Barcus v. Hannibal, Ralls County & Paris Plank Road Co.

26 Mo. 102
CourtSupreme Court of Missouri
DecidedOctober 15, 1857
StatusPublished
Cited by6 cases

This text of 26 Mo. 102 (Barcus v. Hannibal, Ralls County & Paris Plank Road Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barcus v. Hannibal, Ralls County & Paris Plank Road Co., 26 Mo. 102 (Mo. 1857).

Opinion

Scott, Judge,

delivered the opinion of the court.

Justice requires that the plaintiff should be paid the full value of his work. As he agreed to build a road in a complete and workmanlike manner for $2,300 a mile, if he failed to make the road as required by his agreement, he can only expect to receive as much as the road built by him is worth, considering that if it had been built in all respects in pursuance to the contract it would have been worth $2,300 per mile. To escape from this equitable mode of determining the controversy, the plaintiff has endeavored to set up an estimate or estimates by the engineer of the defects in the construction of the work, which he maintains are conclusive between the parties to this suit. It was certainly competent for the defendant to contract that the estimates of the deficiencies in the execution of the work should be made by an engineer, and that his estimates should be binding on the parties interested. As the plaintiff sets up this defence in order to avoid the rule dictated by natural justice for the adjustment of this dispute, he should show, by evidence that would satisfy a jury, that there was such an understanding between the parties. There is no hardship in holding the plaintiff to this proof, as in the event of his failure to make it he is still entitled to the value of the work performed by him estimated according to the terms of the contract, inasmuch as the defendant has taken and used the road.

By the contract it was agreed that the work should be completed by the first of November, 1853. In December following the contractor called on the engineer to examine and receive the work. Upon an examination of it the engineer in[105]*105formed tbe contractor that be bad not complied with his contract and that be should not receive the road. Tbe contractor then made tbe proposition to tbe engineer that an estimate of tbe deficiencies in tbe performance of tbe work should be made and deducted from tbe contract price for building tbe road. ■ After this two estimates of tbe deficiencies in tbe construction of tbe work were made by tbe engineer and submitted to tbe company. As by tbe terms of tbe contract tbe engineer was only authorized to make an estimate of tbe whole work when it was completed, and as be refused to receive tbe work on tbe ground the contract bad not been complied with, bis duty in relation to the contract thereupon ceased, and it was not competent for him to enter into any arrangement with tbe contractor in relation to tbe manner in which tbe deficiencies of construction should be made good to the company.

Tbe parties to tbe contract might have agreed that the engineer’s report should determine the amount of deductions to be made from tbe contract price of tbe work, but in tbe absence of any such agreement we do not see bow tbe engineer could bind tbe company, as there was no power for any such purpose in the contract. Nor do we conceive that there is any thing in the record which shows that tbe company ever consented to tbe proposition made by the contractor. We do not see bow tbe presence of tbe directors in their unofficial capacity on tbe day tbe proposition was made can be considered as any evidence of their assent or the assent of tbe company to tbe proposition. They were not so organized as to do any act binding on tbe corporation; nor did they attempt so to do. Nor do we see bow the subsequent action of tbe board on tbe estimates could bind tbe company, as that action ultimately resulted in a determination not to abide by them. The proposition of tbe contractor, as stated by tbe engineer, did not specify that the estimate should be made by the engineer. Tbe fact that tbe board did, by a resolution on tbe 30th of December, 1853, call upon tbe engineer for a final estimate of tbe work done by the contractor, is scarcely [106]*106any evidence of an agreement between the board and the contractor. As the engineer was an agent for the company, employed at a salary, what was more natural than that they should call upon him for information in regard to the manner in which the work had been performed. The action of the board on the estimates submitted by the engineer is no evidence of their concurrence in the reports; so far from it, they revised and amended them, showing thereby that they did not regard themselves under any contract in relation to the estimates. Indeed, as has been before stated, the contract, as proved by plaintiff’s witness, did not stipulate that the estimate of deficiencies should be made by the engineer.

We have said that the contract did not authorize the engineer to make any arrangement with the contractor by which any deficiency in the work might be made good to the company. The instruction given by the court on this subject seems to base the binding effect of the engineer’s estimate on a supposed agreement made between him and the contractor in December, 1853, and its subsequent ratification by the board. The contract provides that the road shall be built according to the engineer’s specifications and plans, and to be governed by the engineer in all things relating to the work. A subsequent clause, after providing for monthly estimates of the work done with a view to making payment for it, stipulates that within thirty days after the road is completed an estimate of all the work done shall be made and the amount due the contractor shall be paid. These are all the provisions in the contract relative to the manner of its performance ; and it will be seen that they confer no authority on the engineer in relation to the making of estimates in the event of a misunderstanding between the parties arising out of a failure on the part of the contractor to perform his work according to the specifications annexed to the contract.

We do not well see how the instruction relative to the estimates, even admitting that the company is bound by them, can be sustained. It seems to be inconsistent with itself. The phrase “ and that the company afterwards adopted those [107]*107estimates as a basis of settlement,” taken without reference to the evidence in the cause and the agreement of counsel appended to the bill of exceptions, would seem to intimate that the board adopted the report of the engineer as made, whereas the truth is they amended and corrected it; thus showing, if their act is any evidence, that they did not consider themselves bound by his report, as they assumed the power of correcting it. Thus the instruction would have the jury imply the assent of the company to the engineer’s report from an act which shows their dissent from it. As has been observed, it was natural, under the circumstances, that the board should call upon their engineer for information as to the deficiencies in the construction of the road; and because they did so, and afterwards adopted his report with corrections as a basis for an adjustment of the controversy, it is not easy to see how such conduct furnishes any evidence that they assented to a contract or proposition made to the engineer relative to the ascertainment of the deficiencies in the work, when that conduct shows that they did not assent to it.

What has been previously stated applies to the last portion of the work. Those portions of the work which were received under resolutions of the board, and the deficiencies of which were agreed upon and estimated by the parties, can not be re-examined unless fraud in its execution is alleged and proved. If the work was fraudulently executed or its defects in any manner disguised or concealed, the plaintiff is liable for the consequences of such fraud or concealment, although he had no knowledge of it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robertson v. State
142 S.W. 533 (Court of Criminal Appeals of Texas, 1911)
Cann v. Rector of Church of the Redeemer
85 S.W. 994 (Missouri Court of Appeals, 1905)
Willis v. Stevens
24 Mo. App. 494 (Missouri Court of Appeals, 1887)
City of Logansport v. Justice
74 Ind. 378 (Indiana Supreme Court, 1881)
State ex rel. Board of Education v. Tiedemann
69 Mo. 515 (Supreme Court of Missouri, 1879)

Cite This Page — Counsel Stack

Bluebook (online)
26 Mo. 102, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barcus-v-hannibal-ralls-county-paris-plank-road-co-mo-1857.