Barber Asphalt Paving Co. v. Northern Ohio Traction & Light Co.

202 F. 817, 121 C.C.A. 125, 1913 U.S. App. LEXIS 1066
CourtCourt of Appeals for the Sixth Circuit
DecidedMarch 4, 1913
DocketNo. 2,243
StatusPublished
Cited by4 cases

This text of 202 F. 817 (Barber Asphalt Paving Co. v. Northern Ohio Traction & Light Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barber Asphalt Paving Co. v. Northern Ohio Traction & Light Co., 202 F. 817, 121 C.C.A. 125, 1913 U.S. App. LEXIS 1066 (6th Cir. 1913).

Opinion

KNAPPEN, Circuit Judge.

In 1897 the city of Akron, hereafter called the city, entered into contract with plaintiff in error, hereafter called the Paving Company, for the improvement by the latter of a portion of Howard street in Akron, from curb to curb, with stone curbing and asphalt pavement, under a guaranty that the pavement should at all times during the period of 10 years be “in as perfect condition as the day it was laid,” and that at the end of the period the pavement should “show 75 per cent, of the original thickness called for in the contract.” There was at the time a double track street rail[818]*818way extending through this portion of Howard street, the railroad then being operated by the predecessor of defendant in error, hereafter styled the Traction Company, under a franchise which required the railway company and its successors and assigns to “in all instances, construct, operate and maintain, and keep in repair its said railroad.” In 1899, which was two years after the paving contract was niade, the city granted a further franchise to the Traction Company’s predecessor, which provided that the railway tracks should be “so constructed as that the- upper surface of the rails thereof at all times should conform to the grade of the streets in which the same were, laid.” The paving was completed in 1897, and the Paving Company seems to have complied with its contract to keep the pavement in repair, making such repairs each year, until and including the year 1903. In 1904 it refused to make further repairs, claiming that those demanded by the city were induced by breakages of the pavement caused by defects in the foundations under the street car tracks, resulting from the failure of the street railway company to keep its road in repair; it being alleged that, after, the paving was done and with the city’s permission, cars had been used which were too heavy for the track foundations. The city accordingly repaired the pavement, and brought, suit against the Paving Company for reimbursement. This court held on review that the Paving Company was not relieved from its guaranty by the fact that the pavement was broken because of insufficient railway track foundations, nor because of the renewal of the grant to the railway company, nor because heavier cars were used by the latter; but that all these facts must be presumed to have been within the contemplation of the parties when the paving contract was made. 171 Fed. 29, 96 C. C. A. 271. The city finally recovered of the Paving Company upwards of $7,000. Thereupon the Paving Company paid the judgment, and brought this suit against the Traction Company for reimbursement.

The petition in the instant suit alleged the franchise obligation existing when the paving contract was made to keep the street railway in repair; also the requirement of the 1899 franchise that the upper surface of the rails at all times conform to the grade of the street, and the Traction Company’s assumption of those obligations; set up the paving contract of 1897, alleged that “as a part of said contract this plaintiff agreed with said city of Akron to insure the maintenance of said asphalt pavement for a period of 10 years from the date of its construction, and furthermore promised, in the event said pavement should become out of repair during said period, to make the necessary repairs to said pavement so as to keep the same in a good condition of repair during all of said time,” and that at the time the paving contract was made plaintiff “was aware of the obligation imposed by said franchises upon said street railway company with respect to the maintenance and repair of its system of street railway,” and that plaintiff “entered into said contract with said city * * * relying upon said street railway company and its successors to keep and perform its obligations in the premises.” It will be noted that the general agreement to keep the street railway in repair was the only franchise obligation actually existing when the paving contract was made. The [819]*819petition further alleged the failure of the Traction Company to comply with its duty to keep the railway in repair, in that “the foundation, ties and rails of said street railway were of insufficient construction for the street railway traffic upon said street; that said rails were permitted to become loose and that said ties and foundation were insufficient to support the same”; that the excessive vibration of the rails and ties caused the top of the rails to sink below the grade of the street; that the asphalt surface of the pavement near the rails and ties was. thereby broken, permitting the accumulation of rainwater along the rails, and its infiltration through the binder course of the pavement, thus permitting the freezing of and injury to the pavement. The Traction Company or its predecessor was alleged to be primarily liable to the city for such damage, and the Paving Company to be secondarily liable to the city for the repairs. It was asserted that the plaintiff, having been required to make the repairs, “should now be subrogated to-the rights of the city of Akron as against the defendant herein.” The petition was demurred to, the causes which are pertinent here being-(a) that the action was barred by the four-year statute of limitations, and (b) that the facts stated constituted no cause of action against the Traction Company. The demurrer was sustained and the suit dismissed.

The plaintiff plants its action squarely upon the ground of subrogation alone; and upon the theory stated that the Traction Company was “primarily liable” to the city for the injury to the pavement caused by that company’s failure to properly maintain its tracks; that the plaintiff’s obligation to the city was “secondary” only to that of the Traction Company; that the obligation of the latter to keep its tracks in repair was, as between it and the Paving Company, superior to the. latter’s obligation to keep the pavement in repair; that plaintiff was thus in legal effect merely a guarantor or insurer of the performance by the Traction Company of its obligation to the city, its relation being strictly analogous to that of an insurer of goods during transportation in reliance upon the contract of the carrier to safely carry the goods,, or that of a tenant under obligation to repair as against third persons whose negligence makes such repairs necessary; that the Paving Company having satisfied the city’s demand, on account of an injury occasioned, as alleged, exclusively by the misconduct of the Traction Company, the, Paving Company is entitled to such remedies as the city would have had against the Traction Company, had it elected to sue that company.

[1] We may dismiss all question of defendant’s liability to plaintiff for a tortious injury to the pavement not based upon contract between the Traction Company and the city, for the reason, if for no other, that any action for tort which the city may have had was barred by the four-year statute of limitations. Gen. Code of Ohio, § 11224.

[2] Plaintiff’s alleged right of subrogation is thus limited to the enforcement of the Traction Company’s contract obligations to the city. If it be conceded that the Paving Company’s obligation to keep the pavement in repair was merely secondary to that of the Traction Company to keep its tracks in repair — in other words, that the former’s obligation was only one of insurance or indemnity with respect to the-[820]*820obligation of the latter — the right of subrogation would seem clear. But we think the premises relied upon are fatally unsound.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meyer v. Levy
169 So. 2d 339 (District Court of Appeal of Florida, 1964)
Pathe Exchange, Inc. v. Bray Pictures Corp.
231 A.D. 465 (Appellate Division of the Supreme Court of New York, 1931)
Sloat-Darragh Co. v. General Coal Co.
276 F. 502 (Sixth Circuit, 1921)
Atchison, T. & S. F. Ry. Co. v. United States
243 F. 114 (Eighth Circuit, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
202 F. 817, 121 C.C.A. 125, 1913 U.S. App. LEXIS 1066, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barber-asphalt-paving-co-v-northern-ohio-traction-light-co-ca6-1913.