Baker v. Sweet Associates, Inc.

278 A.D.2d 615, 717 N.Y.S.2d 426, 2000 N.Y. App. Div. LEXIS 13159
Appellate Division of the Supreme Court of the State of New York·Decided December 14, 2000·Published·Cited by 1 cases

Opinion

Cardona, P. J.

Appeals (1) from an order of the Supreme Court (Marinelli, J.), entered June 14, 1999 in Albany County, which denied third-party plaintiffs motion to, inter alia, set aside the verdict, and (2) from that part of a judgment of said court, entered January 11, 2000 in Albany County, upon a verdict rendered in favor of third-party defendant against third-party plaintiff.

In October 1995, defendant Albany Water Board (hereinafter the Board) entered into a construction contract with defendant Sweet Associates, Inc. for the rehabilitation of the Feúra Bush Filtration Plant owned by it and defendant City of Albany. Sweet was retained as the general contractor to, inter alia, repair thousands of concrete panels underlying the roof which were cracked and spalled as well as to replace the outer roof membrane. Defendant Smith & Mahoney, P. C. was retained as the engineer to prepare construction specifications for the project providing for, inter alia, the replacement of all concrete which was spalling and missing from the panels.

Sweet engaged one subcontractor to remove the old roof membrane which was completed without incident. It also hired third-party defendant, Moisture Barriers, Inc., to install insulation and a new rubber membrane over the existing concrete decking. When employees of Moisture Barriers began moving [616] around the roof, certain concrete panels started to crack raising concerns about safety. In response, Smith & Mahoney created a roof staging and access plan identifying those portions of the concrete decking which were safe to walk upon. Moisture Barriers was instructed to follow the plan.

Moisture Barriers completed most of the installation before suspending work for the winter in December 1995. As for the unfinished portions of the roof, Moisture Barriers laid portions of the rubber membrane loosely over the insulation board so that it would not be exposed to the elements. In February 1996, after being notified that a portion of the membrane had blown back exposing the insulation, Moisture Barriers sent plaintiff Raymond M. Baker, Jr. (hereinafter plaintiff) and another employee to the site to fix the problem. While plaintiff, in the process of removing insulation, was standing on top of the roof over a concrete panel that had not been repaired, the panel gave way. Plaintiff fell approximately 30 feet sustaining personal injuries.

In July 1996, plaintiff and his wife, derivatively, commenced this action against the Board, the City and Sweet (hereinafter collectively referred to as defendants) alleging causes of action for negligence and violations of the Labor Law. Defendants, in turn, commenced a third-party action against Moisture Barriers for contribution and/or indemnification. Plaintiffs commenced a separate action against Smith & Mahoney which was consolidated with their original action.* Smith & Mahoney, in turn, commenced a third-party action against Moisture Barriers for contribution and/or indemnification. In response, Moisture Barriers asserted a counterclaim against Smith & Mahoney for the same relief.

At the close of proof at trial, Smith & Mahoney moved for a directed verdict requesting that Moisture Barriers’ counterclaim be dismissed. Following denial of that motion, the jury rendered a verdict awarding plaintiffs the sum of $423,200 and finding Smith & Mahoney liable to Moisture Barriers for one half of that amount. Thereafter, Smith & Mahoney made a motion pursuant to CPLR 4404 (a) to, inter alia, set aside the verdict and dismiss the counterclaim of Moisture Barriers. Supreme Court denied the motion resulting in these appeals.

Initially, Smith & Mahoney contends that Moisture Barriers failed to adduce any evidence at trial establishing a prima facie case of negligence against it and, therefore, Supreme Court should have directed a verdict in its favor. As part of our [617] analysis, we must determine Smith & Mahoney’s responsibilities with regard to the construction and whether it breached a duty owing to plaintiff. The construction contract is instructive on this issue and provided, in pertinent part, as follows: “engineer will make visits to the site at intervals appropriate to the various stages of construction as engineer deems necessary in order to observe as an experienced and qualified design professional the progress that has been made and the quality of the various aspects of contractor’s executed Work. Based upon information obtained during such visits and observations, engineer will endeavor for the benefit of owner to determine, in general, if the Work is proceeding in accordance with the Contract Documents. Engineer will not be required to make exhaustive or continuous on-site inspections to check the quality or quantity of the Work. Engineer’s efforts will be directed toward providing for owner a greater degree of confidence that the completed Work will conform generally to the Contract Documents. On the basis of such visits and on-site observations, engineer will keep owner informed of the progress of the Work and will endeavor to guard owner against defective Work. Engineer’s visits and on-site observations are subject to all the limitations on engineer’s authority and responsibility set forth in paragraph 9.13, and particularly, but without limitation, during or as a result of engineer’s on-site visits or observations of contractor’s Work engineer will not supervise, direct, control or have authority over or be responsible for contractor’s means, methods, techniques, sequences or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of contractor to comply with Laws and Regulations applicable to the furnishing or performance of the Work” (emphasis in original). From the above, it is clear that Smith & Mahoney’s obligations were to the owner, that is the Board and City, and not to Sweet, Moisture Barriers or plaintiff, the latter’s employee. It is also clear from this paragraph, as well as paragraph 9.13 referenced therein, that Smith & Mahoney had no right to control Sweet’s performance of the repairs and had a duty to inspect Sweet’s work only to ensure compliance with the contract documents after the repair work was completed.

Significantly, the evidence in the record reveals that Sweet had not completed the repairs to all of the concrete panels at the time of the accident. The minutes of a meeting held on January 5, 1996 among the various parties involved in the construction discloses that the City imposed a 4,000-square-foot limitation on the scope of the repair work and that, due to this limitation, Sweet had not repaired all of the panels at that [618] time. It is undisputed that panel G32, which collapsed under plaintiffs weight, had not yet been repaired by Sweet. The fact that this panel was located in the vicinity of other panels that had been repaired and next to one that had been replaced does not, without more, establish a breach of duty by Smith & Ma-honey.

Free access — add to your briefcase to read the full text and ask questions with AI

Baker v. Sweet Associates, Inc., 278 A.D.2d 615, 717 N.Y.S.2d 426, 2000 N.Y. App. Div. LEXIS 13159 (N.Y. Ct. App. 2000).

278 A.D.2d 615 (Baker v. Sweet Associates, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Armstrong v. Foxcroft Nurseries
2004 NY Slip Op 50053(U) (New York Supreme Court, Rensselaer County, 2004)