Bain Builders, Inc. v. Rockport Retirement, Unpublished Decision (7-22-1999)

CourtOhio Court of Appeals
DecidedJuly 22, 1999
DocketNos. 74486 74672.
StatusUnpublished

This text of Bain Builders, Inc. v. Rockport Retirement, Unpublished Decision (7-22-1999) (Bain Builders, Inc. v. Rockport Retirement, Unpublished Decision (7-22-1999)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bain Builders, Inc. v. Rockport Retirement, Unpublished Decision (7-22-1999), (Ohio Ct. App. 1999).

Opinion

Defendant-appellant cross-appellee Rockport Retirement Ltd. Partnership (Rockport) appeals from the trial court's judgment in favor of plaintiff-appellee cross-appellant Bain Builders, Inc. (Bain). After a trial to the bench on a breach of contract claim, damages were awarded to Bain in the sum of $57,110.48. The prejudgment interest award requested by Bain was denied and is the subject of the cross appeal.

This suit arises out of a written construction and remodeling contract between the appellant and the appellee. The contract called for the appellee to replace the main portion of the roof on a building owned by the appellant. The written contract stated that: "NO ALTERATIONS OR CHANGES SHALL BE MADE, HOWEVER, EXCEPT UPON THE WRITTEN ORDER OF THE OWNER OR HIS AUTHORIZED REPRESENTATIVE, PRIOR TO INSTALLATION." During the course of the construction, various changes were requested by the appellant and performed by the appellee. Some of the changes were reduced to writing while others were not. This suit was filed, in part, in order to recover for the changes requested by the appellee which were not reduced to writing. The appellant also sought recovery for various other costs, such as rental on equipment loaned to the appellant by the appellee and the cost of shingles purchased by the appellee, but used by another contractor at the direction of the appellant. There is no dispute as to the quality of the work performed by the appellee.

On April 5, 1996, Dam filed its complaint. Prior to trial, the first cause of action in foreclosure, based on a mechanics' lien, was dismissed, as were all defendants save the appellant. In the second cause of action, the appellee asserted a breach of contract claim for $27,628.80. The amended complaint, filed March 14, 1997, stares that appellee discovered that partial payment of the initial claim had been made and that a valid claim in excess of $24,000 remained. The prayer requests an amount to be proven at trial. During opening argument, the appellee requested damages in the sum of $65,000.

The following findings of fact and conclusions of law were signed by the trial court and were the basis for the judgment.

The Court found:

1. The Plaintiff Bain Builders and Defendant Rockport Retirement Limited Partnership, who is the owner of the property located at 20375 Center Ridge Road, Rocky River, Ohio, did on or about February 15, 1995 enter into a contract for construction and remodeling of a building and other structures located at such address. Such agreement was for the replacement of the main portion of the roof and such replacement cost one hundred seventy thousand dollars ($170,000.00)

2. The structure was to be covered with vinyl siding to be placed on the structure by Plaintiff Bain and such work and materials were in addition to the work contracted for as set out in the agreement of February 15, 1995. This was to be performed by the Plaintiff Bain Builder for the defendant Rockport and this increased the cost of the project to the amount of two hundred forty-six thousand three hundred ninety-eight dollars ($246,398.00)

3. The Defendant Rockport appointed Defendant Management Associates to act as its general agent and empowered such defendant Management Associates with the general power of an agent to perform all acts, and enter into any agreement, modify any agreement to carry out the construction of the building located as set out above and do all other acts in the agents (sic) sole discretion that such acts were needed to carry out the construction and remodeling of the building and other structures on the property of the Defendant Rockport.

4. Defendant Rockport so instructed the Plaintiff Bain Builders that the defendant Management Associates would act as its General agent and shall have full power in carrying out the construction of such building to enter into additional agreements, modify agreements, and do all other acts to carry out the construction project. The Plaintiff shall receive all direction, orders which could include changes to the project, and additions in the construction project from Defendant Management Associates acting as General agent of Defendant Rockport.

5. Defendant Management Associates in exercising such General agency acted on behalf of the defendant Rockport and commenced the management of the construction and remodeling of such building.

