Badger State Lumber Co. v. G. W. Jones Lumber Co.

121 N.W. 933, 140 Wis. 73, 1909 Wisc. LEXIS 249
CourtWisconsin Supreme Court
DecidedJune 3, 1909
StatusPublished
Cited by13 cases

This text of 121 N.W. 933 (Badger State Lumber Co. v. G. W. Jones Lumber Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Badger State Lumber Co. v. G. W. Jones Lumber Co., 121 N.W. 933, 140 Wis. 73, 1909 Wisc. LEXIS 249 (Wis. 1909).

Opinion

Barnes, J.

The rule is well settled that in executory contracts, where specific performance cannot be enforced, either party has the power to stop the performance on the other side by an explicit order to that effect, by subjecting himself to such damages as will compensate the other party for being stopped in the performance on his part at that point or stage in the execution of the contract. In such cases it is held that an action cannot be maintained to recover the contract price, but may be maintained to recover damages for the breach of the contract. Ward v. Am. H. F. Co. 119 Wis. 12, 25, 96 N. W. 388; Fountain City D. Co. v. Peterson, 126 Wis. 512, 106 N. W. 17; Merrick v. N. W. Nat. L. Ins. Co. 124 Wis. 221, 226, 102 N. W. 593; Tufts v. Weinfeld, 88 Wis. 647, 60 N. W. 992; Woodman v. Blue Grass L. Co. 125 Wis. 489, 494, 103 N. W. 236, 104 N. W. 920; Engeldinger v. Stevens, 132 Wis. 423, 424, 112 N. W. 507.

The decisions of this court upon the question under discus[80]*80sion are in liannony with the great weight of authority elsewhere. Mr. Page states the rule apjdicable where one party to a contract, who is not himself in default, has covenants still to he performed when the breach is committed by the other party, as follows:

“The adversary party cannot ignore the breach, perform the covenants of the contract on his part to be performed, and recover the entire contract price as if no breach had occurred. This state of facts often exists in breach by renunciation.” 3 Page, Contracts, § 1435. See cases cited in notes 2 and 3, p. 2219.

If the contract was still executory the defendant might breach it, and would thereby subject itself to the payment of such damages as would fairly compensate the plaintiff for the breach, and ordinarily such damages would be the difference between the contract price of the lumber and its value at the' time of the breach. Ganson v. Madigan, 13 Wis. 67, 72; S. C. 15 Wis. 144, 150; Chapman v. Ingram, 30 Wis. 290.

The general rule that a breach of an executory contract gives a right of action for damages for the breach and not for recovery of the purchase price is not modified by the case of Boyington v. Sweeney, 77 Wis. 55, 45 N. W. 938. It is there held that where the vendor tenders a delivery in accordance with the terms of the contract, and an actual delivery is prevented by the refusal of the vendee to accept and receive the article at the time and place agreed upon, the vendor may sue for and recover the purchase price. In this case the plaintiff failed to furnish cars within a reasonable time, and before they were furnished a portion of the logs sold were burned, and it was held that the offer to deliver was-tantamount to an actual delivery, and that the vendor had in fact performed his part of the contract. The case-of Pratt v. S. Freeman & Sons Mfg. Co. 115 Wis. 648, 92 N. W. 368, holds that where a vendor, in an executory contract for the sale of goods to be paid for on delivery, discovers that the [81]*81vendeo has become insolvent, he may store the property for the buyer and sue for and recover the purchase price. No other case in this court is called to our attention that has any tendency to mitigate the rigor with which the general rule referred to has been enforced.

It is a conceded fact in the case that the defendant wrote plaintiff on November 29, 1907, stating explicitly that it would he impossible for it to take the stock bargained for. Certain reasons were stated in the letter for the decision arrived at, which were found by the jury to he groundless. The letter was received in due course of mail and was replied to by the plaintiff upon the day following its date. The important questions in the case therefore are: (1) Was the contract executory when defendant’s letter was received ? (2) If it was, did the defendant by its subsequent conduct waive the renunciation of the contract contained in its letter? Whatever difficulties the ease may present do not arise out of any uncertainty as to what the law is on the points involved. A correct application of the facts to the established rules of law is all that is necessary in order to determine the rights of the parties.

