Baltimore Pile Driving and Marine Construction, Inc. v. Wu & Associates, Inc.

CourtSuperior Court of Delaware
DecidedDecember 1, 2021
DocketN19L-07-090 SKR
StatusPublished

This text of Baltimore Pile Driving and Marine Construction, Inc. v. Wu & Associates, Inc. (Baltimore Pile Driving and Marine Construction, Inc. v. Wu & Associates, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baltimore Pile Driving and Marine Construction, Inc. v. Wu & Associates, Inc., (Del. Ct. App. 2021).

Opinion

IN THE SUPERIOR COURT OF THE STATE OF DELAWARE

BALTIMORE PILE DRIVING AND ) MARINE CONSTRUCTION, INC., ) Plaintiff, ) ) v. ) C.A. No. N19L-07-090 SKR ) WU & ASSOCIATES, INC., ) ) Defendant, Counterclaimant, ) Cross-claimant and Third Party ) Party Plaintiff, ) ) ) v. ) ) SELECTIVE INSURANCE COMPANY ) OF AMERICA, ) ) Third Party Defendant. )

DECISION AFTER TRIAL

Timothy S. Martin, Esq. and William J. Taylor (Pro Hac Vice) White and Williams LLP, Attorneys for Plaintiff Baltimore Pile Driving and Marine Construction Inc. & Third-Party Defendant Selective Insurance Company. Edward Seglias, Esq., Emily Letcher, George E. Pallas, Esq. (admitted Pro Hac Vice), and Matthew L. Erlanger, Esq. (admitted Pro Hac Vice) Cohen Seglias Pallas Greenhall & Furman PC. Attorneys for Defendant Wu & Associates, Inc.

I. FACTUAL AND PROCEDURAL BACKGROUND

This is a breach of contract action through which Plaintiff Baltimore Pile Driving and Marine Construction, Inc. (“BPDI”) seeks damages from Defendant Wu & Associates, Inc. (“Wu”) for extra work performed as a subcontractor on a construction project.1 Wu has filed a counterclaim against BPDI, alleging breach of contract and contractual indemnification.

On January 17, 2018, Wu submitted a bid and was awarded a Delmarva Power & Light Co. (“DPL”) contract to construct a new gas material storage shed located at 800 Delmarva Lane, Marine Hub, Wilmington, DE 19801.2 On March 26, 2018, Wu & DPL entered into a contract in which Wu agreed to construct the shed for $1,121,000.3 On March 27, 2018, BPDI and Wu entered into a subcontract (“the Subcontract”) for BPDI to construct an auger cast grout pile, which serves as the foundation for the shed. The Subcontract was worth $294,450.90. The Project schedule required BPDI to start working in May 2018, but this was delayed due to DPL’s difficulties in obtaining the necessary permits.4 On October 11, 2018, BPDI commenced working.5

On October 18, 2018, BPDI claims that it hit its first obstruction while drilling.6 It claims that it experienced downtime and a loss of grout as a result. On

1 Compl. ¶ 10. 2 Counterclaim ¶ 1. 3 Id. at ¶ 2. 4 Def.’s Proposed Findings of Fact and Conclusions of Law ¶ 43. 5 Compl. ¶ 16. 6 Pl.’s Proposed Findings of Fact ¶26. 2 November 14, 2018, it submitted its first change order request (“COR”) for the expenses incurred.7

From November of 2018 to March of 2019, BPDI submitted 31 work orders to Wu for the money it is now seeking. Wu does not dispute the validity of eleven CORs, of which it converted into Wu CORs, and “passed through” to DPL for payment (“pass through CORS”). Wu does not dispute BPDI’s entitlement to payment for eight more CORs, but claims it withheld payment pursuant to its right to a setoff for costs incurred by BPDI. 8 Twelve additional CORs were summarily denied and disputed. 9

On March 11, 2019, DPL directed Wu to terminate BPDI. DPL cited “repeated ongoing concerns” with BPDI as the reason for its requested dismissal, including a lack of necessary planning. 10 When BPDI left the project, it had installed 60 of the proposed 140 production piles.11

On July 29, 2019, BPDI brought suit against Wu & DPL, originally alleging breach of contract, a mechanic’s lien, and unjust enrichment.12 On September 20, 2019, Wu filed an answer and counterclaim against BPDI, alleging breach of contract.13 On January 6, 2021, DPL moved to discharge the lien upon posting of a bond and compelling posting of a bond by Wu, pursuant to a contractual agreement to indemnify DPL.14 On February 12, 2021, the Court granted the motion to discharge the lien upon the posting of a bond in the full amount of the lien sought,

7 Ex. 38 - Order Log. 8 Def.’s Proposed Findings of Fact and Conclusions of Law ¶ 100. 9 Id. at ¶ 101 – 141. 10 Id. at ¶ 68. 11 Id. ¶ 82. 12 Compl. 13 Counterclaim, ¶ 15. 14 DPL’s Motion to Discharge the Lien. 3 $495,746.73. The motion to compel Wu to post a bond was denied. On February 19, 2021, DPL filed a motion in limine to stay relevant crossclaims pertaining to DPL until adjudication of the main claims between BPDI & Wu. On April 15, 2021, the Court granted this motion.

