Baltimore & Ohio Railroad v. C. J. Langenfelder & Son, Inc.

292 A.2d 415, 222 Pa. Super. 138, 1972 Pa. Super. LEXIS 1250
CourtSupreme Court of Pennsylvania
DecidedJune 15, 1972
DocketAppeal, No. 191
StatusPublished
Cited by6 cases

This text of 292 A.2d 415 (Baltimore & Ohio Railroad v. C. J. Langenfelder & Son, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baltimore & Ohio Railroad v. C. J. Langenfelder & Son, Inc., 292 A.2d 415, 222 Pa. Super. 138, 1972 Pa. Super. LEXIS 1250 (Pa. 1972).

Opinion

Opinion by

Watkins, J.,

This is an appeal from the judgment of the Court of Common Pleas, Civil Division, of Allegheny County, Pennsylvania, in an action of trespass in which the jury determined liability in favor of the plaintiff-appellee, The Baltimore and Ohio Railroad Company, and against the defendant-appellant, C. J. Langenfelder & Son, Inc., in the stipulated amount of One Hundred Thousand Dollars ($100,000.00); and from the denial of post-trial motions.

This action was brought by the railroad to recover damages sustained by the collapse of a tunnel. In order to permit the passage of modern railroad cars, it was decided to lower the floor of the tunnel. The tunnel in question, was constructed over one hundred years ago, but had been in continuous use until the early 1960’s. The railroad-plaintiff and the defendant-contractor entered into a contract which required the contractor to perform the task of lowering the floor of the tunnel in accordance with the detailed specifications prepared by the railroad’s engineering staff.

On June 6, 1963, after the tunnel floor had been lowered and while the contractor’s workmen were digging a ditch along one wall of the tunnel, a portion of the tunnel collapsed. The railroad contends that the collapse was due to the contractor’s negligence. Damages were stipulated to be One Hundred Thousand [140]*140Dollars ($100,000.00) and the case was tried before a jury solely on the question of liability. The jury found for the plaintiff-railroad.

The contractor advances three reasons that it contends requires a new trial: (1) the verdict is against the weight of the evidence; (2) the opinion of Dr. Ackenheil, the expert witness, should not have been admitted into evidence and his testimony should have been stricken; (3) the entire general construction contract should not have been permitted to go out with the jury for its use in deliberation since it contained material which was highly prejudicial to the contractor.

The law is clear that the grant or refusal of a new trial is within the sound discretion of the trial court but that discretion is not absolute. Austin v. Ridge, 435 Pa. 1, 255 A. 2d 123 (1969). In passing upon a motion for a new trial, it is necessary to consider the entire record and determine whether the verdict was arbitrary or capricious or that it was against the weight of the evidence, or whether there was clearly error of law or palpable abuse of discretion in the rulings of the court below. Hayes Creek Country Club, Inc. v. Central Penn Quarry S. & C. Co., 407 Pa. 464, 181 A. 2d 301 (1962).

The contractor complains that the hypothetical question put to Dr. Ackenheil, the expert witness, as to causation contained assumptions not in evidence. The expert, of course, cannot base his opinion upon facts not known to him and not supported by the evidence. Collins v. Hand, 431 Pa. 378, 246 A. 2d 398 (1968).

The court below discussed carefully and ably the testimony of this expert and explains the reasons for the admissions of the testimony as well as the exercise of his discretion in refusing a new trial on the first two reasons submitted by the contractor as follows:

[141]*141“The defendant’s first and second reasons for a new trial are interdependent in that defendant argues in his brief that plaintiff sought to rely on the allegedly incompetent testimony of plaintiff’s expert witness, Dr. Ackenheil, in order to cure the insufficiency of plaintiff’s other evidence pointing to defendant’s negligence. Thus, defendant appears to imply that if plaintiff’s expert’s opinion evidence is competent, i.e., based on facts warranted by the evidence, then sufficient evidence would exist to permit the jury to bring in a verdict for the plaintiff.
“The crux of the defendant’s contention, then, is that the hypothetical question put to Dr. Ackenheil regarding causation (R-199, 200, 201, 202) contained assumptions not in evidence. It is a well established principle that an expert cannot base his opinion upon facts unknown to him and not supported by the evidence. Collins v. Hand, 431 Pa. 378, 246 A. 2d 398 (1968) ; Rennekamp v. Blair, 375 Pa. 620, 101 A. 2d 669 (1954). A review of the record reveals no such infirmity.
“Dr. Ackenheil answered the hypothetical by declaring that the failure of the defendant to restore lost stability to the wall foundation was the cause of the collapse. He stated that the contract specifications called for the excavation of short sections of trench and the installation of steel reinforced concrete therein where there was a possibility of disturbing the sidewall foundation (R-213); that the use of dynamite in excavation did disturb the sidewall foundations (R-212, 213); that given the defendant’s expertise, he should have known that the red shale sidewall foundations would become unstable when exposed to water (R-211, 214); that the defendant should have followed the plan specifications for such contingency by trenching five or ten foot sections and pouring the concrete curb to get back support (R-213, 214) ; and finally, that the defendant’s [142]*142failure to comply with the requirements of the specifications was the cause of the collapse (R-213, 214).
“Essentially, the question called upon the doctor to state his opinion as to the cause of the collapse based on the following factors: the duties of the defendant as spelled out in the contract; the weather conditions existing prior to and at the time of the collapse and the resulting condition of the tunnel; the composition of the material encountered by the defendant in its excavation of the tunnel floor when the collapse occurred; and, the nature and extent of defendant’s excavation activities in the tunnel. Each of these factors or elements were introduced into evidence, as is borne out by the following analysis:
“1. The Contract
“The contract contains a number of references to the requirement that plaintiff comply with detailed safety procedures regarding support of foundation walls exposed by defendant’s excavations. One such example is plaintiff’s exhibit 16, captioned ‘Construction Details’, which contains the following admonition :
“Note : In carrying out the excavation for the curb walls, care must be taken not to disturb the existing sidewalls of the tunnel or the ground supporting the sidewalls. Where there is underpinning on a possibility of disturbing the sidewall foundations, excavation adjacent thereto shall be removed in small quantities and the underpinning or curb wall built immediately in order to minimize the danger of disturbing the sidewall foundations. (R-148)
“2. The Weather Conditions “The defendant was only partially successful in pumping out water which had seeped into the tunnel as a result of rains which had fallen in the area for several days prior to the collapse (R-69, 131). The water remaining in the tunnel settled in the three hundred foot [143]*143long, two foot wide by two foot deep, continuous ditch which defendant had been digging adjacent to the existing north wall preparatory to installing the concrete curb required in the specifications (R-68, 69, 83, 93).
“3. Material Encountered

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Klyman v. Southeastern Pennsylvania Transportation Authority
480 A.2d 299 (Supreme Court of Pennsylvania, 1984)
Commonwealth v. Daniels
390 A.2d 172 (Supreme Court of Pennsylvania, 1978)
Lebesco v. Southeastern Pennsylvania Transportation Authority
380 A.2d 848 (Superior Court of Pennsylvania, 1977)
Gonzalez v. United States Steel Corp.
374 A.2d 1334 (Superior Court of Pennsylvania, 1977)
Jones v. Jones
6 Pa. D. & C.3d 464 (Philadelphia County Court of Common Pleas, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
292 A.2d 415, 222 Pa. Super. 138, 1972 Pa. Super. LEXIS 1250, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baltimore-ohio-railroad-v-c-j-langenfelder-son-inc-pa-1972.