Bankers Surety Co. v. Jefferson Realty Co.

137 S.W. 224, 143 Ky. 549, 1911 Ky. LEXIS 484
CourtCourt of Appeals of Kentucky
DecidedMay 9, 1911
StatusPublished
Cited by2 cases

This text of 137 S.W. 224 (Bankers Surety Co. v. Jefferson Realty Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bankers Surety Co. v. Jefferson Realty Co., 137 S.W. 224, 143 Ky. 549, 1911 Ky. LEXIS 484 (Ky. Ct. App. 1911).

Opinion

Opinion op the Coukt by

Judge Lassing

Affirming.

The Jefferson Bealty Company entered into a con- , tract with Herman Probst, an independent contractor, by wbicb lie agreed to erect the building on Fourth street, in Louisville, Kentucky, known as the Paul Jones Bnild-ing. The contract, among other things, provided that he • would furnish:

[550]*550“All materials and perform all the work for the erection, construction and completion of excavation, common concrete,- armored concrete, brick masonry, cut stone work, tile partitions, sheet metal and roofing, structural steel and cast iron, ornamental steel and cast iron, carpenter and wood interior finish, plumbing, interior marble slate and mosaic work, plastering and painting * * * as shown on the drawings and described in the plans and specifications prepared by Prank M. Andrews» architect.”

The contract .further provides:

“Said contractor agrees to protect and save harmless the owners from any loss, cost or damage to them on account of any damage or injury to third persons, or to property, -occasioned by the acts of said contractor, his servants, agents, employes, or any sub-contractors, or his servants, agents or employes.”

Under the contract it was stipulated that the building should be completed within 30 1-2 months from November 8, 1905, and for failure to comply with this provision the contractor agreed to pay as a penalty liquidated damages at the rate of $200' per day for each day in excess of 10 1-2 months required by him to complete the building. The contract price was $309,954, to be paid in installments upon estimates made by the architect as the work progressed. Ten per cent, of these estimates was to be reserved until the contract was completed. The contract also contained a provision protecting the owner against damage to third persons and liens of material-men and mechanics. For the faithful performance of his contract according to its terms the contractor executed' a bond in the sum of $155,000 with the Bankers Surety Company as surety.

The contract was not completed within the time limit. It was charged that the work was not done according to contract, and a dispute arose between Probst and the owners as to the balance due him; many sub-contractors who had not been paid filed mechanics liens against the property; several suits had been brought against the Jefferson Realty Company and Probst for damages growing out of alleged negligent acts on the part of Probst in the conduct of the work, and still others were threatened. With their affairs in this condition, representatives of the Jefferson Realty Company, Probst, and the Surety Company, undertook [551]*551to adjust and compromise their differences. The subcontractors were claiming something like $52,000, Probst was claiming a balance of $63,000, while the Realty Company claimed that they owed only $43,000, which was subject to a reduction on account of counterclaim, amounting to $14,000, and liquidated damages for failure to complete the building within the required time amounting to $17,000; so that the Realty Company was in fact admitting an indebtedness to Probst of but $12,-000, in round numbers. The negotiations looking to a compromise, settlement and adjustment of their differences were carried on through a period of eighteen months. Every phase of the questions in dispute was considered and discussed. Propositions and counter-propositions were made from time to time, until' finally, on June 18, 1909, the following compromise agreement and settlement was entered into between them;

“This agreement, between the Jefferson Realty Company hereinafter referred to as the Realty Company, and Herman Probst, witnesseth as follows:
“There has been a controversy between said parties as to their mutual rights and liabilities growing out of the construction of the Paul Jones Building in the city of Louisville, Kentucky, which has been compromised as herein shown.
“The amount due said Probst from the said Realty Company, on the face of the accounts, without reference to claims for damages, in $43,205.91. It has been agreed that there shall be deducted from this amount the sum of $7,250 in full settlement and satisfaction of all claims which said Realty Company has against said Probst for damages, except as hereafter stated, thus leaving due said Probst from the said Realty Company the sum of $35,955.91.
“2. Said Probst will proceed to reduce his indebtedness to his sub-contractors until it reaches said sum of $35,955.91 or less, and, as provided in the contract between the said Realty Company and Probst. will furnish satisfactory evidence to the said Realty Company that he has so reduced said indebtedness. Thereupon said realty company will honor and pay drafts upon it by said Probst in favor of the remaining unpaid sub-contractors in all not exceeding the sum of $35,955.91, until all of them are paid in full; and if then there be any balance of said sum remaining, the said realty company will pay [552]*552same to said Probst, upon production of satisfactory evidence that all of said sub-contractors have been paid. ■
“3. Said Probst will give a bond with a good and solvent surety company as surety to save said realty company harmless against any damage to which, within the period of two years from June 1, 1908, said realty company may be subjected because of any defects in the plumbing, and to refund to it any costs to which, within said period, it may be subjected in repairing such defects.
“4. Said Probst will give a bond with some good and solvent surety company as surety to save said realty company harmless against any cost or damage which may be adjudged against it in any of the suits by the Louisville Gras Company, Galvin & Pox, Tischendorf-Chreste Lumber Company, E. N. Button, Geo. W. Hines-ley, Thos. Craig, Claud Rickets, Sallie Johnson, Elizabeth Lytle and Joseph Grider, or others, now pending, or that may hereafter be brought against it, seeking to recover against it for any matter which said Probst indemnified it against in the said building contract between them; and he will defend such suits at his- cost.
‘ ‘ 5. The litigation in the suit of Grainger & Company' v. Jefferson Realty Company, and others, including Probst, shall continue as to any claims which said Probst desires to contest; but he will save the realty company harmless from any costs or judgment in that suit, except such as have heretofore been paid by the said realty company. Said realty company makes no claim against said Probst for such costs as it has already paid.
“6. This agreement does not release the Bankers Surety Company on the aforesaid building contract, and the bonds proposed to be executed are additional to its security as surety therein.
“7. There is a claim by said Probst against said realty company of about $578 for the work of removing certain debris from the ground upon which the Paul Jones Building was erected, being work done by said Probst, which Galvin & Pox had originally contracted with the said realty company to do. Galvin & Pox are also making a claim against the said realty company for compensation on account of this work. And this compromise does not affect the claim of Probst on account of the work mentioned in this paragraph.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fidelity Casualty Co. of N.Y. v. Mauney
116 S.W.2d 960 (Court of Appeals of Kentucky (pre-1976), 1938)

Cite This Page — Counsel Stack

Bluebook (online)
137 S.W. 224, 143 Ky. 549, 1911 Ky. LEXIS 484, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bankers-surety-co-v-jefferson-realty-co-kyctapp-1911.