Baise v. Puckett
Opinion
IN THE COURT OF APPEALS
TWELFTH APPELLATE DISTRICT OF OHIO CLINTON COUNTY
TRAVIS BAISE dba T&T RESIDENTIAL : CONSTRUCTION, : CASE NO. CA2023-05-008 Appellee, : OPINION
2/12/2024
- vs - :
:
DAVID PUCKETT, et al., :
Appellants.
APPEAL FROM CLINTON COUNTY COURT OF COMMON PLEAS Case No. CVH 20210111
Hoover Law Firm, LLC, and Phillip D. Hoover, for appellee. Miller, Westwood & Brush, LLP, and Michael B. Miller, for appellants.
HENDRICKSON, P.J.
{¶ 1} Defendants, David and Cantessa Puckett (the "Pucketts"), appeal the April 11, 2023 Judgment Entry and Decision of the Clinton County Court of Common Pleas in favor of Plaintiff, Travis Baise, dba T&T Residential Construction ("T&T").
I. Factual Background
{¶ 2} The facts of this case are relatively simple for the purposes of this appeal.
In 2020, T&T went to the Pucketts' home to make a quote for roofing work. T&T provided
a written quote dated April 30, 2020 to install a new roof on the house and detached garage, to replace fascia, gutters and downspouts on the house and garage, and to replace a portion of siding on the garage. T&T provided a second written quote the same day for removing and replacing all fascia and "freeze metal" gutters on the house and for installing shutters and posts at the house. Each quote stated that 30% of the total would be paid up front and the final 70% paid upon completion. Additionally, each quote prominently contained an "Acceptance of Proposal" box, but neither were signed nor dated by the Pucketts. Nonetheless, the Pucketts paid T&T $6,815 on May 4, 2020. The receipt for that payment states it is for "30% prepayment on $22,717.00" for "Roof, Soffit, Gutters, Post." Notably, $22,717.00 is the sum of the costs provided in the two quotes.
{¶ 3} Upon beginning the work, T&T notified the Pucketts that the original shingle they had selected for the roof was not available. The Pucketts then selected a different shingle for their roof. After completing just the roof, T&T submitted a bill to the Pucketts for the balance due on the roof and six sheets of oriented strand board on Sept 2, 2020. The Pucketts took issue with the invoice for two reasons: the price did not match the quotes, and they believed that payment would not be due until all items on both quotes were completed. A dispute also developed as to whose responsibility it was to communicate with the Pucketts' insurance company to receive money for covered work.
{¶ 4} Communication between the parties subsequently broke down and the Pucketts told T&T to not return. Ultimately, the remainder of the work listed in the two quotes was not completed. The Pucketts later complained that they did not like the color of the shingles, that some shingles on the completed roof were lifting, that there was a rut in the yard, and that two shrubs were damaged from the work done by T&T. T&T received no money from the Pucketts other than the $6,815 paid on May 4, 2020.
II. Procedural Posture
{¶ 5} T&T filed a complaint against the Pucketts setting forth three causes of action: (1) breach of contract; (2) money had and received; and (3) fraud. For the breach of contract claim, T&T alleged that it and the Pucketts "entered [into] a contract whereby [T&T] agreed to complete roof replacement for the sum of $22,717.00 * * * Per the parties' agreement, [the Pucketts] were to remit 30% of the sum as a downpayment and satisfy the remaining 70% upon completion of the roof, facia and gutter." T&T claimed the Pucketts breached their "written agreement" and sought $11,400 in compensatory damages for the completed work as well as compensatory and punitive damages for fraud, attorneys' fees, and costs.
{¶ 6} The Pucketts filed five counterclaims: (1) breach of contract; (2) Consumer Sales Practices Act ("CSPA") violations; (3) negligence; (4) promissory estoppel; and (5) unjust enrichment. The Pucketts sought compensatory damages, $5,000 in noneconomic damages, attorney fees for the CSPA violations, $50,000 in punitive damages, and costs.
