Bain v. White

256 F. 428, 167 C.C.A. 556, 1919 U.S. App. LEXIS 1375
CourtCourt of Appeals for the Fifth Circuit
DecidedFebruary 27, 1919
DocketNo. 3170
StatusPublished

This text of 256 F. 428 (Bain v. White) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bain v. White, 256 F. 428, 167 C.C.A. 556, 1919 U.S. App. LEXIS 1375 (5th Cir. 1919).

Opinion

BATTS, Circuit Judge.

A contract between White, of one part, and Bain and Knott of the other, provided for the drilling by the latter of a well in Hockley county, Tex. The parts of the contract having bearing upon the present controversy are:

Section 3, which provicies that the well should be sunk to a depth of 2,000 feet, unless a flow of oil, gas, or water is secured before that depth is reached; section S, which recites that J. M. Mook & Son had undertaken to drill a well that had not been carried to completion, and provides that Bain and Knott might use this hole, if they thought [430]*430proper; section 6, providing for the compensation, and that, if- the drillers fail to sink the well to a depth of 2,000 feet, they should be held to have breached the contract and entitled to no compensation; section 7, providing that the work should be done in a good and workmanlike manner; section 8, with a provision to this effect, “It is a further , condition and undertaking of the parties of the second part that the well, when completed to a depth of 2,000 feet, shall he a good clean hole”; section 9, providing that White “agreed to furnish and deliver at site of well all piping, with drive shoes for bottom of pipes necessarjr. for completion of the well.”

The questions necessary for determination were: (1) Was the well when completed to a depth of 2,000 feet, a good clean hole? (2) If there was_a faíluré to deliver a “good clean hole” 2,000 feet deep, was this the result of White’s failure to furnish necessary piping? (3) Assuming the failure of the first well, 'did the drillers have a right to drill another, the piping to be furnished by White, and did the refusal of White to furnish additional piping, whereby the drilling of another, hole was prevented, result in loss and damage to the drillers ?

[1] The questions do not come to this court as matters for primary determination, but involve a consideration of whether there was evidence from which the conclusions of fact forming the basis of the judgment could have been drawn. Under a stipulation by tire parties, the jury was waived, and all matters at controversy submitted to the trial judge. The extent to which, under such circumstances, the finding of the District Judge is conclusive, is the subject of discussion in the briefs of the parties. This, at least, may be said of the applicable law: The findings of the trial judge upon issues of fact submitted to him are entitled to as much consideration as the verdict of a jury. The case is disposed of upon the assumption that they are not entitled to greater consideration. Applying the rule applicable to verdicts of the jury, the question as to each of the issues suggested would be whether there was evidence furnishing a basis for the conclusion reached.

Even if the testimony of all the witnesses tendered by defendant be eliminated, it would be possible, under the rule announced, to 'sustain the finding of the court. All of the evidence which was introduced to show that the plaintiff was at any time in a position to deliver, “a good clean hole” 2,000 -feet deep is that of the plaintiff Bain and his employé, Philip Cezeaux. Both o'f these witnesses unequivocally testified that on the 18th of December, 1914, the contractors had ready for delivery to White “a good clean hole” 2,000 feet deep. If they had not testified further, and if no other evidence had been introduced, the statements would doubtless have required a judgment for plaintiffs. The effect, however, of the testimony of both witnesses, is, in large measure, destroyed by their subsequent statements. Bain testified (Record, 96): '

“About the 12th or 15th, I got a note from the driller, and he wrote roe to come out on the 18th, and he would measure the well out to me.
“Q. This pipe was still in there when you went back? . A. When I went back when? ■ - . . : .
“Q. When you went back on the 18th of September? A. They had sidetracked it. then.. :
[431]*431“Q. Now, yon stated that the condition of the well was such that, to leave it a few hours' with the drill stem, this pipe might run over again and obstruct tho well? A. Yes.
“Q. That was the condition when Mr. White was there in December? A. Why, I suppose it was. We had ptilled the pipe on the 18th, and he was up there on the 20th. We had the hole in good shape on the 18th.
“Q. Well, you could have measured it out to him on the 18th? A. Yes, sir.
“Qt And within an hour or two, or perhaps three or four hours, it would have been in a condition that you couldn’t have measured it. A. Well, it might. Then, again, I have known them to stand there for three months, and you go right back to the bottom. This well had a cave in it at the bottom of the 634"-”

Again he testified (Record, 104):

“Q. Then, when you reported that you were down 2,000 according to the contract, the well at that time was not a good hole on account of this casing, was It? A. It was a good hole, good and clean and down 2,000 feet.
“Q. Well, it was clean, but would you call It a good hole? A. Well, it is a good deal better hole than I drilled in lots of other places.”
“Q. Now, when you claimed to have this contract completed, the condition of the well was such that there was a broken pipe, that had been sidetracked, that was liable to lean over in the well and obstruct it at any time? A. Well, it did do it; yes, sir.
“Q. You found that obstruction in there when you went back in January? A. Yes, sir.
“Q. It might have been in there when Mr. White came over, might it not? A. It might have been, yes, sir; but it wasn’t in there—
“Q. Now, when you pulled your drill out and stopped your drilling, it is possible that pipe leaned right back into the hole at that time? A. No, sir; I don’t think so. We had pulled It out to put on a new bit.
“Q. You had some trouble with that pipe in there before, had you? A. No, sir.
“Q. The next time you attempted to put your drill stem in, why you found it obstructed with this pipe you had sidetracked? A. After the well had stood for 10 days without any work.”

Mr. Bain testified (Record, 81):

“Well, we went on down with the well, and got down 2,000 feet We had two measurements; one measurement was .1,973 feet, and one measurement was 2.018 feet.
“Q. When was that? A. That was, I think, the 3d day of November.
“Q. Third day of November, 1914? A. 1914. Mr. White sent Mr. Walker out there to receive the well, and I told Mr. Walker I couldn’t deliver it to him; that I had twisted some pipo off.”

Philip Cezeaux, after having testified (Record, 143 et seq.) that, on the 18th of December, 1914, there was a “good clean hole,” ready for delivery, further testified (Record, 151):

“Q. Now, you were speaking about this being a good clean hole. It had a drill hit and stem in it, did it not? A. Yes, sir.”

Again (Record 152):

“Q. Were you the drill or that broke the drill stem in the hole? A.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
256 F. 428, 167 C.C.A. 556, 1919 U.S. App. LEXIS 1375, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bain-v-white-ca5-1919.