Baise v. Puckett

2024 Ohio 508
CourtOhio Court of Appeals
DecidedFebruary 12, 2024
DocketCA2023-05-008
StatusPublished

This text of 2024 Ohio 508 (Baise v. Puckett) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baise v. Puckett, 2024 Ohio 508 (Ohio Ct. App. 2024).

Opinion

[Cite as Baise v. Puckett, 2024-Ohio-508.]

IN THE COURT OF APPEALS

TWELFTH APPELLATE DISTRICT OF OHIO

CLINTON COUNTY

TRAVIS BAISE dba T&T RESIDENTIAL : CONSTRUCTION, : CASE NO. CA2023-05-008 Appellee, : OPINION 2/12/2024 - vs - :

: DAVID PUCKETT, et al., : Appellants.

APPEAL FROM CLINTON COUNTY COURT OF COMMON PLEAS Case No. CVH 20210111

Hoover Law Firm, LLC, and Phillip D. Hoover, for appellee.

Miller, Westwood & Brush, LLP, and Michael B. Miller, for appellants.

HENDRICKSON, P.J.

{¶ 1} Defendants, David and Cantessa Puckett (the "Pucketts"), appeal the April

11, 2023 Judgment Entry and Decision of the Clinton County Court of Common Pleas in

favor of Plaintiff, Travis Baise, dba T&T Residential Construction ("T&T").

I. Factual Background

{¶ 2} The facts of this case are relatively simple for the purposes of this appeal.

In 2020, T&T went to the Pucketts' home to make a quote for roofing work. T&T provided Clinton CA2023-05-008

a written quote dated April 30, 2020 to install a new roof on the house and detached

garage, to replace fascia, gutters and downspouts on the house and garage, and to

replace a portion of siding on the garage. T&T provided a second written quote the same

day for removing and replacing all fascia and "freeze metal" gutters on the house and for

installing shutters and posts at the house. Each quote stated that 30% of the total would

be paid up front and the final 70% paid upon completion. Additionally, each quote

prominently contained an "Acceptance of Proposal" box, but neither were signed nor

dated by the Pucketts. Nonetheless, the Pucketts paid T&T $6,815 on May 4, 2020. The

receipt for that payment states it is for "30% prepayment on $22,717.00" for "Roof, Soffit,

Gutters, Post." Notably, $22,717.00 is the sum of the costs provided in the two quotes.

{¶ 3} Upon beginning the work, T&T notified the Pucketts that the original shingle

they had selected for the roof was not available. The Pucketts then selected a different

shingle for their roof. After completing just the roof, T&T submitted a bill to the Pucketts

for the balance due on the roof and six sheets of oriented strand board on Sept 2, 2020.

The Pucketts took issue with the invoice for two reasons: the price did not match the

quotes, and they believed that payment would not be due until all items on both quotes

were completed. A dispute also developed as to whose responsibility it was to

communicate with the Pucketts' insurance company to receive money for covered work.

{¶ 4} Communication between the parties subsequently broke down and the

Pucketts told T&T to not return. Ultimately, the remainder of the work listed in the two

quotes was not completed. The Pucketts later complained that they did not like the color

of the shingles, that some shingles on the completed roof were lifting, that there was a rut

in the yard, and that two shrubs were damaged from the work done by T&T. T&T received

no money from the Pucketts other than the $6,815 paid on May 4, 2020.

-2- Clinton CA2023-05-008

II. Procedural Posture

{¶ 5} T&T filed a complaint against the Pucketts setting forth three causes of

action: (1) breach of contract; (2) money had and received; and (3) fraud. For the breach

of contract claim, T&T alleged that it and the Pucketts "entered [into] a contract whereby

[T&T] agreed to complete roof replacement for the sum of $22,717.00 * * * Per the parties'

agreement, [the Pucketts] were to remit 30% of the sum as a downpayment and satisfy

the remaining 70% upon completion of the roof, facia and gutter." T&T claimed the

Pucketts breached their "written agreement" and sought $11,400 in compensatory

damages for the completed work as well as compensatory and punitive damages for

fraud, attorneys' fees, and costs.

{¶ 6} The Pucketts filed five counterclaims: (1) breach of contract; (2) Consumer

Sales Practices Act ("CSPA") violations; (3) negligence; (4) promissory estoppel; and (5)

unjust enrichment. The Pucketts sought compensatory damages, $5,000 in noneconomic

damages, attorney fees for the CSPA violations, $50,000 in punitive damages, and costs.

