Bailey v. Irish Development Corp.

274 A.D.2d 917, 711 N.Y.S.2d 241, 2000 N.Y. App. Div. LEXIS 8252
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJuly 27, 2000
StatusPublished
Cited by8 cases

This text of 274 A.D.2d 917 (Bailey v. Irish Development Corp.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bailey v. Irish Development Corp., 274 A.D.2d 917, 711 N.Y.S.2d 241, 2000 N.Y. App. Div. LEXIS 8252 (N.Y. Ct. App. 2000).

Opinions

—Mugglin, J.

Appeal from an order of the Supreme Court (Hughes, J.), entered September 10, 1999 in Albany County, which, inter alia, denied plaintiffs’ motion for partial summary judgment on the issue of liability pursuant to Labor Law § 240 (1).

At all times herein relevant, plaintiff William R. Bailey, Sr. (hereinafter plaintiff) was a general laborer and truck driver employed by third-party defendant, Cal Parlman, Inc. (hereinafter Parlman). In July 1993, defendant Brooks Contracting, Inc. entered into a contract with defendant Mark Development Company, Inc. to act as general contractor for the construction of a wholesale depot store owned by defendants Mark Centers Limited Partnership, Mark Centers Trust Company and Mark Development Company, Inc. (hereinafter collectively referred to as the Mark defendants). As part of the contract, Brooks agreed to indemnify and hold Mark Development Company, Inc. harmless with regard to accidents arising out of the construction project.

Brooks subcontracted all work for the project. The original subcontract between Brooks and Parlman required Parlman to excavate and install the footing and foundation system. The majority of this work was performed in November 1993, after which work was halted until April 1994. As the result of a change order, Parlman was required to replace all existing footings. The existing footings were to be removed, trucked off-[918]*918site and buried. To accomplish this, Parlman subcontracted with defendant Irish Development Corporation. Although the construction project was shut down on May 27, 1994 when the prospective anchor tenant filed bankruptcy, Brooks was instructed to complete the work of removing the old concrete footings. On June 17, 1994, plaintiff and an employee of Irish Development used an excavator to lift the pieces of concrete footing, each of which was approximately six feet long, six feet wide and 18 inches thick, and weighed in excess of four tons, into the bed of the dump trucks. To accomplish this, they fastened one end of the chain to the bucket of the excavator and plaintiff wrapped the opposite end around a piece of footing. Once the concrete was lifted into the bed of the dump truck, plaintiff was required to unhook the chain and exit the bed of the truck, after which the excavator would pull the chain loose from the footings. On approximately the seventh occasion, as plaintiff attempted to exit the truck and the excavator operator began to pull the chain from the concrete, the chain caught and the two concrete footings then on the truck slid, causing the dump body to rapidly rise into the air. At this time, plaintiff was located on the cab shield and grasped the top edge to avoid falling. Unfortunately, plaintiff was hoisted and injured when he lost his grip, fell to the roof of the truck cab and from there to the frame of the truck under the dump body. Fearful of being crushed by the dump body, he rolled off the truck frame to the ground.

Plaintiff and his wife, derivatively, commenced this action seeking damages under Labor Law §§ 200, 240 (1) and § 241 (6) and under a common-law theory of negligence. Following discovery, plaintiffs moved for partial summary judgment on the issue of liability based on defendants’ alleged violation of Labor Law § 240 (1). The Mark defendants and Brooks cross-moved for summary judgment dismissing plaintiffs’ complaint or, alternatively, for summary judgment dismissing plaintiffs’ Labor Law § 240 (1) cause of action against all defendants and summary judgment for common-law indemnification against Irish Development. Parlman opposed plaintiffs’ motion and supported the cross motion for summary judgment dismissing plaintiffs’ complaint. Irish Development opposed plaintiffs’ motion, supported the motion for dismissal of plaintiffs’ complaint and opposed the moving defendants’ motion for indemnification. Supreme Court dismissed plaintiffs’ Labor Law § 240 (1) claim against all defendants, dismissed plaintiffs’ common-law negligence and Labor Law § 200 claims against Brooks, Mark Centers Limited Partnership and Mark Centers Trust, and concluded that the dismissal rendered the claim for common-[919]*919law indemnity moot as to these defendants. The court denied Mark Development’s motion for indemnification, finding that questions of fact existed as to its role in plaintiffs injury. Plaintiffs now appeal.