6. The architectural plans in existence and forming the basis of the contract between Plaintiff Bain Builders and Defendant Rockport were not correct and, if followed, would result in an (sic) constructing an unsafe building. Extensive modifications were made subsequent to the original agreement to the architectural plans and resulted in much additional work and materials being both performed and supplied by the Plaintiff Bain Builders.

7. Plaintiff Builders completed all terms of all agreements and the construction performed by the Plaintiff Bain Builders was satisfactory and in doing this the Plaintiff Bain Builders earned all funds as set out below in performing such work and providing materials.

8. Plaintiff Bain Builders and Defendant Rockport entered into agreements for further construction changes as both set out in the changed architectural plans and in requiring the plaintiff to perform additional work not contained within the plans resulting in additional cost for plaintiff which Defendant Rockport agreed to pay the plaintiff and such agreements and extensive additional work increased the cost of the portion of work performed by Plaintiff Bain Builder (sic) from one hundred seventy thousand dollars to two hundred sixty-three thousand two hundred thirteen dollars and eighty nine cents ($263,213.89).

9. Defendant Rockport paid to the Plaintiff Bain Builders only a portion of such amount due and did not pay the balance of thirty-one thousand five hundred fifty dollars and eighty-eight cents ($31,550.88) and such amount is still due and owing and became due and owing as of June 1, 1995.

10. In July of 1995 Plaintiff Rockport through its general agent Defendant Management Associates agreed to additional work to be performed by the Plaintiff which caused an amount to be due for such work in the amount of two thousand dollars ($2,000.00) and such construction work has not been paid, became due and owing on July 30, 1995, and is still due and owing.

11. During the time of the construction of the building, the Plaintiff purchased shingles for the portion of the roof for which it had been contracted to place on the structure and paid for all of the shingles present at such job site. Further the shingles purchases (sic) were of better quality as ordered pursuant to the order of the Defendants who agreed to pay the cost increas (sic) for such additional quality but did not and such amount of one thousand three hundred sixty-eight dollars ($1,368.00) and such amount is still due and owing.

12. The Defendants took shingles which were the property of the plaintiff Bain Builders and had the shingles placed on other portions of roof of the building that Plaintiff Bain Builders was not responsible (sic). The plaintiff purchased them and such shingles are worth two thousand two hundred forty dollars ($2,240.00) and such amount is demanded of the Defendants but the Defendants have refused payment and such amount is still due and owing.

13.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Riggs, Ferris & Geer v. Harrison Lillibridge
316 F.2d 60 (Second Circuit, 1963)
White v. Euclid Square Mall
669 N.E.2d 82 (Ohio Court of Appeals, 1995)
Stevens Skin Softener, Inc. v. Revco Drug Stores, Inc.
699 N.E.2d 549 (Ohio Court of Appeals, 1997)
Sandusky Mall Co. v. Pet Corner, Inc.
690 N.E.2d 78 (Ohio Court of Appeals, 1997)
Alexander v. Culp
705 N.E.2d 378 (Ohio Court of Appeals, 1997)
Frantz v. Van Gunten
521 N.E.2d 506 (Ohio Court of Appeals, 1987)
C. E. Morris Co. v. Foley Construction Co.
376 N.E.2d 578 (Ohio Supreme Court, 1978)
State ex rel. Shady Acres Nursing Home, Inc. v. Rhodes
455 N.E.2d 489 (Ohio Supreme Court, 1983)
Seasons Coal Co. v. City of Cleveland
461 N.E.2d 1273 (Ohio Supreme Court, 1984)
Royal Electric Construction Corp. v. Ohio State University
73 Ohio St. 3d 110 (Ohio Supreme Court, 1995)
Landis v. Grange Mutual Insurance
695 N.E.2d 1140 (Ohio Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Bain Builders, Inc. v. Rockport Retirement, Unpublished Decision (7-22-1999), Counsel Stack Legal Research, https://law.counselstack.com/opinion/bain-builders-inc-v-rockport-retirement-unpublished-decision-ohioctapp-1999.