Ballinger v. Luers, Unpublished Decision (1-26-2004)

2004 Ohio 284
CourtOhio Court of Appeals
DecidedJanuary 26, 2004
DocketCase No. CA2003-04-053.
StatusUnpublished
Cited by1 cases

This text of 2004 Ohio 284 (Ballinger v. Luers, Unpublished Decision (1-26-2004)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ballinger v. Luers, Unpublished Decision (1-26-2004), 2004 Ohio 284 (Ohio Ct. App. 2004).

Opinion

OPINION
{¶ 1} Plaintiff-appellant, Jim Ballinger, acting pro se, appeals from the Warren County Common Pleas Court's decision awarding defendant-appellee, James K. Luers, $2,260 for breach of contract, and $700 for slander of title.

{¶ 2} Ballinger is a Consulting Engineer and Surveyor. At the time of this dispute, Luers was the owner of a 13.896-acre tract of land situated in Franklin Township, in Warren County, Ohio. In February 2001, Luers decided to subdivide this property for a project known as "Timberwind Subdivision." In furtherance of the project, Luers' son, Tim, acting on Luers' behalf, orally contracted with Ballinger to have him provide engineering and surveying services for the project, for $1,800. Luers and Ballinger subsequently modified the contract price by increasing it to $2,000.

{¶ 3} Luers' objective in contracting for Ballinger's services was to obtain a final plat for the property, approved for recordation by the Warren County Regional Planning Commission ("WCRPC") and other governmental authorities. While the parties never set a specific date by which the engineering and surveying services had to be completed, both parties contemplated that a preliminary plat would be approved at the WCRPC's March 2001 meeting.

{¶ 4} In March 2001, Ballinger billed Luers for $800, for locating the property's boundaries. Luers paid this amount. Because certain problems arose regarding the plat's layout, the preliminary plat was not tentatively approved until June 28, 2001. On July 27, 2001, Luers, having become increasingly dissatisfied with Ballinger's work, sent him a letter demanding that Ballinger produce a final plat, suitable for recordation, by August 3, 2001, at which time he would be paid the remaining $1,200 balance of his fee. In the letter, Luers accused Ballinger of bad faith and incompetence, and threatened to complain to "the appropriate State Registering Agency, County Offices, and Better Business Bureau and pursue recuperation (sic) of expenses."

{¶ 5} In September 2001, Ballinger completed a final plat, lacking only his signature and seal. On September 24, 2001, Luers went to Ballinger's office, prepared to pay him the remaining $1,200 balance due on their contract in exchange for the signed and sealed final plat. However, Ballinger refused to turn over the plat to Luers unless he signed a document that Ballinger had drafted, entitled "Release and Termination of Services." Ballinger's release included provisions stating he was "sorry he got involved with amateurs and neophytes who refuse to take his advice and counsel and then blame him for events that work out as he had warned they would[;]" that he "no longer wishes to be `the engineer of distressed properties[;]'" and that "[s]ince [Luers] has no faith in his engineer, and since [he] has no intention of working for a client who has no money[,] * * * [t]he approved final plat and corners marked is the best place to conclude business."

{¶ 6} Luers refused to sign the release until he could consult with his attorney. On October 2, 2001, Luers' attorney went to Ballinger's office, where Ballinger told him that in order to obtain the final plat, Luers would now have to sign both the Release and Termination of Services, and an "Addendum." The proposed Addendum stated that "Ballinger on further reflection realized" that the $2,000 contract price covered only the location of the boundaries, and not the entire job. The addendum further stated that:

{¶ 7} "The fair and reasonable fee for the engineering and surveying services that has [sic] been received is $4587.78 of which $800.00 had been paid.

{¶ 8} "The balance due of $3,787.78 will be tendered by certified check. Upon receipt Ballinger will seal and sign the record plat."

{¶ 9} Luers refused to sign the Release and Termination of Services or the Addendum, and refused to pay the additional $2,587.78 that Ballinger had sought to add to the contract price with the Addendum. Luers contracted with Paul A. Rodenbeck, a registered engineer and surveyor, to complete work on the project at a cost of $3,460. Rodenbeck estimated that the work Ballinger had completed reduced his work by 25 percent to 35 percent. Rodenbeck subsequently sent a letter to the Ohio Registration Board of Engineering and Surveyors, regarding Ballinger's proposed final plat of Timberwind Subdivision. In the letter, Rodenbeck cited a potential violation of the "Minimum Standards for Boundary Surveys," and enumerated numerous inconsistencies between Ballinger's unrecorded final plat, and Rodenbeck's final plat and Luers' deed.

{¶ 10} On October 15, 2001, Ballinger filed an affidavit for a mechanic's lien on the property, claiming he was owed $3,787.78, for engineering and surveying services. Luers obtained a release of the mechanic's lien by posting a $7,575.56 bond, at a cost of $700, including attorney fees. On January 16, 2002, Luers had Ballinger served with a notice to commence suit.

{¶ 11} On March 19, 2002, Ballinger filed a complaint against Luers, seeking $3,787 in damages for unjust enrichment, and additional $3,787 for damages to his health and professional reputation. Luers filed a counterclaim for breach of contract, slander to title, and unjust enrichment. The matter was referred to a magistrate.

{¶ 12} In January 2003, the magistrate held a hearing on the matter. On March 6, 2003, he issued a decision, finding against Ballinger and in favor of Luers, with regards to their respective claims. The magistrate determined that Luers was entitled to judgment in the amount of $2,260 on his breach of contract claim, plus prejudgment and post-judgment interest, and $700 for slander of title, with post-judgment interest. Ballinger filed objections to the magistrate's decision. On April 15, 2003, the trial court overruled Ballinger's objections after noting that Ballinger had failed to file a transcript of proceedings as required by Civ.R. 53. The trial court adopted the magistrate's findings of fact and conclusions of law as its own final order.

{¶ 13} Ballinger now appeals from the trial court's decision and raises several assignments of error.

Assignment of Error No. 1
{¶ 14} "The Magistrate (trial court) correctly found facts but came to the wrong conclusions."

{¶ 15} Ballinger describes the issue presented for review as follows:

{¶ 16} "The trial court effectively documentated [sic] appellants [sic] release [sic] but recission [sic] occurs two months earlier."

{¶ 17} Although Ballinger's arguments are difficult to follow, he apparently is arguing that Luers, by virtue of his July 27, 2001 letter, rescinded the parties' contract before he breached it. He also asserts that Luers' letter imposed new contractual obligations upon him. Ballinger appears to be contending that this alleged rescission gave him the right to insist that Luers sign the Release and Termination of Services, and Addendum that he drafted. Further, he appears to be asserting that he had a right to collect against Luers under the theories of unjust enrichment and quantum meurit. We disagree with each of these arguments.

{¶ 18} First, Luers' July 27, 2001 letter to Ballinger, demanding that a final plat, suitable for recordation, be produced by August 3, 2001, did not rescind the parties' agreement, nor was it an attempt by Luers to do so.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Telxon Corp. v. Smart Media, Unpublished Decision (11-23-2005)
2005 Ohio 6223 (Ohio Court of Appeals, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
2004 Ohio 284, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ballinger-v-luers-unpublished-decision-1-26-2004-ohioctapp-2004.