Baldwin Co. v. Rainey Construction Co.

229 Cal. App. 3d 1053, 280 Cal. Rptr. 499, 91 Daily Journal DAR 5143, 91 Cal. Daily Op. Serv. 3198, 1991 Cal. App. LEXIS 404
CourtCalifornia Court of Appeal
DecidedApril 30, 1991
DocketG009556
StatusPublished
Cited by5 cases

This text of 229 Cal. App. 3d 1053 (Baldwin Co. v. Rainey Construction Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baldwin Co. v. Rainey Construction Co., 229 Cal. App. 3d 1053, 280 Cal. Rptr. 499, 91 Daily Journal DAR 5143, 91 Cal. Daily Op. Serv. 3198, 1991 Cal. App. LEXIS 404 (Cal. Ct. App. 1991).

Opinion

Opinion

MOORE, J.

Plaintiff and appellant The Baldwin Company (Baldwin) appeals a judgment of the superior court confirming an arbitration award in *1055 favor of defendant and respondent Rainey Construction Company, Inc. (Rainey). Baldwin contends the court erred by confirming a portion of the arbitrator’s award while rejecting the balance, and that, accordingly, the judgment must be reversed with directions to vacate the award.

Rainey contends the appeal is frivolous and asks that it be summarily dismissed. It seeks sanctions against Baldwin and/or its counsel in the sum of $12,000 plus costs.

Facts

On October 21, 1987, Rainey, a general contractor, contracted with Baldwin, a developer, to construct Portola Hills Fire Station 42. The contract required that all disputes be submitted to arbitration before the American Arbitration Association (AAA).

Baldwin contends the project was completed 83 days after the date scheduled for completion. Pursuant to the contract between the parties, Rainey could receive extensions of time for delays which were unforeseeable, beyond the control or without the fault or negligence of Rainey, or the responsibility of the owner. Rainey submitted a request to be paid for such delay days, which was reviewed by Baldwin and its project architect. Under authority granted by the general conditions of the contract, the project architect determined Rainey was entitled to no extensions of time or delay days because the request was untimely.

As a result, Rainey contended it was entitled to contractual and other damages. In addition, Rainey claimed the contract had been anticipatorily breached by Baldwin, which indicated it would refuse to pay an additional $10,000 which it was withholding. The contract allowed Baldwin to retain $10,000 from the final payment for 365 days following recordation of the notice of completion. The $10,000 was withheld as a warranty retention, to be refunded less any claims made for warranty performance and correction of contract deficiencies. As of the arbitration date, no notice of completion had been filed on the project and the one-year time period for the warranty retention had therefore not yet begun.

Baldwin refused to pay any of the monies demanded by Rainey, claiming it was damaged by delays with regard to the project. The matter proceeded to an arbitration at AAA on September 12, 1989. On October 11, following the presentation of evidence and argument by the parties, the arbitrator made the following award: “1. The Arbitrator finds in favor of [Rainey], in the amount of $57,109.20. fl[] 2. The Arbitrator finds that [Rainey] is entitled to payment of $10,000 withheld as a warranty retention pursuant to *1056 . . . the contract less any claims made against the retention for warranty performance and correction of construction deficiencies. [If] 3. [The parties] shall bear their own costs and expenses of arbitration.”

On October 13 Baldwin filed a request for clarification and objection to the award under Code of Civil Procedure sections 1283.4 and 1284. 1 The arbitrator did not act on the request for clarification within 30 days and therefore the award became final. (§ 1284.)

On February 6, 1990, Rainey filed a petition to confirm award and for entry of judgment. Baldwin filed opposition on February 28, and the matter was set for hearing on March 21. Following the hearing, the superior court ordered judgment entered for Rainey and against Baldwin in the amount of $57,109.20. The court held the additional $10,000 declared to be due Rainey was merely “an advisory opinion.” As noted, no notice of completion had been filed on the project and the one-year time period for the warranty retention had therefore not yet begun. Accordingly, that portion of the award was denied without prejudice to Rainey’s rights to bring a proceeding for same again at some future date. The court ordered the petition to confirm the arbitration award “granted in part and denied in part” as follows: “It Is Ordered that the award ... is confirmed in part in that a judgment is to be entered in favor of [Rainey] and against [Baldwin] in the amount of $57,109.20. With regard to the award of $10,000.00, the Court finds this award to be an advisory opinion upon which a judgment cannot be entered at this time. Therefore with regard to the $10,000.00 portion of the arbitration award, the Petition is denied without prejudice to [Rainey’s] rights to those monies.” The court’s March 21 minute order stated the petition to confirm the arbitration award and for entry of judgment was granted and that the “court confirmed arbitration award in amount of $57,109.20.”

On April 9 Baldwin filed an objection to the order confirming the arbitration award. In its opening brief, Baldwin represents to this court that its objection requested “clarification of the court’s confirmation in part and denial in part of the arbitration award.” However, Baldwin is not candid. First, the page reference cited by Baldwin to support its contention is to the court’s minute order. Second, the objection simply requested “any reference to costs ... be stricken from the judgment,” inasmuch as Rainey failed to request costs as part of its petition, was not awarded costs as part of the court’s order, and did not disclose the nature of any costs claimed, nor file a memorandum of costs. At no time did Baldwin make any other objection to the form or content of the court’s order confirming arbitration award.

*1057 Judgment was entered on April 11, and this appeal followed. 2

I

Jurisdiction of Court to Correct Award

Baldwin’s sole contention on appeal is that the superior court exceeded its jurisdiction in confirming a portion of the arbitration award and rejecting the balance. Baldwin argues the court erred because it neither confirmed or vacated the award, but chose a “hybrid” of confirming in part and vacating in part. It argues that “that procedure, although well intended, is not permitted under the Code.” Our review of the record leads us to conclude the court, largely at the urging of Baldwin, properly confirmed the award of $57,109.20, then corrected the award as to the $10,000 “without affecting the merits of the decision upon the controversy submitted,” as permitted by section 1286.6.

Section 1285 provides in pertinent part, “Any party to an arbitration in which an award has been made may petition the court to confirm, correct, or vacate the award.” Section 1285.2 provides that “[a] response to a petition . . . may request the court to dismiss the petition or to confirm, correct or vacate the award.” In addition, section 1286.6 provides, “[T]he court, unless it vacates the award . . . , shall correct the award and confirm it as corrected if the court determines that: ... [H] (b) [t]he arbitrators exceeded their powers but the award may be corrected without affecting the merits of the decision upon the controversy submitted . . . .”

Prior to the amendment of section 1286 in 1961, the trial court had the power to modify and correct awards, giving effect to their intent and promoting justice between the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cooper v. Lavely & Singer Professional Corp.
230 Cal. App. 4th 1 (California Court of Appeal, 2014)
Opinion No. (2004)
California Attorney General Reports, 2004
Armendariz v. Found. Health Psychcare Servs., Inc.
6 P.3d 669 (California Supreme Court, 2000)
Lopes v. Millsap
6 Cal. App. 4th 1679 (California Court of Appeal, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
229 Cal. App. 3d 1053, 280 Cal. Rptr. 499, 91 Daily Journal DAR 5143, 91 Cal. Daily Op. Serv. 3198, 1991 Cal. App. LEXIS 404, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baldwin-co-v-rainey-construction-co-calctapp-1991.