When does a contract, executory when made, become executed so that the vendor may sue and recover the purchase price of the article contracted for ? In the early case of Ganson v. Madigan, 13 Wis. 67, 72, the court held:

“Where the vendor has actually .taken all the steps necessary to vest the title to the goods sold in the vendee, he may sue for goods sold and delivered, and the rule of damages would be the contract price; but where he is ready and willing to perform, and offers to do' so, but the vendee refuses, even though the title is not vested in the vendee, the vendor still has his action on the contract for damages; but the rule of damages in such case would be the actual injury sustained, which is ordinarily the difference between the value of the property at the time of the refusal and the price agreed on.”

[82]*82TRe contract in this ease was for tRe sale of a reaper, and tRe vendee was informed tRat Re could Rave Ris pick of a large number of reapers skipped to tRe agent of tRe vendor in knocked-down form. TRe vendee refused to make any selection, and tRe court Reid tRat because of tRe failure of the vendor to set up tRe reaper and make an offer or tender of it as an entirety Re could not recover tRe purckase price, but only damages for tRe breacR of tRe contract. TRe decision was re-examined at some lengtk and re-affirmed on a second appeal. 15 Wis. 144, 150. TRe rule adopted in this case Ras not been departed from in any substantial particular, and it has in effect been followed in a number of cases since decided. Tuffs v. Weinfeld, 88 Wis. 641, 60 N. W. 992; Hoffman v. King, 58 Wis. 314, 317, 17 N. W. 136; Ward v. Am. H. F. Co. 119 Wis. 12, 25, 96 N. W. 388; McMillan v. Fox, 90 Wis. 173, 62 N. W. 1052.

Under tRe autRorities cited, and assuming that tRe title to tRe lumber contracted for did not pass to tRe vendee in tRe contract, we fail to see any logical ground for saying that suck contract was not an executory one in so far as it related to lumber not delivered when tRe letter of renunciation was written. A portion of tRe lumber was sawed and in pile at Du-rand, Wisconsin. As to suck lumber it was necessary to separate tRe No. 3 and better lumber from tRat below tRe grade of No. 3 and to ascertain tRe quantity of tRe same. EacR party migkt furnisR an inspector, and in case of disagreement it was provided tRat an inspector of tRe National Hardwood Lumber Association should act as umpire to settle the dispute. If tRe vendee failed to select an inspector, then tRe vendor might inspect, and suck inspection skould be final. TRe vendor was required to Raul tRe lumber from the pile and deliver it on board cars at Durand. A portion of the lumber was at two or three different country mills several miles distant from Durand. TRe contract required suck lumber to be inspected and tallied in tRe same manner as tRat located at [83]*83Durand, and also required the vendor to haul the same to Du-rand and deliver it on hoard cars. There was also a small quantity of lumber not sold under the contract mixed with that which was, and it necessarily would have to be separated before the contract was completed by the vendor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bomberger v. McKelvey
220 P.2d 729 (California Supreme Court, 1950)
Knight v. Moore
234 N.W. 902 (Wisconsin Supreme Court, 1931)
Craig v. Higgins
224 P. 668 (Wyoming Supreme Court, 1924)
New Prague Flouring Mill Co. v. Spears
194 Iowa 417 (Supreme Court of Iowa, 1922)
Smith v. Lingelbach
187 N.W. 1007 (Wisconsin Supreme Court, 1922)
Sussman v. Gustav
186 P. 882 (Washington Supreme Court, 1920)
Sheffield-King Milling Co. v. Jacobs
175 N.W. 796 (Wisconsin Supreme Court, 1920)
J. B. Bradford Piano Co. v. Hacker
156 N.W. 140 (Wisconsin Supreme Court, 1916)
Fernekes v. Nugent Sanitarium
149 N.W. 393 (Wisconsin Supreme Court, 1914)
Allen v. City of Greenwood
133 N.W. 1094 (Wisconsin Supreme Court, 1912)
German American Bank v. Webster Manufacturing Co.
128 N.W. 48 (Wisconsin Supreme Court, 1911)
Glidden State Bank v. School District No. 2 of Jacobs
128 N.W. 285 (Wisconsin Supreme Court, 1910)
Richards v. Manitowoc & Northern Traction Co.
121 N.W. 937 (Wisconsin Supreme Court, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
121 N.W. 933, 140 Wis. 73, 1909 Wisc. LEXIS 249, Counsel Stack Legal Research, https://law.counselstack.com/opinion/badger-state-lumber-co-v-g-w-jones-lumber-co-wis-1909.