Baltimore Contractors, Inc. v. The Renegotiation Board

383 F.2d 690, 1967 U.S. App. LEXIS 5129
Court of Appeals for the Fourth Circuit·Decided September 13, 1967·No. 10090·Published·Cited by 3 cases

Opinion

HAYNSWORTH, Chief Judge:

We agree with the Tax Court that the Renegotiation Act of 1951 is a constitutional exercise of the war powers of Congress. The Korean Conflict was smaller than World War II, but its impact upon the nation’s economy was heavy enough to warrant congressional invocation of the war powers to limit profits on defense contracts.

Within three weeks after the invasion of the Republic of Korea by the armies of North Korea, 1 the President authorized the use of American troops to repel the attack and announced a substantial increase in procuring and stockpiling defense-related materials. 2 Shortly thereafter, a bill, 3 modeled after the Renegotiation Act of 1942, 4 was introduced in the House. Although extensive hearings were held during August of 1950, 5 neither house of Congress acted upon the bill during that session. 6 However, when Congress convened in January of 1951, a similar bill was introduced, promptly passed both houses 7 and was signed into law on March 23, 1951. 8

With certain exemptions, 9 the statute subjected to renegotiation all contracts with named government agencies to the extent of amounts received or accrued after January 1, 1951, 10 unless the contract had been executed prior to July 1, 1950. 11 Among the contracts to which the Act did not apply were those having no direct and immediate connection with the national defense. 12

On October 13, 1950, and January 31, 1951, months after the opening of hostili *692 ties and the hearings during the preceding August on the original version of the Renegotiation Act of 1951, General Services Administration 13 and Baltimore Contractors, Inc. executed two contracts 14 for the construction of fire prevention facilities at government warehouses 15 used to store crude rubber and other strategic materials. 16 The contractor completed the construction of the respective facilities in 1951 and 1952 and, under the completed contracts method of accounting, received the profits, respectively, in those years. 17

After negotiations failed to establish the amount of excessive profits received by the contractor, the Board issued unilateral orders fixing the amount at $150,000. The contractor sought de novo redetermination of the amount in the Tax Court 18 and collaterally contended that the Act was unconstitutional. The Tax Court upheld the statute but found that the excessive profits had been only $125,000. 19 After denial of timely motions to reconsider and for review by the entire court, this appeal was filed.

Here the contractor contends that the Act is unconstitutional because the impact of the Korean Conflict upon the American economy did not justify congressional use of the war powers retroactively to renegotiate contracts.

Lichter v. United States, 20 which held the Renegotiation Act of 1942 21 to be a law necessary and proper for carrying into execution the war powers of Congress, answers many of the questions with which we are faced. While the opinion is written in terms of “total global warfare,” 22 like the Tax Court, we are of the opinion that its reach is not limited to warfare so far flung.

Clearly, congressional power to raise and support armies does not depend upon the existence of a declared war. It is enough if the exigencies of the situation justify congressional use of those powers in a certain way. World War II created a pressing need for rapid procurement of new materials, at a pace and in volume without precedent, causing a breakdown in contract cost and profit analysis in virtually every sector of the American economy. 23 In that atmosphere, renegotiation of defense contracts was found to be “well within the constitutional discretion of Congress. * *” 24 Similarly, the outbreak of hostilities in Korea, though in smaller degree, had a marked effect upon the economy. It spawned a “vast program of military *693 procurement” 25 of “items not included in the customary output of * * '* plants, as well as many items that were wholly new and unfamiliar” 26 and “in enormous quantities far in excess of ordinary levels.” 27 As a direct result, there occurred a breakdown in the ordinary processes of defense contract pricing, making it possible for contractors to realize excessive profits on defense contracts. Under the authority of Lichter, this was ample justification for congressional action aimed at renegotiation of defense contracts, even though the entire economy was not disrupted. In addition, the clear possibility of a direct military confrontation between the United States and one or both of the major Communist powers, 28 and the danger of a consequent expansion of the otherwise limited fighting into total global warfare, makes it absolutely clear that the Renegotiation Act of 1951 was a law necessary and proper to the exercise of congressional war powers, and was within the constitutional power of Congress.

Free access — add to your briefcase to read the full text and ask questions with AI

Baltimore Contractors, Inc. v. The Renegotiation Board, 383 F.2d 690, 1967 U.S. App. LEXIS 5129 (4th Cir. 1967).

383 F.2d 690 (Baltimore Contractors, Inc. v. The Renegotiation Board) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Perry v. United States
527 F.2d 629 (Court of Claims, 1975)
S. S. Silberblatt, Inc. v. Renegotiation Board
51 T.C. 907 (U.S. Tax Court, 1969)