Bair v. Barron

539 P.2d 578, 97 Idaho 26, 1975 Ida. LEXIS 355
CourtIdaho Supreme Court
DecidedAugust 5, 1975
Docket11650
StatusPublished
Cited by23 cases

This text of 539 P.2d 578 (Bair v. Barron) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bair v. Barron, 539 P.2d 578, 97 Idaho 26, 1975 Ida. LEXIS 355 (Idaho 1975).

Opinion

McQUADE, Chief Justice.

On July 3, 1969, plaintiff-respondent, Carl J. Bair, (hereinafter respondent or lessee) and his wife entered into a share crop lease agreement for a term of three years with Rancho Del Norte a co-partnership of Blackfoot, Idaho, (hereinafter Rancho) under which respondent agreed to lease from Rancho and Rancho agreed to lease to respondent certain real property located in Bingham County, Idaho. The real property is particularly described by legal description, but for purposes of this opinion it will be referred to as farms numbered 9, 10, 11, and 12. Under the terms of the lease, respondent was to raise at least 300 acres of potatoes on the premises each year that the agreement was in effect, provided however, that no potatoes were to be grown on the same parcel of the land in consecutive years. As to the remaining land, it was left to the respondent’s discretion as to what type of crops were to be planted from year to year. Rancho was to receive as rental for the use and occupation of the property, one-fourth of all the crops harvested. Rancho agreed to construct two additional bedrooms on the dwelling house situated on farm number 10 for the use and benefit of the respondent during the term of the lease. The lease contained a provision that in the event the premises were sold by the lessor during the term of the lease, either party including any such purchaser had the right to terminate the agreement upon thirty (30) days notice in writing subsequent *28 to the date of the sale. The lease made no applicable provision concerning accrued rights, i. e., how the parties would deal with compensation for the work accomplished and materials furnished by the lessee should the lease be terminated by either party prior to its expiration date. The lease was to commence on September 1, 1969, and to terminate upon the completion of the harvest of 1972.

Rancho contracted with a management consulting service to provide technical assistance and to consult with respondent in regard to his farming operation. The trial court found that this consulting service directed and induced respondent to enter upon a high yield production program pursuant to the provision of the lease which required the respondent to grow at least 300 acres of potatoes. The high yield potato program involved fall plowing with the application of potash, and contemplated spring plowing with the application of nitrogen and phosphate. Respondent in farming the leased premises followed the instructions of the management consulting service.

On or about October 21, 1969, Rancho sold the leased property and assigned its interests in the leased premises to the defendants-appellants, Gary Reed Barron, Nanette Rita Barron, and J. Reed Barron (hereinafter Barrons or appellants). Appellants thereupon took possession subject to the terms and conditions of the lease. Respondent was not apprised of the sale of the premises until approximately November 15, 1969, when he received a letter from Rancho informing him of the sale of the premises and assignment of the lease to the appellants.

Subsequent to the receipt of this letter, respondent wrote to the appellants on November 20, 1969, advising them that he would like to terminate the lease, and that he was willing to renegotiate the lease to the best interest and welfare of both parties. The record indicates that respondent wrote to the appellants on at least two additional occasions; first in a letter dated February 11, 1970 and second, in a letter dated March 2, 1970. On both occasions he apprised them of the difficulties he was encountering in securing financing for the upcoming season, advised them that he was unable to continue the lease, and asked them for reimbursement for the work done and the materials furnished at his expense up until that time. There is no indication that appellants responded to these letters. Finally, on March 5, 1970, respondent served written notice on appellants that he was terminating the lease. A short time after the lease was terminated by the respondent, appellants were successful in leasing the vacated premises to two new tenants, Jessie Griffith and Blaine Dance.

Respondent brought this action to recover the value by which he claimed the leased premises were improved as a result of the work he performed and the materials he furnished in preparation for the 1970 farming season after appellants disregarded his demands for reasonable compensation. His basic contention was that he plowed, planted, seeded and fertilized portions of leased land in good faith pursuant to the terms of the lease and that the leased premises were improved by his efforts. He joined as defendants in the action the Barrons, Jessie Griffith, and Blaine Dance, alleging that all of the above, jointly and severably had been unjustly enriched at his expense in the amount of $5,742.26.

