Baltimore Contractors, Inc. v. Department of Natural Resources

10 Ct. Cl. 148
CourtWest Virginia Court of Claims
DecidedJanuary 8, 1975
DocketNos. D-510, D-516, D-528
StatusPublished
Cited by1 cases

This text of 10 Ct. Cl. 148 (Baltimore Contractors, Inc. v. Department of Natural Resources) is published on Counsel Stack Legal Research, covering West Virginia Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baltimore Contractors, Inc. v. Department of Natural Resources, 10 Ct. Cl. 148 (W. Va. Super. Ct. 1975).

Opinion

JONES, JUDGE:

Sometime in the early 1960’s the Economic Development Administration (EDA) of the United States Department of Commerce announced the availability of federal funds for the construction of recreational facilities in the State of West Virginia. The State’s responsibility for this program was assigned to the respondent, Department of Natural Resources (DNR), and DNR retained the services of The Architects Collaborative (TAC), a well-known and highly regarded architectural firm of Cambridge, Massachusetts, for purposes of preliminary studies of the feasibility of several proposed State Park projects. It was finally determined that the State would build what now have become widely known and popular State Parks, namely, Hawks Nest State Park, Canaan Valley State Park, Pipestem State Park and Twin Falls State Park. TAC was employed by DNR [149]*149to serve as architect engineer for all of the projects. TAC sub-contracted the detailed design work and construction supervision to Irving Bowman & Associates (IBA), an architectural and engineering firm in Charleston, West Virginia. The claim of Baltimore Contractors, Inc., hereinafter referred to as Baltimore, involves only the Pipestem and Twin Falls projects.

In an effort to help West Virginia contractors, the two projects were divided into numerous smaller projects and individual plans and specifications were prepared by TAC. A satisfactory bidder was found for the golf courses, but otherwise the multi-package plan proved unproductive. Then, with encouragement from Baltimore and other large contractors, the Pipestem and Twin Falls projects, minus golf courses, were consolidated. This was done by modification of the bid proposal and by eight addenda, tying the numerous contracts together into one large contract, upon which bids were asked and received. While there was tacit approval of this procedure by all bidders, who presumably knew what they were bidding on, the language employed in the consolidation did result in troublesome questions of interpretation, particularly as regards Addendum No. 4 pertaining to the Pipestem project, which will be alluded to further herein.

A site inspection was held at Pipestem sometime in August, 1967. The meeting was attended by representatives of TAC, DNR, two contractors who later bid on the contract and a road contractor interested in the separate contract for construction of a road into Pipe-stem. While a notice of the meeting was sent to Baltimore, it did not attend. The group inspected the site on foot and by automobile, and also examined models of both Pipestem and Twin Falls. Jay Henry, Chief Engineer for State Parks of DNR, testified that bidders at the pre-bid inspection were told that they took the roads “as is”. With specific reference to Twin Falls, Mr. Henry further testified as follows: “I told them there was the road at one end that was temporary and a road at the other end which was going to be re-built, but that’s about the only extent that I can recall on the discussion at Twin Falls.”

A site inspection was made by Dale Willey, an employee in the Estimating Department of Baltimore. On September 6, 1967, he met with Sam Flournoy, an employee of DNR, in Charleston and was [150]*150driven by Mr. Flournoy to Pipestem and, according to Mr. Willey’s testimony, on to Twin Falls and back to Charleston. Mr. Flourney has no recollection of taking Mr. Willey to Twin Falls but instead recalls stopping at Hawks Nest. In any event, Mr. Willey kept no records and made no written reports of his inspection; and subsequent events would indicate that nothing he saw or learned posed any problem or required any explanation or action so far as Baltimore was concerned.

On October 20, 1967, Baltimore submitted a bid for the construction of certain buildings and related structures and facilities at Pipe-stem State Park, Summers County, West Virginia, and Twin Falls State Park, Wyoming County, West Virginia. The bid was accepted and the contract in the total amount of $11,576,300 was awarded to Baltimore, and entered into by the parties on February 19, 1968. On February 27, 1968, a Notice to Proceed directed Baltimore to commence work on April 1, 1968. The contract called for completion within 460 calendar days, and provided for the assessment of liquidated damages in the amount of $150 “for each consecutive calendar day after the above established completion date that the work remains incomplete”.

Early in April, 1968, DNR, having become disenchanted with TAC by reason of a lack of communication and cooperation in the correction of design errors and other disagreements, canceled its contract with TAC, thereby also terminating the services of IBA, and employed Zando, Martin & Milstead (ZMM), Architects and Engineers, of Charleston, West Virginia.

Baltimore has filed three separate claims, aggregating $1,191,-944.54, arising out of its contract with DNR, as follows:

1. For failure to provide and maintain access roads for the Pipe-stem and Twin Falls projects, Baltimore’s petition claims damages for direct expenses of providing access, additional overhead expenses due to delay, additional heating expense due to delay, and loss of efficiency at Pipestem, in the amount of $506,353.08, and for labor and truck rental expense for transporting workers from highway to job site, labor, equipment, utilities attributable to delay and other additional expenses at Twin Falls in the amount of $98,151.67, a total of $681,733.82. Baltimore now claims a larger sum “as adjusted in accordance with the testimony introduced at trial” in the new total amount of $712,105.36.

[151]*1512. For delays resulting from errors in design of window walls and failure to timely approve window wall shop drawings, Baltimore’s petition alleges damages in the amount of $313,697.57. Eliminating the overall delay expense in connection with the alleged failure of DNR to furnish road access to both projects, and further eliminating certain items which were withdrawn during the course of the hearings, this claim has been reduced by Baltimore to $45,778.86.

3. For additional unanticipated expenses in drilling jack holes for the two main lodge passenger elevators at Pipestem, Baltimore’s petition claims damages in the amount of $54,061.75, and indirect expense due to delay in the amount of $142,451.40, a total of $196,513.15. Counsel for Baltimore have withdrawn the claim for delay, leaving an alleged loss of $54,061.75.

Baltimore’s claim in this case, as modified, is for damages in the total amount of $811,945.97.

Much testimony was heard and many of Baltimore’s exhibits were admitted over objections of DNR, subject to later determination by the Court as to relevance and materiality. All testimony and exhibits pertaining to design errors and inaccuracies in surveys noted prior to bidding but not confirmed thereafter, are considered by the Court not to be material to the issues and will have no bearing on the Court’s decision in this case.

This case is complicated by a number of “errors and omissions” attributable in considerable degree to both the claimant and the respondent. It is clear that Baltimore hurried into this contract, bidding with knowledge of uncertainties and apparently counting on change orders to make up for any substantial misunderstandings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lincoln v. United States
49 Ct. Cl. 300 (Court of Claims, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
10 Ct. Cl. 148, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baltimore-contractors-inc-v-department-of-natural-resources-wvctcl-1975.