On May 24, 2021, BPDI agreed to dismiss its claim for unjust enrichment.

BPDI’s remaining claims in this action relate to Breach of Contract (Count II) and the Building Payments Act (Count V).

II. THE TRIAL

The Court held a three-day bench trial from May 24-26, 2021. The case was deemed fully submitted for decision after the parties submitted their post-trial briefing.

During trial, the Court heard from and considered the testimony of the following witnesses:

David D. Lawrence Peter Robey Ralph Boedeker Donald E.W. Stauffer

Kirby Wu Theodore A. Thomson, Jr. Swamy Avasarala

III. STANDARD OF REVIEW

The Court is the finder of fact in a bench trial. 15 The plaintiff must prove each element of a claim by a preponderance of the evidence, meaning that the Court shall find in favor of the party upon whose side “the greater weight of the evidence is

15 Pencader Associates, LLC v. Synergy Direct Mortg. Inc., 2010 WL 2681862, at *2 (Del.Super. June 30, 2010). 4 found.”16 Since the Court is the finder of fact, it is up to the Court to weigh the credibility of witnesses and resolve conflicts in witness testimony. 17

IV. ANALYSIS

Both BPDI and Wu have alleged a breach of contract against each other. BPDI claims that Wu materially breached the contract by refusing to accept and/or pay its valid COR requests. It seeks $471,831.50 for outstanding change orders in addition to attorneys’ fees and costs. 18 Wu claims that BPDI breached the contract when DPL terminated BPDI from the contract, thus not completing performance and leaving Wu “significantly damaged” in the amount of $41,766.81, in addition to attorneys’ fees and costs.19 This is also the amount that Wu asserts against Selective Insurance Company (“Selective”) as BPDI’s bonding company. Both parties assert they are due attorneys’ fees and costs pursuant to the Delaware Building Construction Payments Act. 20

For the reasons set forth below, the Court finds that BPDI has proven by a preponderance of the evidence, through credible testimony of its witnesses and the documents relied upon at trial, that Wu breached the Subcontract when it refused to pay BPDI for several of the CORs it filed. Thus, Wu is liable to BPDI for certain COR payments as discussed below.

16 Id. (quoting Pouls v. Windmill Estates, LLC, 2010 WL 2348648, at *4 (Del.Super. June 10, 2010)). 17 Id. at *3. 18 BPDI’s Complaint and Demonstrative Trial Exhibit “B” have different numbers for the total outstanding CORs. The Complaint lists CORs for a total of $477,839.50 and the Exhibit lists CORs for a total of $497,441.00. In addition, COR #40, which requests $32,554.00, is listed twice in Trial Exhibit “B”. For that reason, the Court has made its own calculation of the individual CORs that were submitted. 19 Def.’s Proposed Findings of Fact and Conclusions of Law at 15, fn 1. 20 6 Del. C. §3501 et seq. 5 A. BPDI-Wu Subcontract Interpretation 1. The parties claim that alternate provisional language governs the CORs. BPDI and Wu claim that two different documents – both of which are incorporated by reference into the Subcontract -- govern the COR claims made by BPDI.

BPDI relies on the BPDI Proposal, which is integrated into the Subcontract by Section 1.3. It states in relevant part, “except to the extent of a conflict with a specific term or condition contained in the Subcontract Documents, the General Conditions governing this Subcontract shall be the AIA Document A201TM 2017, General Conditions of the Contract for Construction, and the Subcontractor’s Proposal. . .”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lorillard Tobacco Co. v. American Legacy Foundation
903 A.2d 728 (Supreme Court of Delaware, 2006)
E.I. Du Pont De Nemours & Co. v. Admiral Insurance Co.
711 A.2d 45 (Superior Court of Delaware, 1995)
Rhone-Poulenc Basic Chemicals Co. v. American Motorists Insurance Co.
616 A.2d 1192 (Supreme Court of Delaware, 1992)
Sassano v. CIBC World Markets Corp.
948 A.2d 453 (Court of Chancery of Delaware, 2008)
Eagle Industries, Inc. v. DeVilbiss Health Care, Inc.
702 A.2d 1228 (Supreme Court of Delaware, 1997)
Brandywine Smyrna, Inc. v. Millennium Builders, LLC
34 A.3d 482 (Supreme Court of Pennsylvania, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Baltimore Pile Driving and Marine Construction, Inc. v. Wu & Associates, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/baltimore-pile-driving-and-marine-construction-inc-v-wu-associates-delsuperct-2021.