Bailey v. United States

78 Fed. Cl. 239, 2007 U.S. Claims LEXIS 261, 2007 WL 2317493
CourtUnited States Court of Federal Claims
DecidedAugust 10, 2007
DocketNo. 02-1078L
StatusPublished
Cited by13 cases

This text of 78 Fed. Cl. 239 (Bailey v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bailey v. United States, 78 Fed. Cl. 239, 2007 U.S. Claims LEXIS 261, 2007 WL 2317493 (uscfc 2007).

Opinion

OPINION AND ORDER

WOLSKI, Judge.

The plaintiff, Gary Bailey, alleges that the United States, acting through the Army Coips of Engineers (“Corps”), has taken his property without payment of just compensation. The matter concerns the application of the Clean Water Act (“the Act”) to a platted subdivision located in Lake of the Woods, Minnesota. Plaintiff contends that actions of the Corps, including the denial of an after-the-fact permit under section 404 of the Act, 33 U.S.C. § 1344, and the ordered restoration of land upon which a road was constructed, have resulted in a taking of the subject property. The government has moved to dismiss his complaint under Rule 12(b)(1) of the Rules of the United States Court of Federal Claims (“RCFC”) for lack of subject matter jurisdiction, to the extent that the claims are based on the restoration order— which it contends would not be ripe for review. It has also moved for summary judgment, under RCFC 56, arguing, among other things, that Mr. Bailey did not own the property affected by the Corps’s actions and can prove no compensable damages caused by these actions. For the reasons explained below, the Court DENIES the motion to dismiss, and GRANTS-IN-PART and DENIES-IN-PART the motion for summary judgment.

I. BACKGROUND1

In June 1989, plaintiff and his then-wife purchased, for $135,000, land in Lake of the Woods County, Minnesota, including the property that is at the center of this dispute. See Def.’s App. 142; Pl.’s Prop. Facts ¶¶ 3-5.2 This purchase included two forty-acre parcels (or “quarters of quarters” under the Public Land Survey System (“PLSS”)), one eighty-acre parcel (or a “half of a quarter”), and an irregularly-shaped, non-aliquot lot. See Def.’s App. 142; see also id. 320-21 (Nelson Decl. ¶¶ 6-7). The shores of Lake of the Woods form the eastern border of the irregular lot, which is designated under the PLSS as Government Lot 3 of Section 21 in Township 163 North, Range 33 West. See id. 142.3 The platted subdivision at issue, now known as “Sunny Beach,” see Pl.’s App. 35, is mostly located within Government Lot 3.4 See [242]*242Def.’s App. 219; Pl.’s App. 11, 29.5

A. The Platting of the Subdivision

Mister Bailey’s initial plan for the Sunny Beach property was to build a marina or harbor on the property, by enlarging a drainage ditch, removing fill, and placing the fill on an upland location to create a parking area and a roadbed. See Pl.’s Prop. Facts ¶¶ 13-14; Def.’s App. 128, 329; Bailey Aff. ¶ 4. He applied to the Corps for a permit to allow the dredging in February 1990, and the Corps approved the dredging under the authority of a general permit. Pl.’s Prop. Facts ¶¶ 13-14; see also Def.’s App. 130, 204 (Whiting Deck ¶ 4); Pk’s App. 1. The project did not come to fruition. Bailey Aff. ¶ 4. Three years later, the Corps sent Mr. Bailey a letter, dated August 18, 1993, which referenced the previously-issued approval for the harbor project and informed him:

It has now come to our attention that this harbor is apparently located in a wetland area and that you propose to place fill and/or dredged material into this wetland area to develop residential lots. Therefore, you will need another Department of the Army permit for this activity. Please note that harbor dredging can still be done provided all dredged material is placed directly on an upland area and not sidecast into the adjoining wetlands, even temporarily. As requested, we have also enclosed a copy of the National Wetlands Inventory map and its legend that shows the wetlands in this area. However, you should use caution while relying upon this map as it may not be accurate in showing all the wetlands in this area.

