Baltimore & O. R. Co. v. Camp

105 F. 212, 12 Ohio F. Dec. 293, 1900 U.S. App. LEXIS 3821
CourtCourt of Appeals for the Sixth Circuit
DecidedDecember 4, 1900
DocketNo. 829
StatusPublished
Cited by1 cases

This text of 105 F. 212 (Baltimore & O. R. Co. v. Camp) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baltimore & O. R. Co. v. Camp, 105 F. 212, 12 Ohio F. Dec. 293, 1900 U.S. App. LEXIS 3821 (6th Cir. 1900).

Opinion

EVANS, District Judge.

This case has heretofore been twice before this-court. The facts out of which the action arose have been fully stated in previous opinions, reported, the first, In 13 C. C. A. 233, 65 Fed. 952, 31 U. S. App. 213, and the second in 26 C. C. A. 626, [213]*21381 Fed. 807, 51 U. S. App. 110. After a third trial, which also resulted in a verdict and judgment for the plaintiff, I he railroad company has again brought the case here, and has made various assignments of error. Some of these raise the question of whether, there was evidence sufficient to authorize the submission of the case to the jury at all; others, the question of whether the pleadings should have been amended; and others, whether the court below should have granted a new trial, — but these (especially in view of our previous decisions). are so obviously insufficient to warrant a reversal that: we need not further allude to them. Indeed, among the specifications of error there appear to he only three which seem to require any detailed treatment.

1. The court below refused to permit the plaintiff in error to prove that at the time of the injury to 'Oamp there was an existing contract between him and the railroad company, whereby, upon certain payments of dues, an indemnity fund had been created for the employés oí the railroad company, out oí which, in case of injury, Camp, as an empioyd, might, at his option, elect either to take indemnity for his injuries out of this fund, or else to claim it from the company itself, hut which did not permit him to do both; and the court further refused to permit the introduction of evidence tending to show7 that after the injury, and before the action was brought, Cam}), had elected to take, and had in fact received, payment of certain installments, pursuant to the contract, out of this indemnity fund; and which facts, it is contended, the court should have permitted the railroad company to prove in bar of Camp’s right to recover in this suit. The plaintiff below objected to the introduction of this testimony, and each part of it; and to the refusal of the court to permit it to go to the jury the railroad company excepted, and this ruling of the court is the basis of the second error assigned.

Section 5070 of the Revised Statutes of Ohio provides:

“The answer shall contain: 1. A general or specific denial of ouch material allegation of the petition controverted hy the defendant. 2. A statement of any new matter constituting a defense, counterclaim or set-off, in ordinary and concise language.”

An examination of the pleadings in the case will sliow that there was no averment in the answer of any new mal ter constituting a defense to which the proposed evidence was in any way applicable. There was, therefore, no issue upon the subject, and no averment in the answer to which the proposed evidence would bo relevant, and the court cannot doubt that its rejection hy the trial court was entirely proper. Whatever degree of liberality may have been readied in the practice in Ohio, the plaintiff was still entitled to insist upon his rights under the section of the statute'just copied, that any new matter constituting a defense should he stated in the answer, to the end that he might have notice of it in time to meet it. The testimony having been objected to when offered, the general rule still is that there must be allegation as well as proof; and, there being no allegation in tilia case, and no offer to amend the pleading, the proof offered was not pertinent. We are of opinion, therefore, that this assignment of error is not well taken.

[214]*2142. The eighth specification of error, No. 3, is based upon the refusal of the court to charge the jury as follows:

“Tbe rules of the company introduced in evidence provide: ‘All conductors- and enginemen must go to telegraph offices at Bpllaire, Zanesville, Newark, Chicago Junction, 'Sandusky, and Shawnee, and ask for orders, before leaving these stations. The application for orders, as above, will be made by the use of “Blank A.” Conductors and enginemen must get orders or clearance card. “Blank B,”' before leaving above stations.’ If the plaintiff and the conductor of the train which they were running did not comply with the conditions of this, rule, and started their train east in disregard of the same, when the compliance with its terms would have enabled the train dispatcher to have given the order to the plaintiff and the conductor at Newark, instead of Black. Hand, then, and in that 'ease, the plaintiff has no right to complain, because the passing and hold orders were sent to Black Hand instead of Newark. Going to the office three-quarters of an hour before leaving, and not afterwards, would not be a compliance with this rule.”

The rules of the railroad company, as disclosed by the testimony of' defendant, provide as stated in the proposed instruction; but the proof was very clear that Camp did, at 10 o’clock and 4 minutes a. m.,. at Newark, ask for and get “orders,” though not a formal “clearance a card.” The rule, however, as appears upon its face, did not require that both should be obtained. The orders were that the train of' which Camp was the engineer should proceed east from Newark, and this involved the passing of express passenger train No. 47 between Newark and Black Hand. This train was, as his other orders showed,, running 3 hours ahd 10 minutes late, and the only passing place was Clay Lick, where his orders also required him to pass a freight train, which of itself would take about 15 minutes. These orders were received at a time which, when construed in connection with the standing rule of the company, which required a freight train, such as Camp’s, to reach a meeting station and get on a side track at least 10 minutes before the time for the arrival of the passenger train, made it necessary, as the time was too short, in his judgment, to reach Clay Lick soon enough to obey this rule, that 'Camp’s train should not start until after the passenger train had not only reached Clay Lick,, but had come into Newark, a distance of about six miles. But, notwithstanding these facts, the court was asked, in the proposed instruction, to charge the jury conclusively, and as matter of law, “that going to the office three-quarters of an hour before leaving, and not afterwards, would not be a compliance with this rule.” To this we cannot agree. Nor can we agree to the contention that it was essential to have a “clearance card” as well as “orders.?’ Whether an instruction upon this subject, properly phrased, might not have been well given to the jury in such manner as to leave the question of fact to them to say whether Camp, in what he did, was obeying the orders- and rules binding upon him in the then present conditions and emergency, might be an interesting question if presented; but it is not presented, and in the form proposed by the railroad company the instruction was not sound, and should not have been given, because it told the jury absolutely, and without qualification or condition, although he then got his orders, that Camp’s going to the office three-quarters of an hour before leaving, and not afterwards, would not be-a compliance with the rule. That conclusion might depend, and did. [215]*215depend, upon the circumstances as the jury might find them to exist. An instruction proposed by a party must be correct in every substantial and important particular before it is error to refuse it as a whole. We think this assignment is not well taken.

3. The thirteenth specification under assignment of error No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southern Ry. Co. v. Hopkins
161 F. 266 (Fifth Circuit, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
105 F. 212, 12 Ohio F. Dec. 293, 1900 U.S. App. LEXIS 3821, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baltimore-o-r-co-v-camp-ca6-1900.