Baldwin Enterprises, Inc. v. Articon Hotel Services, LLC

2021 IL App (5th) 200150-U
CourtAppellate Court of Illinois
DecidedFebruary 18, 2021
Docket5-20-0150
StatusUnpublished

This text of 2021 IL App (5th) 200150-U (Baldwin Enterprises, Inc. v. Articon Hotel Services, LLC) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baldwin Enterprises, Inc. v. Articon Hotel Services, LLC, 2021 IL App (5th) 200150-U (Ill. Ct. App. 2021).

Opinion

2021 IL App (5th) 200150-U NOTICE NOTICE Decision filed 02/18/21. The This order was filed under text of this decision may be NO. 5-20-0150 Supreme Court Rule 23 and is changed or corrected prior to the filing of a Petition for not precedent except in the

Rehearing or the disposition of IN THE limited circumstances allowed the same. under Rule 23(e)(1). APPELLATE COURT OF ILLINOIS

FIFTH DISTRICT ______________________________________________________________________________

BALDWIN ENTERPRISES, INC., ) Appeal from the ) Circuit Court of Plaintiff and Counterdefendant, ) Jefferson County. ) ) v. ) No. 17-L-28 ) ARTICON HOTEL SERVICES, LLC, ) ) Defendant, Counterplaintiff, and Third-Party ) Plaintiff, ) ) v. ) ) PEOPLES NATIONAL BANK, N.A., UNKNOWN ) OWNER, and UNKNOWN NECESSARY PARTIES, ) ) Third-Party Defendants ) ) (Articon Hotel Services, LLC, Counterplaintiff and Third- ) Party Plaintiff-Appellant; Baldwin Enterprises, Inc., ) Honorable Counterdefendant-Appellee, and Peoples National Bank, ) Michael J. Valentine, N.A., Third-Party Defendant-Appellee). ) Judge, presiding. ______________________________________________________________________________

JUSTICE MOORE delivered the judgment of the court. Presiding Justice Boie and Justice Wharton concurred in the judgment.

ORDER

¶1 Held: We reverse those portions of the circuit court’s order that granted a summary judgment to hotel owner and bank on contractor’s claim for a mechanic’s lien on the basis of provision in escrow agreement promising full performance for the contract price free and clear of mechanic’s liens, as such provision did not constitute a lien waiver where a dispute between the parties halted performance and

1 payment, and despite unambiguous terms of subsequent lien waivers executed in conjunction with progress payments, whether owner and/or bank, innocently and in good faith, relied upon the waivers as full waivers as to future payments on the construction contract is a question of fact which determines whether parol evidence, such as trade custom and usage, may be considered to determine the intent of the parties. Circuit court erred in holding that provision in escrow agreement executed at beginning of project subordinated contractor’s mechanic’s lien to bank’s lien in funding project because such provision, if construed to provide for such subordination, is prohibited by section 1(d) of the Mechanics Lien Act (770 ILCS 60/1(d) (West 2016)) until at least 50% of construction loan has been disbursed on the project.

¶2 The counterplaintiff and third-party plaintiff, Articon Hotel Services, LLC (Articon),

appeals, pursuant to Illinois Supreme Court Rule 304(a) (eff. Mar. 8, 2016), the portions of the

March 30, 2020, order of the circuit court of Jefferson County, which granted summary judgment

in favor of the counterdefendant, Baldwin Enterprises, Inc. (Baldwin), and the third-party

defendant, Peoples National Bank (Bank), on Articon’s claim for a mechanic’s lien on hotel

property located in Mt. Vernon. For the following reasons, we reverse and remand for further

proceedings. 1

¶3 BACKGROUND

¶4 Baldwin filed an amended complaint for breach of contract against Articon in the circuit

court of Jefferson County on August 4, 2017, and a second amended complaint on January 17,

2018. According to the complaint, Baldwin and Articon entered into a contract in 2015 whereby

Articon agreed to provide labor and materials necessary for the renovation of Baldwin’s existing

Holiday Inn hotel in Mt. Vernon and conversion to a 200-guestroom Double Tree by Hilton, in

exchange for a payment of $6,065,298.82. The complaint alleges that although Baldwin had paid