The five named defendants filed a motion to dismiss this action which was denied. The defendants then filed a motion for summary judgment which was granted as to defendants Griffith and Dance, but denied as to the Barrons. The Barrons then filed an answer and an amended answer to respondent’s complaint. Before the action came to trial, J. Reed Barron died, and the trial court granted respondent’s motion to substitute his son, Gary Reed Barron, as administrator for his father’s estate, as a party.

This cause of action was tried by the trial court and a jury pursuant to I.R.C.P. *29 49(a). Special verdicts in the form of answers to interrogatories were returned by the jury setting forth the work performed by the respondent for plowing, discing, seeding, and fertilizing. The trial court concluded, based in part upon the answers to the interrogatories, and in part upon its own findings of fact, that respondent “unofficiously” and while under a legal duty to do so, conferred benefits upon the appellants which amounted to $5,311.26. It also concluded that respondent realized the benefit of the dwelling house situated on farm number 10, in the sum of $525, which it offset against the $5,311.26 owing to the respondent. It therefore held the appellants jointly and severally liable for the sum of $4,586.26, interest thereon and for costs. It is from this judgment that this appeal has been brought. We affirm.

Appellants set forth 31 assignments of error, which can be reduced to 5 major contentions; first, that the trial court erred in its construction of the termination clause of the lease; second that the trial court erred in failing to find a voluntary surrender under the lease, and in allowing respondent to recover under a theory of unjust enrichment; third, that the trial court erred in its evidentiary rulings; fourth, that the trial court erred in some of its findings of fact; and fifth, that the trial court erred in failing to make additional findings of facts and conclusions of law as requested by appellants.

In their first assignment of error, appellants maintain that the construction placed upon the termination clause of the lease by the trial court was unreasonable, contrary to the intention of the parties, and therefore erroneous. They urge this Court to find respondent’s termination of the lease to be contrary to the terms of that agree-, ment.

The termination clause at issue reads as follows:

“Section XII-Termination.
2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sines v. Blaser
592 P.2d 1367 (Idaho Supreme Court, 2012)
Belstler v. Sheler
264 P.3d 926 (Idaho Supreme Court, 2011)
Pritsker v. Gateway Woodside, Pb
Superior Court of Rhode Island, 2009
Beco Construction Co. v. Bannock Paving Co.
797 P.2d 863 (Idaho Supreme Court, 1990)
Draper v. Draper
772 P.2d 180 (Idaho Supreme Court, 1989)
Smith v. Idaho State University Federal Credit Union
760 P.2d 19 (Idaho Supreme Court, 1988)
Smith v. IDAHO ST. UNIV. FED. CR. UNION
760 P.2d 19 (Idaho Supreme Court, 1988)
Miller v. Miller
745 P.2d 294 (Idaho Supreme Court, 1987)
Olsen v. Country Club Sports, Inc.
718 P.2d 1227 (Idaho Court of Appeals, 1986)
Haskin v. Glass
640 P.2d 1186 (Idaho Court of Appeals, 1982)
Fouser v. Paige
612 P.2d 137 (Idaho Supreme Court, 1980)
Stephens v. City of Notus
609 P.2d 168 (Idaho Supreme Court, 1980)
Dick v. Amalgamated Sugar Co.
605 P.2d 506 (Idaho Supreme Court, 1979)
Christensen v. Christensen
605 P.2d 80 (Idaho Supreme Court, 1979)
McNeil v. Gisler
604 P.2d 707 (Idaho Supreme Court, 1979)
Unigard Insurance Group v. Royal Globe Insurance
594 P.2d 633 (Idaho Supreme Court, 1979)
Jensen v. Bledsoe
593 P.2d 988 (Idaho Supreme Court, 1979)
Hertz v. Fiscus
567 P.2d 1 (Idaho Supreme Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
539 P.2d 578, 97 Idaho 26, 1975 Ida. LEXIS 355, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bair-v-barron-idaho-1975.