Baker v. Western Casualty & Surety Co.

411 P.2d 711, 196 Kan. 345, 1966 Kan. LEXIS 280
CourtSupreme Court of Kansas
DecidedMarch 5, 1966
Docket44,354
StatusPublished
Cited by7 cases

This text of 411 P.2d 711 (Baker v. Western Casualty & Surety Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baker v. Western Casualty & Surety Co., 411 P.2d 711, 196 Kan. 345, 1966 Kan. LEXIS 280 (kan 1966).

Opinion

The opinion of the court was delivered by

Hatcher, C.:

This is an appeal from a judgment in an action for damages for the alleged breach of a contract.

There is no substantial dispute as to the basic facts.

Inasmuch as the Bowen Construction Company is the principal party and the Western Casualty Company is an insurer raising no separate issues, it will save confusion if we treat the Bowen Construction Company as the only defendant and appellant in identifying the parties.

In the early summer of 1961, plaintiff had been an unsuccessful bidder on a state highway prime contract and contacted the Bowen *346 Construction Company, the successful bidder, in reference to the possibility of obtaining a subcontract to supply the necessary BC-1 aggregate. After some negotiation a subcontract was entered into between plaintiff and defendant, the Bowen Construction Company. Under the principal provisions of this contract Baker was to supply all of the necessary ingredients for the BC-1 aggregate. He was to make delivery at the rate of 1,000 tons per day and was to be paid $1.30 per ton on the 10th of each month for all materials delivered in the preceding month on quantities to be determined by state highway commission weights.

In case the plaintiff defaulted and refused to correct the default, defendant was given the right to complete the contract. In case the cost of completing the contract was less than the contract price the plaintiff was to receive the difference and if the cost were higher plaintiff was to pay defendant the difference.

Sometime in July, plaintiff commenced delivering rock to the hot mix plant site in preparation for the work. He brought in approximately 5,000 or 6,000 tons of rock. This rock was rejected by the engineer for the State Highway Commission as being unsatisfactory for BC-1 aggregate. Plaintiff was so notified on July 17th, and requested to remove the rock from the highway right-of-way. Plaintiff failed to do so and defendant moved the rock to one side with a bulldozer in order to set up the hot mix plant. Defendant set up the hot mix plant on the rock that could not be successfully dozed to one side.

On July 24, prior to commencement of the production of asphalt, at a meeting attended by plaintiff, defendant’s representative and the highway engineer, it was agreed to try to produce BC-1 by using a mixture of 30% rock, 15% lime and 55% sand and gravel. The highway engineer set the gates on the hot mix plant and determined how much of each type of material was fed into the machine. The contractor cannot change these settings without the state’s approval. Production of asphalt was commenced on July 28th, and continued on July 29th, with this mixture. During these two days plaintiff furnished the sand, gravel, rock and lime. The highway engineer then condemned the lime and the rock that was being used as not meeting state specifications. Plaintiff was notified of this fact.

On August 9th, another meeting was held between plaintiff, defendant’s representatives and the highway engineer, and it was decided to try a mixture of 60% sand and gravel, 20% rock and 20% *347 lime from a different quarry. Production was commenced in August with production on each of the following dates: August 1, 7, 8, 10, 12,14,15,16,18,19, 21 and 31. During August there were 5,925.113 tons of RC-1 aggregate used making a total production up to September 1st, of 6,323,421 tons.

Plaintiff did not furnish any of the lime used on the project during August. He commenced hauling silt to the project on August 11th, and it was available after that date. The highway engineer, Moret, testified that it was his decision to use lime rather than silt for several days after silt was available because he knew the lime was producing a satisfactory mix and he didn’t know if a satisfactory mix could be obtained with the silt. If there was a change from lime to silt there would have to be a recalibration of the plant which would result in shutdown time. Difficulty had been encountered in finding a satisfactory mix. It cost the contractor approximately $40 to $50 per hour to shut the hot mix plant down as seven men are required to operate it. In addition there are 13 men on the road crew who cannot work if asphalt is not being produced. On September 7th, it was decided to switch from Valley Falls lime and rock to Oxendale rock and silt. This mixture was first used on September 8th.

Plaintiff continued delivering material until October 6, 1961. However, defendant had been required to furnish some lime.

On October 6th, plaintiff informed defendant that he would not haul any more material “until we get this thing settled and that money like you promised.” On October 7th, plaintiff told the highway engineer he was not hauling any more material until he got paid for that which he had already hauled and some different arrangement was made concerning the percentage of rock that was being used.

Plaintiff testified that he quit the job on October 6th, because defendant owed him $812.50 and that he was not going to furnish any more material unless defendant came up with some money.

After plaintiff quit on October 6th, defendant had to purchase some of the RC-1 materials from other sources and brought in bulldozers, high loaders, crusher, etc., to produce other BC-1 material.

On June 9th, 1964, plaintiff filed this action against the defendant in which he claimed $29,120.36 for material furnished and $8,640.60 for loss of profits on material not delivered under the contract. The defendant answered and also filed a counter claim and setoff in the amount of $22,487.75 being the difference between the contract price *348 with plaintiff and the cost of the additional material to defendant.

The case was tried to a jury which returned a verdict of $23,895.12 in favor of the plaintiff.

Defendant has appealed.

The appellant first complains of the failure of the court to direct a verdict for the reason the evidence shows as a matter of law that the defendant did not breach the contract when it withheld $812.50 from the August 21st, estimate as it was justified in so doing.

A determination of the question requires more detailed facts. On August 21st, the appellant mailed a pay estimate to appellee which read in part as follows:

“Item No. Item Description Original Contract Quantities Completed Quantity To Date Unit Unit Price Amount Earned To Date

Aggregate for Bit. Const. 6250 ton 1.30 8125.00

Total Earned To Date 8125.00

Less Retained 10% 812.50

Total 7312.50

Less-Previous Payments none

Amount Due This Estimate 7312.50”

The estimated amount due was not paid until sometime in September.

The plaintiff complained about the ten percent retained from time to time and on October 6, 1961, wrote a letter to the defendant stating:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Geo. C. Christopher & Son, Inc. v. Kansas Paint & Color Co.
523 P.2d 709 (Supreme Court of Kansas, 1974)
Woods v. Aetna Life Insurance
464 P.2d 183 (Supreme Court of Kansas, 1970)
Hildebrand v. Mueller
449 P.2d 587 (Supreme Court of Kansas, 1969)
Brown v. Godfrey
438 P.2d 117 (Supreme Court of Kansas, 1968)
Furstenberg v. Wesley Medical Center
436 P.2d 369 (Supreme Court of Kansas, 1968)
Virginia Surety Co. v. Schlegel
434 P.2d 722 (Supreme Court of Kansas, 1967)
Brewer v. Home-Stake Production Co.
434 P.2d 828 (Supreme Court of Kansas, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
411 P.2d 711, 196 Kan. 345, 1966 Kan. LEXIS 280, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baker-v-western-casualty-surety-co-kan-1966.