Articon approximately 73% of the contract price, Articon had completed only approximately 10

1 Articon also appeals the circuit court’s order denying its motion for summary judgment as to its claim for a mechanic’s lien. However, because an order denying a motion for summary judgment does not finally determine any count or issue in this action, it is not appealable pursuant to Illinois Supreme Court Rule 304(a) (eff. Mar. 8, 2016). 2 to 15% of the construction on the property. The complaint further alleges that Articon stopped

working and abandoned the project on February 27, 2017, and the estimated cost to complete the

work is more than $1,549,748.06. The complaint acknowledges that Articon submitted draw

requests on the project that Baldwin refused to pay in the amount of $930,108.17. However, the

complaint alleges these pay requests were based on Articon’s incorrect representation that 87.14%

of the work had been completed under the contract, which is why Baldwin refused to pay. The

complaint also outlines areas in which Baldwin alleges Articon’s work on the project was

defective. Count II alleges a cause of action for slander of title due to a mechanic’s lien Articon

filed against the hotel property on March 24, 2017, which the complaint alleges was improper.

¶5 On August 8, 2017, Articon filed a counterclaim against Baldwin, and a third-party

complaint against the Bank, in its capacity as a mortgage holder for the subject property. Count I

of Articon’s counterclaim/third-party complaint requested to foreclose a mechanic’s lien on the

property in the amount of $930,108.33, the amount which Articon alleges Baldwin still owes for

labor and materials it expended pursuant to the contract. The counterclaim further alleges causes

of action against Baldwin for breach of contract, breach of the duty of good faith and fair dealing,

and quantum meruit.

¶6 On September 22, 2017, Baldwin filed an answer and affirmative defenses to Articon’s

counterclaim. In its sixth affirmative defense, Baldwin asserted that Articon waived its right to

assert a mechanic’s lien in two different documents. First, a “Waiver of Claims for Payment

Agreement” signed by Articon’s representative on January 17, 2017, is attached to Baldwin’s

answer as Exhibit A. This document is a “fill-in-the-blank” form which lists Articon as the

contractor and Baldwin as the owner. The form has “check-the-box” options to designate the type

of waiver the contractor is making in return for the payment indicated. The first option is titled

3 “Full/Final Waiver- Missouri Residential Jobs,” the second option is titled “Full/Final Waiver- any

Commercial Jobs and Illinois Residential Jobs,” and the third option is titled “Partial Waiver.” In

the case of Exhibit A, the “filled-in” information provides that, on the project/real property known

as “Holiday Inn- Mt. Vernon, IL,” and in consideration for receipt of $600,277.20, Articon is

subject to the second option, “Full/Final Waiver- any Commercial Jobs and Illinois Residential

Jobs.” Second, Baldwin attached a document entitled “Construction Disbursing Escrow

Agreement No. 154162” (Escrow Agreement) as Exhibit B to its answer. This document, which is

entered into between Benchmark Title Company, LLC as escrowee, Baldwin as owner, Articon as

contractor, and the Bank as mortgagee, appears to have been executed on October 15, 2015. We

will discuss the specific language of these documents in the analysis portion of this order.

¶7 On September 25, 2017, the Bank filed its answer and affirmative defenses regarding count

I of Articon’s counterclaim/third-party complaint which sought to foreclose the mechanic’s lien.

The Bank also raised waiver of the mechanic’s lien as an affirmative defense, for the same reasons

as set forth by Baldwin.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Premier Electrical Construction Co. v. La Salle National Bank
477 N.E.2d 1249 (Appellate Court of Illinois, 1984)
Merchants Environmental Industries, Inc. v. SLT Realty Ltd. Partnership
731 N.E.2d 394 (Appellate Court of Illinois, 2000)
Luczak Brothers, Inc. v. Generes
451 N.E.2d 1267 (Appellate Court of Illinois, 1983)
In re Marriage of Callahan
2013 IL App (1st) 113751 (Appellate Court of Illinois, 2013)
Burgoyne v. Pyle
261 Ill. App. 356 (Appellate Court of Illinois, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
2021 IL App (5th) 200150-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baldwin-enterprises-inc-v-articon-hotel-services-llc-illappct-2021.