{¶ 7} The matter proceeded to a bench trial on January 31, 2023. On April 11,

2023, the trial court issued its decision and ruled on several key issues that are relevant

for this appeal: (1) the two quotes and the parties' actions operated as an implied contract,

not an express one; (2) T&T "did partially perform the agreement and completed

installation of the roof" and is entitled to recover for that work; (3) the cost of the roof

totaled $16,257.00; (4) the Pucketts originally paid $6,815.00; and (5) there were no

issues with the installation of the roof other than T&T damaged shrubbery at the home.

The court awarded $9,442.00, plus court costs on T&T's breach of contract claim as well

as $1,500 to the Pucketts on their negligence claim for the damaged shrubbery.

III. Discussion

{¶ 8} The Pucketts now appeal and raise a single assignment of error for our

-3- Clinton CA2023-05-008

review:

THE TRIAL COURT ERRED AND THE DECISION WAS AGAINST THE WEIGHT OF THE EVIDENCE TO FIND THAT A BREACH OF CONTRACT OCCURRED BASED ON THE CAUSES OF ACTION PLED BY PLAINTIFF.

{¶ 9} The Pucketts contend the trial court's judgment was against the manifest

weight of the evidence because T&T's complaint asserted a claim for breach of express

contract and not for unjust enrichment, contract implied in fact, contract implied in law or

quantum meriut. As a result, the Pucketts argue the trial court found something that T&T

neither asserted nor gave notice in his pleadings as a pursued cause of action.

A. Standard of Review

{¶ 10} A review of the manifest weight of the evidence is the same in criminal and

civil cases. Smith-Knabb v. Vesper, 12th Dist. No. CA2022-06-044, 2023-Ohio-259, ¶

16. A manifest weight of the evidence determination must examine "the inclination of the

greater amount of credible evidence, offered at a trial, to support one side of the issue

rather than the other." State v. Barnett, 12th Dist. Butler No. CA2011-09-177, 2012-Ohio-

2372, ¶ 14. During this examination, the appellate court will inspect the entire record but

must keep in mind that because testimony and evidence were presented directly to a

judge or jury, the trier of fact was in the best position to evaluate witness credibility and

the weight of the evidence. State v. Maloney, 12th Dist. Butler No. CA2022-07-069, 2023-

Ohio-2711; Id. at ¶ 14-15. Ultimately, a judgment will be overturned only where there has

been "a manifest miscarriage of justice" and the evidence "weighs heavily in favor of" a

different result. Barnett, 2012-Ohio-2372, citing State v. Thompkins, 78 Ohio St.3d 380,

387 (1997).

B. Applicable Law

{¶ 11} There are three types of contracts under Ohio law: (1) express contracts;

-4- Clinton CA2023-05-008

(2) implied in fact contracts; and (3) implied in law contracts. Sterling Constr., Inc. v.

Alkire, 12th Dist. Madison No. CA2013-08-028, 2014-Ohio-2897, ¶ 23, citing JS

Productions, Inc. v. G129, L.L.C., 12th Dist. Butler No. CA2011-02-029, 2011-Ohio-4715,

¶ 15. To create an express contract, there must be an offer and acceptance of written

terms. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sterling Constr., Inc. v. Alkire
2014 Ohio 2897 (Ohio Court of Appeals, 2014)
Klan v. Med. Radiologists, Inc.
2014 Ohio 2344 (Ohio Court of Appeals, 2014)
Sexton v. City of Mason, Unpublished Decision (1-8-2007)
2007 Ohio 38 (Ohio Court of Appeals, 2007)
Terex Corp. v. Grim Welding Co.
568 N.E.2d 739 (Ohio Court of Appeals, 1989)
State ex rel. Solid Rock Ministries Internatl. v. Monroe
2022 Ohio 431 (Ohio Court of Appeals, 2022)
MacDonald v. Bernard
438 N.E.2d 410 (Ohio Supreme Court, 1982)
State v. Thompkins
678 N.E.2d 541 (Ohio Supreme Court, 1997)
Smith-Knabb v. Vesper
2023 Ohio 259 (Ohio Court of Appeals, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
2024 Ohio 508, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baise-v-puckett-ohioctapp-2024.