{¶ 7} The matter proceeded to a bench trial on January 31, 2023. On April 11, 2023, the trial court issued its decision and ruled on several key issues that are relevant for this appeal: (1) the two quotes and the parties' actions operated as an implied contract, not an express one; (2) T&T "did partially perform the agreement and completed installation of the roof" and is entitled to recover for that work; (3) the cost of the roof totaled $16,257.00; (4) the Pucketts originally paid $6,815.00; and (5) there were no issues with the installation of the roof other than T&T damaged shrubbery at the home. The court awarded $9,442.00, plus court costs on T&T's breach of contract claim as well as $1,500 to the Pucketts on their negligence claim for the damaged shrubbery.
III. Discussion
{¶ 8} The Pucketts now appeal and raise a single assignment of error for our
review:
THE TRIAL COURT ERRED AND THE DECISION WAS AGAINST THE WEIGHT OF THE EVIDENCE TO FIND THAT A BREACH OF CONTRACT OCCURRED BASED ON THE CAUSES OF ACTION PLED BY PLAINTIFF.
{¶ 9} The Pucketts contend the trial court's judgment was against the manifest weight of the evidence because T&T's complaint asserted a claim for breach of express contract and not for unjust enrichment, contract implied in fact, contract implied in law or quantum meriut. As a result, the Pucketts argue the trial court found something that T&T neither asserted nor gave notice in his pleadings as a pursued cause of action.
A. Standard of Review
{¶ 10} A review of the manifest weight of the evidence is the same in criminal and civil cases. Smith-Knabb v. Vesper, 12th Dist. No. CA2022-06-044, 2023-Ohio-259, ¶ 16. A manifest weight of the evidence determination must examine "the inclination of the greater amount of credible evidence, offered at a trial, to support one side of the issue rather than the other." State v. Barnett, 12th Dist. Butler No. CA2011-09-177, 2012-Ohio- 2372, ¶ 14. During this examination, the appellate court will inspect the entire record but must keep in mind that because testimony and evidence were presented directly to a judge or jury, the trier of fact was in the best position to evaluate witness credibility and the weight of the evidence. State v. Maloney, 12th Dist. Butler No. CA2022-07-069, 2023- Ohio-2711; Id. at ¶ 14-15. Ultimately, a judgment will be overturned only where there has been "a manifest miscarriage of justice" and the evidence "weighs heavily in favor of" a different result. Barnett, 2012-Ohio-2372, citing State v. Thompkins, 78 Ohio St.3d 380, 387 (1997).
B. Applicable Law
{¶ 11} There are three types of contracts under Ohio law: (1) express contracts;
(2) implied in fact contracts; and (3) implied in law contracts. Sterling Constr., Inc. v. Alkire, 12th Dist. Madison No. CA2013-08-028, 2014-Ohio-2897, ¶ 23, citing JS Productions, Inc. v. G129, L.L.C., 12th Dist. Butler No. CA2011-02-029, 2011-Ohio-4715,
¶ 15. To create an express contract, there must be an offer and acceptance of written terms. Id.
{¶ 12} With an implied in fact contract, however, a "meeting of the minds * * * is shown by the surrounding circumstances which made it inferable that the contract exists as a matter of tacit understanding." Sterling Constr., Inc. v. Alkire, 12th Dist. Madison No. CA2013-08-028, 2014-Ohio-2897, ¶ 23. Contracts implied in fact are often found where services and materials are provided by one party to another, "under such circumstances that the party to be charged knew or should have known that the services were given with the expectation of being paid on the basis of their reasonable worth." Id., citing Terex Corp. v. Grim Welding Co., 58 Ohio App.3d 80, 82, (9th Dist.1989).
Free access — add to your briefcase to read the full text and ask questions with AI
2024 Ohio 508 (Baise v. Puckett) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.