Plaintiffs contend that Supreme Court improperly denied their motion for partial summary judgment on liability under Labor Law § 240 (1) since the excavator, a hoisting device, improperly caused the concrete to slide and/or fall from the dump body, resulting in the rapid raising of the dump body causing plaintiff to fall from an elevated work site.

Labor Law § 240 (1) imposes a nondelegable duty upon owners and contractors to provide necessary and appropriate protection to workers employed on a construction site (see, Rocovich v Consolidated Edison Co., 78 NY2d 509, 513). The statutory protection afforded by Labor Law § 240 (1) is intended to encompass only elevation-related hazards which result in injury to workers as a result of inadequate or missing safety equipment (see, Bland v Manocherian, 66 NY2d 452, 457-459). Recognizing that requiring workers to labor at elevated work sites creates a significant risk of injury through the operation of gravity, Labor Law § 240 (1) contains a list of devices intended to protect workers from the elevation-related risks (see, Ross v Curtis-Palmer Hydro-Elec. Co., 81 NY2d 494, 501). As the Court of Appeals explained in Rocovich v Consolidated Edison Co. (supra, at 514), “The contemplated hazards are those related to the effects of gravity where protective devices are called for either because of a difference between the elevation level of the required work and a lower level or a difference between the elevation level where the worker is positioned and the higher level of the materials or load being hoisted or secured. It is because of the special hazards of having to work in these circumstances, we believe, that the Legislature has seen fit to give the worker the exceptional protection that section 240 (1) provides.”

Since we agree with Supreme Court’s conclusion that none of the devices listed in Labor Law § 240 (1) were intended to or would have prevented the series of events which led to plaintiffs injury, we affirm the denial of plaintiffs’ motion for partial summary judgment and the dismissal of this cause of action. A violation of the statute must be a proximate cause of the injury before liability is imposed (see, Bland v Manocherian, 66 NY2d 452, supra). This accident was not caused by defective or missing safety equipment. Unlike the previous occasions, the operator of the excavator did not wait for plaintiff to exit the truck before attempting to remove the chain. This [920]*920conduct proximately caused the accident. Moreover, we can envision no device listed in Labor Law § 240 (1) which would be intended to guard against this type of unique incident. To the extent that the accident may have occurred by reason of the malfunction or inadequacy of the truck equipment, it constitutes injury caused by a hazard that this section of the statute does not protect against (see, De Haen v Rockwood Sprinkler Co., 258 NY 350). Moreover, the record demonstrates that plaintiff, when injured, was engaged in hauling away concrete construction debris which once had been but was no longer a part of the building or structure. Under such circumstances, Labor Law § 240 (1) has no application (see, Gentile v New York City Hous. Auth., 228 AD2d 296,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kowalik v. Lipschutz
81 A.D.3d 782 (Appellate Division of the Supreme Court of New York, 2011)
Vasquez Ex Rel. Bautista v. GMD Shipyard Corp.
582 F.3d 293 (Second Circuit, 2009)
Foote v. Lyonsdale Energy Limited Partnership
23 A.D.3d 924 (Appellate Division of the Supreme Court of New York, 2005)
Paolangeli v. Cornell University
296 A.D.2d 691 (Appellate Division of the Supreme Court of New York, 2002)
Martucci v. Tirro Construction Corp.
192 Misc. 2d 22 (New York Supreme Court, 2002)
Owen v. Commercial Sites, Inc.
284 A.D.2d 315 (Appellate Division of the Supreme Court of New York, 2001)
Sajta v. Latham Four Partnership
282 A.D.2d 969 (Appellate Division of the Supreme Court of New York, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
274 A.D.2d 917, 711 N.Y.S.2d 241, 2000 N.Y. App. Div. LEXIS 8252, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bailey-v-irish-development-corp-nyappdiv-2000.