Baltimore & Ohio R. R. v. Laffertys

14 Va. 478
Supreme Court of Virginia·Decided August 9, 1858·Published

Opinion

Moncure, J.

An agreement was entered into between the appellees and the appellant in this case, similar to those which were entered into between the appellees and the appellant in the case just decided, of The Baltimore & Ohio Rail Road Company v. Polly, Woods & Co., except that in this case the work to be done was on the 161st and 162d sections of said road. The agreement bears date on the 20th day of January 1851, the work was to be completed on or before the first of June 1852, and the prices agreed to be paid for the different kinds of work were generally different from the prices agreed to be paid for similar work in that case.

The work was finished on the 1st of December 1852. The monthly and final estimates were made of the quantity, character and value of the work, as provided for in the said agreement.

In June 1853 the appellees instituted an action of assumpsit against the appellant. The declaration contained but two counts, to wit, the indebitatus count, and the account stated. No bill of particulars appears in the copy of the record which is before this court; though it is probable that one was filed with the declaration. After various proceedings were had in the action, a verdict was found for the appellees on the [480]*480general issue, for fifteen thousand three hundred and seven dollars and sixty cents, with interest thereon from the 20th day of December 1852 until paid; and-judgment was rendered accordingly on the 5th of July 1854.. The appellant obtained a supersedeas to the judgment.

The first error assigned in the petition for the supersedeas, is the rejection by the court of .three special pleas which were offered by the defendant. They are similar to the three special pleas which were offered and rejected in the case of The Baltimore & Ohio Rail Road Company v. Polly, Woods & Company; except that the first special plea in this case avers full payment of the amount ascertained by the final estimate. And for reasons assigned in that case, I amCof opinion that the court did not err in rejecting the three special pleas in this.

The second assignment of error is founded on .the defendant’s second bill of exceptions. On the trial of the cause, the plaintiffs having offered evidence of work done by them for the defendant, proposed to examine a witness (Charles De Hass) as to the amount and value of the work; and thereupon the defendant objected to the admissibility of such evidence, and offered to prove that the whole of said work was done’under a written contract, duly executed' by the plaintiffs and defendant (and set out in hcec verba in the bill of exceptions) ; and that a final estimate of said work had been made according to the provisions of said contract; which objection the court overruled, and the defendant excepted.

The question presented by this assignment of error, is the same in effect with the question presented by the second assignment of error in the case above referred to: and for reasons given in that case, I am of opinion that the court did not err in overruling the objection above mentioned.

[481]*481The third and last assignment of error is, the refusal of the court to give the three instructions asked for by the defendant, and the giving of certain other tions in lieu of the second and third. This assignment of error is founded on the defendant’s third and plaintiffs’ second bills of exception, which refer to each other, and are to be taken together. From which it appears that on the trial of the cause the plaintiffs having offered evidence tending to prove the cause of action as declared upon, and the defendant having proved the written contract aforesaid, and offered evidence tending to prove that the work in the declaration mentioned was done under that contract; and having further offered in evidence papers purporting to be monthly and final estimates of the local or resident engineer mentioned in said contract; and the plaintiffs having offered evidence tending to impeach said estimates, and show mistake and error on the face of them; and the defendant having offered evidence to sustain them ; and the plaintiffs and defendant having proved facts tending to show a waiver in the times of the performance of said contract and alteration of some of the terms thereof; the defendant thereupon moved the court to instruct the jury as follows, viz:

1st; that if they believe from the testimony that the work, &c. set out in the first count of the declaration, and charged in the bill of particulars, was done by the plaintiffs under the said written contract; then although they may further believe from the testimony that no proper and sufficient final estimate of said work has been made by the engineer charged with that duty, according to the terms of the contract, the plaintiffs are yet not entitled to recover under said first count, unless they further show that, after a demand or other proper exertions on their part, they have been unable to procure such a final estimate as is required by the contract.

[482]*4822nd; that if they believe, &c. (as above); then that Pontiffs are not entitled to recover under said count, unless they have further shown, either that they had given or had offered to give to the defendant a release under seal, from all claims or demands whatsoever growing in any manner out of said contract.

3d; that if they believed, &e. (as above); and further, that in accordance with said contract, a final estimate of said work, &c. has been made out by said engineer; and that the fall amount of said estimate has been paid by the defendant to the plaintiffs; then, in the absence of any proof of fraud or other misconduct on the part of said engineer, they ought to find for the defendant so far as said first count is concerned.

These instructions the court refused to give; but in lieu thereof, or of the second and third, gave the following :

“ The contract between plaintiffs and defendant, provides for the performance of certain kind of work for the defendant, and the mode and times of ascertaining the quantity and nature of such work as the same shall have been executed, and fixes the compensation for each respective kind. The contract provides for embankment, earth excavation, loose rock excavation, and solid rock excavation; and the character of these different kinds of work, besides this general classification, are again more specially defined in the contract. From the general language used in their classification, and from the very nature of the subject, it is apparent that at no stage of the work, where there is any gradual change in the character of the material to be removed, there can be a precise ad-measurement or ascertainment, by any agency or method which might have been adopted, of the quantity,, and especially of the character of either or each class; but something must be left to the judgment of one or the other party, or to some proper substitute. Hence, [483]*483in the provision for ascertaining quantities and classi.fication, the term “estimate” is properly used, rather than the more precise and definite term of “ ment,” as the amount of the respective classes of work could not be ascertained in advance, and it was desirable that the

Free access — add to your briefcase to read the full text and ask questions with AI

Baltimore & Ohio R. R. v. Laffertys, 14 Va. 478 (Va. 1858).

14 Va. 478 (Baltimore & Ohio R. R. v. Laffertys) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.