Def.’s App. 130 (underscoring in original).

The following Spring, the Corps visited the site and discussed the matter further with Mr. Bailey. A letter from the Corps dated May 13, 1994 referenced the visit and stated, “[a]s discussed on-site, you may wish to hire a qualified, private consultant to help you delineate this highly diverse site and prepare the required application that was previously provided to you.” Id. 132. No wetlands delineation was done at that time, by either Mr. Bailey or the government. Over two years later, in December 1996, plaintiff applied to Lake of the Woods County to have a 13.2 acre strip of land in Government Lot 3, along the lakeshore, platted as a subdivision. Pk’s Proposed Facts ¶ 18. In December 1998, Lake of the Woods County Board approved the Sunny Beach fourteen-lot subdivision, and re-zoned the land from “natural resource” to “residential” use. Id.; see also Pk’s App. 35; Def.’s App. 329; Bailey Aff. ¶¶ 6-7.6

B. The Access Road

It appears that the County normally requires public access to any platted areas, see Pk’s App. 49, and to meet this requirement plaintiff began, in the Spring of 1998, preparations to construct an extension of an existing county road. Pk’s Prop. Facts ¶ 19. The existing road, Sandy Shores Drive, at that time terminated just north of the western edge of the platted subdivision. See Def.’s App. 318. Over the next several months, construction of the road extension began, starting with land clearing activities. Pk’s Prop. Facts ¶¶ 19-20. As plaintiff described it, a contractor he had hired “roughed in a road.” Def.’s App. 123; see also id. 121-22. According to a Corps official, on June 15, 1998, an unspecified Corps representative visited the site and “advised Mr. Bailey to perform no additional work unless he obtained a Corps permit.” Def.’s App. 204-05 (Whiting Deck ¶ 7); see Def.’s Prop. Facts ¶ 20. No written order appears to have been issued formally directing plaintiff or the County to cease the road building activity. See Pk’s Prop. Facts ¶ 20.

Mister Bailey filled out and signed an application, dated June 17, 1998, for an after-[243]*243the-fact permit for the access road. Def.’s App. 133-34; Pl.’s App. 21-22. The project notification form he used was designed for applications to the state, county, and local government, as well as the Corps, and he signed on a specific line allowing it to be considered an application for a Section 404 permit under the Clean Water Act. See Def.’s App. 134; Pl.’s App. 22. Plaintiff submitted this application to the County, along with a Wetland Replacement Plan Application pursuant to the Minnesota Wetland Conservation Act. See Pl.’s App. 24-27. After evaluating the application under the state act, the County forwarded it to the Corps. See Def.’s App. 355. The Corps filed the application on August 17, 1998. See id.; see also Pl.’s App. 19, 28. The next month, the Corps sent plaintiff a letter dated September 17, 1998, stating that the Corps “underst[oo]d the road was completed” and believed it was “in a forested wetland” requiring a Corps permit. Def.’s App. 208. The letter acknowledged receipt of Mr. Bailey’s permit application, and directed:

No additional work requiring Department of the Army authorization may be performed prior to obtaining that authorization[;] this includes any additional land-clearing of this wetland area.

Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stanwyck v. United States
Federal Claims, 2016
Lucree v. United States
117 Fed. Cl. 750 (Federal Claims, 2014)
Bailey v. United States
116 Fed. Cl. 310 (Federal Claims, 2014)
Mehaffy v. United States
98 Fed. Cl. 604 (Federal Claims, 2011)
Banks v. United States
88 Fed. Cl. 665 (Federal Claims, 2009)
Resource Investments, Inc. v. United States
85 Fed. Cl. 447 (Federal Claims, 2009)
L-3 Communications Integrated Systems v. United States
84 Fed. Cl. 768 (Federal Claims, 2008)
Forest Glen Properties, LLC v. United States
79 Fed. Cl. 669 (Federal Claims, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
78 Fed. Cl. 239, 2007 U.S. Claims LEXIS 261, 2007 WL 2317493, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bailey-v-united-states-uscfc-2007.