Bain v. Paciotti-Orr, Unpublished Decision (12-2-1999)

CourtOhio Court of Appeals
DecidedDecember 2, 1999
DocketNo. 75384.
StatusUnpublished

This text of Bain v. Paciotti-Orr, Unpublished Decision (12-2-1999) (Bain v. Paciotti-Orr, Unpublished Decision (12-2-1999)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bain v. Paciotti-Orr, Unpublished Decision (12-2-1999), (Ohio Ct. App. 1999).

Opinion

JOURNAL ENTRY and OPINION
Plaintiffs-appellants David R. Bain and Bain Builders Remodelers (hereinafter referred to in the singular as "Bain") appeal from the trial court opinion and order that granted the motion to dismiss filed by defendants-appellees Joan Paciotti-Orr and "John Doe Corporation No. 1" (hereinafter referred to in the singular as "Paciotti-Orr")

Bain asserts the trial court erred in dismissing his complaint, plaint, arguing that his contractual claim for monies due against Paciotti-Orr was both timely and separate from issues previously determined by a panel of arbitrators.

This court has reviewed the record, finds the trial court's action was appropriate and, therefore, affirms it.

The following facts are gleaned from the record on appeal.

In October 1993. Paciotti-Orr, owner of a business known as "Create-a-Center, Inc.," engaged Bain as a general contractor to construct a commercial building known as the "Strongsville Child Development Elder Day Care Center" in Strongsville, Ohio. The parties signed a standard American Institute of Architects ("AIA") form agreement that called for completion of the work by April 4, 1994 at a total cost of $1,025,000.00. Under the heading "General Conditions of the Contract for Construction," the agreement also contained the following pertinent provisions:

ARTICLE I GENERAL PROVISIONS

* * *

1.1.2 THE CONTRACT

The Contract Documents form the Contract for Construction. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. The Contract may be amended or modified only by a Modification. * * *

ARTICLE 4 ADMINISTRATION OF THE CONTRACT

4.3 CLAIMS AND DISPUTES

4.3.1 Definition. A Claim is a demand or assertion by one of the parties seeking, as a matter of right, adjustment or interpretation of Contract terms, payment of money, extension of time or other relief with respect to the terms of the Contract. The term "Claim" also includes other disputes and matters in question between the Owner and Contractor arising out of or relating to the Contract. Claims must be made by written notice. The responsibility to substantiate Claims shall rest with the party making the Claim.

4.3.2 Decision of Architect. Claims, including those alleging an error or omission by the Architect, shall be referred initially to the Architect for action as provided in Paragraph 4.4. A decision by the Architect, as provided in Subparagraph 4.4.4, shall be required as a condition precedent to arbitration or litigation of a Claim between the Contractor and Owner as to all such matters arising prior to the date final payment is due, regardless of (1) whether such matters relate to execution and progress of the Work or (2) the extent to which the Work has been completed. * * *

4.3.3 Time Limits of Claims. Claims by either party must be made within 21 days after occurrence of the event giving rise to such Claim or within 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by written notice. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely manner.

4.5 ARBITRATION

4.5.1 Controversies and Claims Subject to Arbitration. Any controversy or Claim arising out of or related to the Contract, or the breach thereof, shall be settled by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association, and judgment upon the award rendered by the arbitrator or arbitrators may be entered in any court having jurisdiction thereof * * *.

(Emphasis added.)

Sometime in the spring of 1994, disputes arose between the parties regarding Paciotti-Orr's "payment of periodic draw payments" to Bain and Bain's "scheduled completion date" for the project. Thereafter, in a written modification of the contract, the parties agreed as follows: Paciotti-Orr agreed to pay Bain a "draw payment" in the amount of $167,000 upon the completion ofthe modification and also to pay Bain two additional draw payments on July 22, 1994 and July 29, 1994. Bain agreed to obtain an occupancy permit from the city by August 10, 1994 or, upon failing to do so, pay to Paciotti-Orr a liquidated damage amount. The modification contained a clause noting that the remaining terms and conditions of the AIA contract were neither altered, modified nor amended.

On July 22, 1994 Bain notified Paciotti-Orr that she had breached the contract. On August 8, 1994 Paciotti-Orr discharged Bain from work on the project.

In late October 1994, Paciotti-Orr filed a claim for arbitration. Bain filed a response in which he asserted a claim against Paciotti-Orr for "$188,180 representing the amount currently due and outstanding" to Bain "under the underlying contract."

The arbitrator held a hearing in February 1995. At the conclusion of the hearing, one of the arbitrators invited the parties to submit post-hearing briefs supported by already-admitted documentary evidence "to show [the arbitrators] where you believe the final contract price is set out."

In April 1995, the arbitrators issued their award, in which Paciotti-Orr's claims against Bain were dismissed with prejudice and Bain's "request for damages" against Paciotti-Orr was dismissed with prejudice.

In June 1997, Bain filed a complaint for declaratory judgment in the Cuyahoga County Court of Common Pleas "seeking to reduce the arbitration award of April 3, 1995 to judgment." The case was designated CV-335462. Bain subsequently filed a motion for summary judgment in the case in which he argued that "pursuant to the agreement between the parties of October 3, 1993, the arbitration of April 3, 1995, is a final determination of therights and liabilities of the parties." (Emphasis added.)

On October 29, 1997, while his motion for summary judgment was pending in CV-335462, Bain filed the instant action against Paciotti-Orr and an unnamed corporation.

In count one of his complaint, Bain asserted that pursuant to the terms of the contract, he had "completed ninety percent (90%) of the project which was the subject of the agreement [between himself and `Defendants'], and [has] not been paid by the Defendants for the work performed * * *." Bain estimated his damages to be in the amount of $491,000.00. Bain attached to his complaint a copy of the parties' AIA contract and the July 1994 modification of the contract.

On December 23, 1997 Bain filed a motion to consolidate the instant case with CV-335462.

On January 30, 1998 Paciotti-Orr responded in the instant case with a Civ.R. 12 (B) (1) motion to dismiss Bain's complaint.1 Paciotti-Orr argued that in view of both the contract's arbitration provisions and the arbitration award, the trial court lacked subject matter jurisdiction. She attached to her motion as exhibits a copy of the AIA contract, a portion of the transcript of the arbitration hearing, and a copy of the award of the arbitrators.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sanders v. Webb
621 N.E.2d 420 (Ohio Court of Appeals, 1993)
Shockey v. Fouty
666 N.E.2d 304 (Ohio Court of Appeals, 1995)
Avco Financial Services Loan, Inc. v. Hale
520 N.E.2d 1378 (Ohio Court of Appeals, 1987)
Stores Realty Co. v. City of Cleveland
322 N.E.2d 629 (Ohio Supreme Court, 1975)
State ex rel. Bush v. Spurlock
537 N.E.2d 641 (Ohio Supreme Court, 1989)
ABM Farms, Inc. v. Woods
692 N.E.2d 574 (Ohio Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Bain v. Paciotti-Orr, Unpublished Decision (12-2-1999), Counsel Stack Legal Research, https://law.counselstack.com/opinion/bain-v-paciotti-orr-unpublished-decision-12-2-1999-ohioctapp-1999.