Bangor Hydro-Electric Co. v. Public Utilities Commission

589 A.2d 38, 1991 Me. LEXIS 99
CourtSupreme Judicial Court of Maine
DecidedApril 4, 1991
StatusPublished
Cited by4 cases

This text of 589 A.2d 38 (Bangor Hydro-Electric Co. v. Public Utilities Commission) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bangor Hydro-Electric Co. v. Public Utilities Commission, 589 A.2d 38, 1991 Me. LEXIS 99 (Me. 1991).

Opinion

WATHEN, Justice.

Bangor Hydro-Electric Company (“Bangor Hydro”) appeals a final order of the Maine Public Utilities Commission (“PUC”) denying without prejudice Bangor Hydro’s petition for certificates of public convenience and necessity for two independent hydroelectric generating projects. 1 Bangor Hydro contends that the PUC arbitrarily ignored its own rules and precedents, made findings of fact that were not supported by the evidence, and erred in denying the cer-" tificates due to uncertainties created by their premature filing. Finding no error, we affirm the order of the PUC.

On November 22, 1989, Bangor Hydro filed petitions for certificates of public convenience and necessity requesting the PUC to approve three hydroelectric projects along the Penobscot River. The Basin Mills project, which was expected to provide 32 MW of additional capacity by 1999, involved the construction of a new dam and power facility. Construction on the project was not to begin until 1996. The Veazie project, which was expected to add 6 MW of capacity by 1996, and the Milford *40 project, which was expected to add 2 MW of capacity by 1993, were to provide for an increase in the generating capability of currently existing hydroelectric facilities.

On August 17, 1990, the PUC denied without prejudice the Basin Mills and Veaz-ie petitions. 2 Re Bangor Hydro-Electric Company, Nos. 89-193 and 89-195 (Me.P. U.C. Aug. 17, 1990). While the PUC found that this decision was warranted solely on grounds of the petitions’ prematurity, it also cited Bangor Hydro’s failure to pursue least-cost options and demand-side resource planning as an alternative to the projects. In its order, the PUC described the standard used in evaluating petitions for certificates of public convenience and necessity:

[T]he utility must demonstrate that the power from the new source is needed and that the resource being considered is the most economical or at least it is a part of an overall least cost plan. In addition, the utility must demonstrate that the timing is reasonable.

This is the standard first articulated by the PUC in the 1979 Sears Island order and most recently reaffirmed in the Hydro-Quebec order. See Re Central Maine Power Co., No. 88-111, slip op. at 26 (Me.P.U.C. Jan. 23, 1989) (“Hydro-Quebec order”); Re Central Maine Power Co., No. U.# 3238, slip op. at 6-7 (Me.P.U.C. Dec. 31, 1979) (“Sears Island order”). It is consistent with the PUC’s longstanding policy of encouraging the development of qualifying facilities (“QFs”) 3 while requiring utilities to pursue a least-cost plan as required by the Maine Energy Policy Act of 1988, 35-A M.R.S.A. § 3191 (Supp.1990) (“MEPA”). 4

Bangor Hydro argues that the PUC erred in finding that the company did not allow independent power producers to bid against the Basin Mills and Veazie projects and it did not use the bidding process to minimize costs. These findings of fact “may not be upset on appeal if [they were] supported by substantial evidence in the record.” New England Tel. & Tel. Co. v. Pub. Util. Comm’n, 470 A.2d 772, 780 (Me.1984); accord New England Tel. & Tel. Co. v. Pub. Util. Comm’n, 448 A.2d 272, 278-79 (Me.1982); Cent. Maine Power Co. v. Pub. Util. Comm’n, 414 A.2d 1217, 1232 (Me.1980). It is the duty of the appellate court to “sustain whatever findings of fact underlie the [PUC’s] ultimate determinations on the basis of all of the evidence of record ... if the findings of fact are not clearly erroneous, i.e., are basically supported by the totality of’ the evidence of record.” Id.

The PUC found that, although Bangor Hydro had issued a request for proposals, the bidding and negotiation process was far from complete, and the company had no intention of completing the process until the PUC proceeding was over. The PUC could reasonably have based these findings on the evidence presented, including the testimony of Jeffrey A. Jones, Bangor Hydro’s Manager of Power Supply, *41 who stated that, although a bidding process had begun, it would probably not be completed before this case was concluded. He further admitted that the company had not given bidders an opportunity to bid against these particular hydro projects because these projects were already priced below the avoided costs. Thus, the PUC’s findings of fact were basically supported by the totality of the evidence of record and not clearly erroneous.

Bangor Hydro contends that the PUC arbitrarily ignored a standard of review articulated in Re Hiram Hydroelectric Redevelopment Project and Central Maine Power Company, No. 80-166 (Me. P.U.C. Nov. 24, 1981) (“Hiram order”) and reaffirmed in Re Central Maine Power Company, No. 85-158 (Me. P.U.C. Dec. 23, 1986) (“Lewiston Falls order”). This so-called “short-cut” standard provides that

a utility can meet its burden [of showing that it meets the requirements for “public convenience and necessity” under 35-A M.R.S.A. § 3132] if it demonstrates (1) that the facility for which approval is sought would have been a qualifying facility ... but for the fact that over 50% of the facility is owned by a utility and (2) that the revenue requirements associated with the facility are below the utility’s avoided costs.

Hiram order at 3-4. In the Lewiston Falls order, the PUC approved a stipulation that a need existed for the Lewiston Falls Hydroelectric Redevelopment Project, according to the standard announced in the Hiram order. Lewiston Falls order at 1.

The Hiram order allows small projects essentially owned by utilities to be treated like QFs and awarded certificates of public convenience and necessity if their revenue requirements are below the utility’s avoided costs. This order, however, provides no precedent for the present case. In the Sears Island order, the PUC had emphasized the need “to determine ... whether the facilities proposed by the petitioner meet [the] need [for additional generating or transmitting capacity] in the most economical and reasonable manner.” Sears Island order at 6. Such an inquiry is now mandated following the Hydro-Quebec order and the passage of the MEPA. See Hydro-Quebec order at 3; 35-A M.R.S.A. § 3191. In the Hiram order, the PUC failed to determine whether the proposed projects were more economical than other alternatives. Hiram order at 6. Furthermore, the PUC did not even apply the “short-cut” standard, which appeared in dicta, in the Hiram case, limiting the standard to prospective application. Hiram order at 4. Nor does the Lewiston Falls order, by its own admission, serve any precedential value. Lewiston Falls order at 14. At best, this standard of review places small utility-owned projects on an equal footing with QFs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Quiland, Inc. v. Public Utilities Commission
2008 ME 135 (Supreme Judicial Court of Maine, 2008)
S.D. Warren Co. v. Board of Environmental Protection
2005 ME 27 (Supreme Judicial Court of Maine, 2005)
Bangor Hydro-Electric Co. v. Board of Environmental Protection
595 A.2d 438 (Supreme Judicial Court of Maine, 1991)
Imagineering, Inc. v. Superintendent of Insurance
593 A.2d 1050 (Supreme Judicial Court of Maine, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
589 A.2d 38, 1991 Me. LEXIS 99, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bangor-hydro-electric-co-v-public-utilities-commission-me-1991.