BARABAY PROP. HOLD. CORP. v. Boh Bros. Const. Co., LLC

991 So. 2d 74, 2008 WL 1930404
CourtLouisiana Court of Appeal
DecidedMay 2, 2008
Docket2007 CA 2005
StatusPublished
Cited by8 cases

This text of 991 So. 2d 74 (BARABAY PROP. HOLD. CORP. v. Boh Bros. Const. Co., LLC) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BARABAY PROP. HOLD. CORP. v. Boh Bros. Const. Co., LLC, 991 So. 2d 74, 2008 WL 1930404 (La. Ct. App. 2008).

Opinion

991 So.2d 74 (2008)

BARABAY PROPERTY HOLDING CORPORATION
v.
BOH BROTHERS CONSTRUCTION CO., L.L.C. d/b/a Boh Brothers Construction.

No. 2007 CA 2005.

Court of Appeal of Louisiana, First Circuit.

May 2, 2008.

*76 Michael D. Ferachi, Kyle A. Ferachi, Baton Rouge, LA, for Plaintiff/Appellee Barabay Property Holding Corporation.

Martin A. Stern, William D. Shea, Lauren J. Delery, Baton Rouge, LA, for Defendant/Appellant Boh Brothers Construction Co., L.L.C., d/b/a Boh Brothers Construction.

Before GAIDRY, McDONALD, and McCLENDON, JJ.

GAIDRY, J.

A contractor appeals a judgment against it for damages arising from its removal and disposal of excavated soil from a landowner's property during the course of a public construction project. For the following reasons, we affirm the judgment.

FACTUAL BACKGROUND AND PROCEDURAL HISTORY

The plaintiff, Barabay Property Holding Corporation (Barabay), owns approximately 4,000 acres of land in Jefferson Parish. The property was subject to a personal servitude for underground public utilities in favor of Jefferson Parish, granted by Barabay in 1997. The servitude contained the following language:

Grantee [Jefferson Parish] promptly shall remove all left over material and all stakes or posts which may have been put into the ground, and generally, restore the surface of the land to nearly its original condition as may be practical.

In 1999, Jefferson Parish solicited bids for the construction of an underground water line that would pass through the servitude on Barabay's property. Boh Brothers was ultimately awarded the contract as the lowest bidder. Construction on the water line project proceeded according to plans prepared by the engineering firm of Camp, Dresser & McKee, Inc. As the water line was being placed underground, excavation was necessary, and a large amount of soil was excavated and later removed from the site by Boh Brothers. The contract between Jefferson Parish and Boh Brothers provided:

It shall be the contractor's responsibility to haul and stack all designated salvageable material at area designated by authorized representative. (No direct payment.) Materials not designated to be salvaged shall be disposed of off site unless otherwise directed by engineers. (No direct payment)

By resolution adopted on January 10, 2001, the Jefferson Parish Council formally accepted the project as complete.

Barabay instituted this litigation by filing a petition for damages against Boh Brothers in East Baton Rouge Parish on January 12, 2001. Boh Brothers answered the petition, denying liability and asserting the affirmative defenses of statutory immunity under La. R.S. 9:2771, its limited liability based upon surety status under La. R.S. 9:2773, Barabay's contributory negligence, and Barabay's failure to mitigate its damages.

*77 The parties proceeded to undertake discovery, and the next significant pleading was a motion for summary judgment by Boh Brothers, filed on April 20, 2004, seeking the dismissal of Barabay's action based upon Boh Brothers's statutory immunity under La. R.S. 9:2771. The motion was heard on November 8, 2004, and was denied by the trial court by judgment signed on December 10, 2004.

Barabay filed a request for a status conference on December 15, 2004. The parties subsequently submitted a joint pretrial statement and order in connection with the pretrial conference held on April 12, 2005. The trial on the merits was scheduled for June 27, 2007.

On May 25, 2007, Boh Brothers filed a pretrial brief, in which it addressed the issue of its claimed statutory immunity, the nature of the damages claimed by Barabay, and an alternate defense of "equitable estoppel" in the event the trial court rejected its defense of statutory immunity. On June 19, 2007, Barabay filed a motion in limine, seeking to preclude Boh Brothers from asserting the affirmative defense of estoppel and from offering any testimony or other evidence in support of that defense.

Barabay's motion in limine was set for hearing on the morning of the trial on the merits. Following a conference in chambers, the trial court ruled in favor of Barabay, granting its motion in limine. The trial on the merits then proceeded. At the conclusion of Barabay's presentation of evidence, Boh Brothers moved for an involuntary dismissal of Barabay's cause of action, on the grounds that no evidence was introduced to prove that Boh Brothers deviated from the project plans and specifications, and thus it was immune from liability under La. R.S. 9:2771. The trial court denied its motion, ruling that La. R.S. 9:2771 did not apply under the circumstances.

At the conclusion of the trial, the trial court stated that it would rule in favor of Barabay, finding Boh Brothers liable for the sum of $58,020.00, representing the value of approximately 5,802 cubic yards of excavated soil removed from Barabay's property. Its judgment reflecting that ruling was signed on July 6, 2007. Boh Brothers now appeals.

ASSIGNMENTS OF ERROR

Boh Brothers contends that the trial court committed error in the following respects:

1. The trial court erred by refusing to enlarge the pleadings to permit Boh Brothers to offer estoppel as a defense to plaintiff's claims.
2. The trial court erred in concluding that Boh Brothers was not entitled to statutory contractor immunity, even though it constructed the water line in compliance with the plans provided to it by the Project's engineers.
3. The trial court's conclusion that Boh Brothers was liable for the removal of the soil was manifest error because Barabay offered no proof of Boh Brothers' liability.

DISCUSSION

The Affirmative Defense of Estoppel

Estoppel is an affirmative defense that must be affirmatively pleaded in a defendant's answer. See La. C.C.P. art. 1005. Louisiana Code of Civil Procedure article 1154 provides:

When issues not raised by the pleadings are tried by express or implied consent of the parties, they shall be treated in all respects as if they had been raised by the pleading. Such *78 amendment of the pleadings as may be necessary to cause them to conform to the evidence and to raise these issues may be made upon motion of any party at any time, even after judgment; but failure to so amend does not affect the result of the trial of these issues. If evidence is objected to at the trial on the ground that it is not within the issues made by the pleadings, the court may allow the pleadings to be amended and shall do so freely when the presentation of the merits of the action will be subserved thereby, and the objecting party fails to satisfy the court that the admission of such evidence would prejudice him in maintaining his action or defense on the merits. The court may grant a continuance to enable the objecting party to meet such evidence.

A trial court has great discretion to admit or to disallow evidence subject to an objection based upon the scope of the issues and pleadings and to determine whether evidence is encompassed by the general issues raised by the pleadings. Muscarello v. Ayo, 93-2081, pp. 4-5 (La. App. 1st Cir.10/7/94), 644 So.2d 846, 849. It has likewise been generally recognized that a trial court has much discretion under La. C.C.P. art. 1154 to allow a party to amend his pleadings. Id., 93-2081 at p. 5, 644 So.2d at 849.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
991 So. 2d 74, 2008 WL 1930404, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barabay-prop-hold-corp-v-boh-bros-const-co-llc-lactapp-2008.