Bankers' Surety Co. v. Elkhorn River Drainage Dist.

214 F. 342, 130 C.C.A. 650, 1914 U.S. App. LEXIS 1146
CourtCourt of Appeals for the Eighth Circuit
DecidedApril 20, 1914
DocketNo. 4032
StatusPublished
Cited by4 cases

This text of 214 F. 342 (Bankers' Surety Co. v. Elkhorn River Drainage Dist.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bankers' Surety Co. v. Elkhorn River Drainage Dist., 214 F. 342, 130 C.C.A. 650, 1914 U.S. App. LEXIS 1146 (8th Cir. 1914).

Opinion

RINER, District Judge.

This was ah action brought by' the Elk-horn River Drainage District, defendant in error, against the Bankers’ Surety Company, plaintiff in error, upon a bond given to secure the performance of a contract theretofore entered into 'between the Elk-horn River Drainage District and the Standard Drainage Company for .the construction of certain cut-offs along the course of the Elkhorn river, in Dodge and Washington counties, Neb., for the purpose of straightening it and facilitating the passage of water down that stream. For convenience the Elkhorn River Drainage District will be hereafter designated the “district,” the Bankers’ Surety Company the “surety company," and the Standard Drainage Company the “drainage company.” .

A trial was had in the district court resulting in a judgment in favor of the district against the surety company for the sum of $14,-850, and this is a writ of error to reverse that judgment.

On the 15th of December, 1909, the district awarded contracts for the construction of 65 miles of drainage work. The contracts were four in number, to as many different contractors. The contract for straightening the Elkhorn river, which was to be the trunk line or main stem of all the drainage work provided for under these four contracts, was let to the drainage company, and is the only one with which we have to do in this case. By the terms of the contract the drainage company agreed to commence the work provided for in the contract on or before the 1st day of March, 1910, and to entirely complete it on or before the 31st day of December, 1910. The contract also provided, among other things, that all work to be performed thereunder should be done and performed according to certain specifications which were attached and made a part of the contract; that the district reserved the right to change the line, grade, and endings' of the work from that shown on the plans furnished; that, if the contractor failed to prosecute the work with sufficient force, in the opinion of the engineer of the district,.to insure .its completion within the time specified in the contract, the district should have the right to employ such additional force as the engineer might deem necessary to complete the work within that time, or the district might declare the contract forfeited and abandoned; that the contractor should be liable for damages arising from a failure to complete the work within the time specified in the contract; that in the event of delay caused by the district by reason of the failure of the engineer to stake out the work promptly, or from any other cause for which the district was responsible, the time for completion of the work should be extended for a period equal to not less that the aggregate length of time of such delay. To secure the faithful performance of this contract, the drainage company gave a bond with the Title Guaranty & Surety Company as surety. During the progress of the work in 1910, the district, as authorized by the contract, made some changes in the line of the excavation work to be performed by the drainage company.

On the 30th of December, 1910, one day before the time fixed by the contract for the completion of the work, only -about one-third of [344]*344it had been finished, and to avoid a forfeiture of the contract, after some negotiations between the drainage company and the district, the bond in suit was executed and accepted as additional security; the district agreeing not to declare a forfeiture at that time. As the recitals in the bond contain a statement of the facts as they existed at the time the bond was executed, it is here set out at length:

“Know all men by these presents: That we, Standard Drainage Co., of Windom, Minnesota, as principal, first party, and the Bankers’ Surety Oo. oí Cleveland, Ohio, as surety, are held and firmly bound unto Elkhorn Drainage District, second party, in the sum of thirty dollars per day as liquidated damages for the noncompletion of the contract hereinafter mentioned, said per diem damages to commence with the first day of January, nineteen hundred eleven, and continue for each day until the work hereinafter mentioned is fully completed, for the payment of which sum, well and truly to be made, we hereby bind ourselves, our successors and assigns.
“Dated this 30th day of December, nineteen hundred ten.
“Whereas on the 15th day of December, nineteen hundred nine, first party entered into a contract in writing with second party, a drainage district organized under chapter 153 of the Laws of Nebraska of 1007 and amendments thereto; and
“Whereas said contract provided that said first party should do certain excavating and construct certain embankments, and do certain clearing and grubbing, all with reference to the straightening_ of the channel of the Elk-horn river through Dodge and Washington counties, Nebraska: and
“Whereas said contract provided that all of said work should be commenced on or before the first day of March, nineteen hundred ten, and be entirely completed on or before the thirty-first day of December, nineteen hundred ten; and
“Whereas, said party entered into a bond with second party in the sum of ten thousand dollars for the faithful performance of said contract, in which bond the Title Guaranty & Surety Go., was surety; and
“Whereas, the time for the completion of «aid contract has nearly expired and only a small portion of said work has been done, and it is now known that the very large majority of said work cannot be completed by the expiration of the time provided therefor in said contract; and
“Whereas, said work provided in said contract to be done, contemplated an expenditure of more than thirty thousand dollars, estimated cost to be paid to said first party; and
“Whereas said work contemplated the expenditure of many thousands of dollars in addition thereto for right of way and'other expenses, all of said work above mentioned relating to what is known as the ‘river cut-off work’; and
“Whereas said river cut-off work constitutes the ‘trunk line’ of a more comprehensive drainage system now being established by said second party, the total expenditures for said drainage system being considerably in excess-of two hundred thousand dollars; and
“Whereas nearly all of said drainage work has now been completed except the river cut-off work; and
“Whereas the balance of the drainage system other than the river cut-off work is dependent in part for its effectiveness upon the completion of said river put-off work, and will not furnish adequate relief or do its full measure of service without the completion of said river cut-off work; and
“Whereas the benefits that said second party will obtain from said drainage system will be several multiples of the cost thereof, being a benefit of from six hundred thousand dollars to one million dollars; and
“Whereas said first party admits that it is impossible to finish said work by the contract time therefor; and
“Whereas said second party has the right to declare a forfeiture of said contract and has a right to take steps to arrange with some one else to do said work; and
[345]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Kanter
137 F.2d 828 (Eighth Circuit, 1943)
Southern Pac. Co. v. Globe Indemnity Co.
21 F.2d 288 (Second Circuit, 1927)
Northwestern Terra Cotta Co. v. Caldwell
234 F. 491 (Eighth Circuit, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
214 F. 342, 130 C.C.A. 650, 1914 U.S. App. LEXIS 1146, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bankers-surety-co-v-elkhorn-river-drainage-dist-ca8-1914.