Baldwin v. Polti

101 S.W. 543, 45 Tex. Civ. App. 638, 1907 Tex. App. LEXIS 399
CourtCourt of Appeals of Texas
DecidedMarch 27, 1907
StatusPublished
Cited by11 cases

This text of 101 S.W. 543 (Baldwin v. Polti) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baldwin v. Polti, 101 S.W. 543, 45 Tex. Civ. App. 638, 1907 Tex. App. LEXIS 399 (Tex. Ct. App. 1907).

Opinion

NEILL, Associate Justice.

This suit was brought by Charles Polti against David G. Baldwin to recover $1,371.70, with interest thereon from the 8th of April, 1905, alleged to be a balance due for work done by the plaintiff on a certain building of the defendant, and to foreclose a mechanic’s lien on it and the lots upon which it is located.

The substance of plaintiff’s allegations is, that on February 1, 1904, he entered into a written contract with defendant to do certain stone work on the east and south walls of the building, etc., specified in the contract, for which he was to be paid by defendant a sum not to exceed, in any event, $7,885; that shortly after the contract was made it was modified by an oral agreement between the parties, whereby it was agreed that for doing the labor and furnishing the material stipulated in the written contract plaintiff should receive the sum of $7,685. That plaintiff fully performed his part of the contract, and defendant becamé indebted to him, according to it's terms in the sum of $7,685. That during the construction of the building under the contract as modified by the oral agreement, defendant made certain changes in the plans and specifications, adding a large amount of ruble and cut-stone work, making changes in the arches on the first floor, and various other changes shown by an exhibit attached to and made a part of plaintiff’s petition; that such changes required extra work, which was done by plaintiff at the special instance and request of defendant, for which plaintiff is entitled to payment, over and above the original contract price ($7,685), of its reasonable value, which he alleges is, as shown by the various items appearing in the exhibit attached to his petition, $2,051.45. That he has been paid on the contract $8,364.75, and there is still due him for extra work done the sum of $1,371.07, for which he prayed judgment.

The defendant answered by a general denial and specially pleaded, that the original written contract was, as alleged by the plaintiff, changed and modified; but that it was understood and 'agreed between the parties that no additional price should be charged upon the extra openings added to the original plans and specifications of the building, nor any extra charge for any extra work in increasing the thickness of the walls from that originally designed as shown from the plans and specifications of the building, and that, it was agreed when such work was done that the sum of $7,685 should include the consideration for all such extra work as might be done by reason of the necessity of creating the extra openings and increasing the thickness of the walls of the building, such modifications being fully understood by the parties when they orally changed the original contract. Defendant also pleaded in reconvention that certain work on a part of the building was not in accordance with *640 the contract and defective for that reason, and asked judgment for damages against plaintiff on proof of the matters so pleaded.

The trial of the. case resulted in a verdict and judgment in favor of the plaintiff for $1,064.07 with interest at the rate of 6 percent per annum from January 1, 1906, amounting in the aggregate to $1,091.73-, together with a foreclosure of his mechanic’s and builder’s lien on the building and lots upon which it is situated.

Conclusions of Fact. It Avill be seen from our statement of the pleadings, that plaintiff’s claim for extra work is $2,051.45; which, added to the sum to be paid according to contract, makes $9,736.45, which he should have been paid in all. He was paid by the defendant $8,364.75, which, according to plaintiff’s statement, would leave a balance due him of $1,371.70. The defendant disputed several items in plaintiff’s account which amount in the aggregate to $1,061.25. This is in effect an admission by the defendant that he owes plaintiff $310.45 of the $1,371.70 claimed by him, and shows that the real contention between them is in regard to the $1,061.25 involved in the disputed items in plaintiff’s account.

The solution of the matter in dispute depends upon whether the material and labor embraced in the several items Avere comprehended by the contract. If they Avere, they could not have been deemed extras; and plaintiff, in receiving the amount of money agreed upon by the contract, was paid for them. If, hoAA'ever, they Avere not contemplated by the contract, but were required by changes made in the plans and specifications of the building after the contract was entered into, then, they should be regarded as extras, and plaintiff would be entitled to recover their reasonable value. There was evidence tending to support the latter theory, contended for by the plaintiff, and, in deference to the verdict, we find accordingly.

Conclusions of Law. 1. As to the items in dispute, the court instructed the jury that if it believed from the evidence the work was not contemplated by the parties, in the oral agreement modifying the original contract and did not come within its terms, but if it believed from a preponderance of the evidence that any or all of said work Avas done by Polti outside of the oral contract, and was done at the special instance and request of BaldAvin or his superintendent, Stewart, as extra, to find for plaintiff as to such items, if any, as the jury believed from a preponderance of the evidence was done outside of said contract as extra at the special instance and request of Bald-win or his superintendent; and to find against plaintiff as to all sufih items, if any, as it believed from the evidence fell within the provisions and terms of the oral contract, or said original contract as modified by the oral agreement.

This portion of the charge is objected to by the first assignment of error because there were no allegations in plaintiff’s pleadings of the agency of Stewart as superintendent of the defendant, or that he was vested with authority to authorize changes or contract for extra work to be done upon the building, such issue being only raised by the evidence.

It will he observed that it is not questioned that Stewart was defendant’s superintendent and agent in the construction of the building, or that he was vested as such agent with authority to authorize changes and contract for the extra work; but the objection goes to the pleadings and *641 not to the evidence, which is admitted by the assignment as tending to show such agency and authority!

It is a general rule, that the act of an agent is the act of his principal; which is expressed in the maxim, qui facit per alium, fácil per se. And as there was no question as to Stewart’s agency and authority, proof of his doings within the scope of his agency, supports the allegation that they were the acts of the defendant. Therefore, the charge is not obnoxious to the objection raised by the assignment.

2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Collins v. Hall
161 S.W.2d 311 (Court of Appeals of Texas, 1942)
Belcher v. Bullion
121 S.W.2d 483 (Court of Appeals of Texas, 1938)
Griffin v. Berry
6 S.W.2d 183 (Court of Appeals of Texas, 1928)
Ferguson v. Lewis
290 S.W. 858 (Court of Appeals of Texas, 1927)
Jackson v. Dickey
281 S.W. 1043 (Texas Commission of Appeals, 1926)
Beckham v. Cayton
262 S.W. 840 (Court of Appeals of Texas, 1924)
Lewis v. Farmers' & Mechanics' Nat. Bank of Ft. Worth
204 S.W. 888 (Court of Appeals of Texas, 1918)
Nimmo v. O'Keeff
204 S.W. 883 (Court of Appeals of Texas, 1918)
Orient Land Co. v. Reeder
173 S.W. 939 (Court of Appeals of Texas, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
101 S.W. 543, 45 Tex. Civ. App. 638, 1907 Tex. App. LEXIS 399, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baldwin-v-polti-texapp-1907.