Ball, Ball & Brosamer, Inc. v. Commissioner

1990 T.C. Memo. 454, 60 T.C.M. 587, 1990 Tax Ct. Memo LEXIS 498
CourtUnited States Tax Court
DecidedAugust 22, 1990
DocketDocket No. 3553-87
StatusUnpublished
Cited by2 cases

This text of 1990 T.C. Memo. 454 (Ball, Ball & Brosamer, Inc. v. Commissioner) is published on Counsel Stack Legal Research, covering United States Tax Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ball, Ball & Brosamer, Inc. v. Commissioner, 1990 T.C. Memo. 454, 60 T.C.M. 587, 1990 Tax Ct. Memo LEXIS 498 (tax 1990).

Opinion

BALL, BALL AND BROSAMER, INC. AND BALL AND BROSAMER, J.V., A JOINT VENTURE, BALL, BALL AND BROSAMER, INC., TAX MATTERS PARTNER, Petitioner v. COMMISSIONER OF INTERNAL REVENUE, Respondent
Ball, Ball & Brosamer, Inc. v. Commissioner
Docket No. 3553-87
United States Tax Court
T.C. Memo 1990-454; 1990 Tax Ct. Memo LEXIS 498; 60 T.C.M. (CCH) 587; T.C.M. (RIA) 90454;
August 22, 1990, Filed

*498 Decision will be entered for the petitioner.

Fielding H. Lane and Mary Eileen Butler, for the petitioner.
James W. Clark, for the respondent.
KORNER, Judge.

KORNER

MEMORANDUM FINDINGS OF FACT AND OPINION

In his Final Partnership Administrative Adjustment, respondent determined that the partnership failed to include $ 3,391,053 in gross income attributable to the completion of a long-term contract in 1983. The sole issue to be decided is whether Job 553, a heavy construction job, was completed for Federal income tax purposes under the completed contract method of accounting in 1983 or 1984.

FINDINGS OF FACT

Some of the facts have been stipulated and are so found. The stipulation of facts and exhibits attached are incorporated by this reference.

Ball, Ball*499 & Brosamer, Inc. is the tax matters partner of Ball, Ball & Brosamer, Inc. and Ball & Brosamer, J.V., the partnership. The tax matters partner had its principal place of business in Alamo, California, at the time the petition was filed. The partnership used the calendar year as its annual accounting period and elected to report the income from its long-term contracts pursuant to the completed contract method of accounting.

The partnership commenced business in January, 1981, and was engaged in heavy construction work, particularly for government agencies. Job 553, whose completion is the subject of this opinion, was performed pursuant to a contract between the partnership and the United States Department of the Army, Corps of Engineers.

The contract was part of a $ 500 million project for the construction of a space shuttle complex at Vandenberg Air Force Base. This complex included, among other things, a space shuttle launch facility, a space shuttle maintenance check out facility, and a space shuttle mate/de-mate facility. As part of the overall project, the partnership's specific contractual obligations were as follows:

Removal of existing bituminous runway pavement and*500 replacement with concrete pavement; concrete runway extension overruns and shoulders; airfield lighting and NAVAIDS; regulator building; drainage; utility relocation; laser tracking system; and other appurtenant work; towway (V-80 partial); apron (V-19); all on North Vandenberg Air Force Base, California.

Funding for the construction of the space shuttle complex was provided by a number of different appropriations authorized by Congress for the different facilities or aspects of the project. As part of the Government's management of the construction of the space shuttle complex, the Government "packaged" the various types or items of work required for construction of the different space shuttle facilities into contracts to provide efficient work units, using parts of the different Congressional appropriations to fund the work included within each contract. This packaging was done based on the Government's determination of how best to accomplish the desired work, how best to minimize disruptions, and how best to obtain the most competitive or best price for the work.

The partnership bid all of the work in the contract as a unit for an initial contract price of $ 19,976,745. The*501 partnership determined the bid prices for the various items of work included in the contract by spreading the contract price or total costs for performance of the contract as a whole, including mobilization, equipment, and other costs. During the course of the partnership's work on the contract, 57 written modifications to the contract were issued reflecting various changes in the work ordered by the contracting officer, which increased the total consideration that was received by the partnership to $ 22,152,866.50.

Payments were based upon estimates, approved by the Contracting Officer, of the partnership's progress on the job. The performance report for the period ending December 31, 1983, reflected that all elements of the contract were approximately 100 percent complete.

Construction of all elements of the shuttle facility at Vandenberg Air Force Base was not projected to be completed until 1985, although the contract between the partnership and the Government required the partnership to complete the contract by September 10, 1983, before change orders.

Part of the partnership's contractual obligations was to build an additional 7,000 feet of concrete runway, plus extensions*502 and overruns; in addition, the partnership was to remove 6,000 of the existing 8,000 feet of runway and rebuild it with concrete. Petitioner initially built the new runway, leaving the old one open for aircraft usage. After the new runway was completed, the petitioner then closed, removed, and rebuilt the old section. The entire 15,000 foot runway was sufficiently completed for use by aircraft for landing and takeoff by the summer of 1983. The Air Force took beneficial occupancy of the runway, apron, and appurtenant facilities in September 1983, and placed them in regular service at that time.

As part of the contract, the partnership was required to relocate Tangair Road on Vandenberg Air Force Base because the old road came too close to a space shuttle check-out facility, which was deemed to be a possibly hazardous facility. The work on Tangair Road was initially completed in 1982, and the road was heavily traveled. Problems became apparent with the new road as it began to deteriorate, and it was closed in 1983 so that petitioner could perform additional work. Tangair Road was reopened in May 1983, after petitioner made modifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ball, Ball & Brosamer, Inc. v. Commissioner
964 F.2d 890 (Ninth Circuit, 1992)
Ball v. Commissioner Internal Revenue Service
964 F.2d 890 (Ninth Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
1990 T.C. Memo. 454, 60 T.C.M. 587, 1990 Tax Ct. Memo LEXIS 498, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ball-ball-brosamer-inc-v-commissioner-tax-1990.