollars. Plaintiffs in reply claim that the failure was caused by the negligence of the defendant in not having the building in such a state of progression that the measurements for the stairs could be taken, and that the measurements could not be taken from the plans and specifications, but must be made by actual, physical measurement of the house itself. Plaintiffs offered evidence tending to show this state of facts, and to show that under such contracts the general custom was to take actual measurements, and that such contracts were entered into with reference to such general custom. The introduction of this testimony was objected to by defendant, and the objection was sustained by the court. Among the questions asked and rejected by the court, was the following:

“Q. Now I will ask you to state, Mr. Carter, whether or not it was possible to take the measurements requisite and necessary for the manufacture of the panel, wainscoting and stair work from the plans and specifications ?”

And also the following question:

“Q. I will ask you whether or not there is any general custom, in a contract of this kind, which establishes the fact or understanding in the business that certain measurements must be taken before work can be done, even where the contract provides it must be done according to plans and specifications ?

To the refusal of the court to allow this testimony to be introduced, the plaintiffs duly excepted, and assign it as error here. "We think the court erred in refusing to allow this testimony. It could not be introduced for the purpose of contradicting the contract, or to interpret it inconsistently with its language; but of explaining its meaning in the [39]*39light of general custom, with reference to which the parties would be supposed to contract; and on the further principle that a man will not be presumed to intentionally contract to do a thing that it is impossible for him to do.

As we read the cases cited by the respondent, none of them go to that extent. In Davis v. Galloupe, 111 Mass. 121, the plaintiffs, stone cutters, agreed in writing with defendant to furnish stone for his building according to the plans and specifications of an architect, and to do all the fitting and rebating necessary. Wooden patterns were necessary' for cutting the stone under the plans, and the plaintiffs procured and paid for them without asking the defendant or the architect to furnish them. Held, in an action to recover the amount paid for these patterns, that evidence of the usage of stone cutters in cutting stone for a building to purchase such patterns and recover the cost from the owner of the building was inadmissible. But it seems to us there is no parallel between that case and the one at bar. Here it was attempted to show that it was impossible for plaintiffs to comply with the contract without an actual measurement; that a general custom grew out of that fact, and that the parties contracted with reference to that fact. There the contract could be and was performed; and the court made that plain distinction, and inferentially announced the doctrine, that if the performance of the contract had been impossible without the patterns having been furnished by the defendant, the custom might have been shown, by the use of this significant language:

“As the plaintiffs actually prepared the patterns, it is obvious that it was not necessary that the defendant should furnish them to enable the plaintiffs to do the work.”

Partridge v. Insurance Co., 15 Wall. 573, enunciates the doctrine that the custom cannot be proven to vary or contradict the well expressed intention of the parties. In Sawtelle v. Drew, 122 Mass. 228, all that was decided was, that [40]*40evidence to prove a custom was inadmissible in the absence of evidence that the plaintiff knew of such custom. On the other hand, the court in its opinion says:

“A custom, within the meaning of the law, if general, is incorporated into and becomes a part of every contract to which it is applicable; if local, of every contract made by parties having knowledge of, or bound to know, its existence.”

In Sanford v. Rawlings, 43 Ill. 92, a workman in marble had entered into a written contract to erect a monument, and a workman was called to testify “what in the trade of a marble dealer is meant by a contract to erect a monument,” and the court very properly said that—

“ It was wholly unnecessary to call a worker in marble to prove the legal import of a contract to erect a monument, or what would be understood by such a contract in the trade, because there could be no dispute as to its meaning. The law would attach to this language a precise signification.”

And so with the other cases cited by respondent. On a careful examination we do not think they go so far as to exclude the testimony offered in this case. In Stewart v. Keteltas, 36 N. Y. 388, a case on a level with the one at bar, the plaintiffs having contracted to erect and furnish a new building therein referred to, agreeably to the drawings and specifications made by defendant’s architect and signed by the parties, the court says:

“An objection to the offering of any excuse by the plaintiff for not performing his part of the contract within the time stipulated is properly overruled, and that under such contract, where the work to be performed by the plaintiff could not be performed until other work was done by defendant or his employes, the failure to have such preliminary work completed in season to enable the plaintiff to complete his within the time limited by the contract is a sufficient excuse for the plaintiff for not completing the work within the time.”

[41]*41The very object of one of the questions objected to in the case at bar was to show that the plaintiff’s work could not

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Of Washington v. Arthur Seth
Court of Appeals of Washington, 2013
State v. Boss
144 Wash. App. 878 (Court of Appeals of Washington, 2008)
State v. Baxter
134 Wash. App. 587 (Court of Appeals of Washington, 2006)
State v. Zimmerman
121 P.3d 1216 (Court of Appeals of Washington, 2005)
Kerr v. Cochran
396 P.2d 642 (Washington Supreme Court, 1964)
Pfeiffer v. State
278 P. 63 (Arizona Supreme Court, 1929)
Cormier v. Martin Lumber Co.
167 P. 1105 (Washington Supreme Court, 1917)
French v. Seattle Traction Co.
66 P. 404 (Washington Supreme Court, 1901)

Cite This Page — Counsel Stack

Bluebook (online)
28 P. 360, 3 Wash. 34, 1891 Wash. LEXIS 117, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bardwell-v-ziegler-wash-1891.