Badger Lumber Co. v. Mullins

275 S.W. 957, 310 Mo. 602, 1925 Mo. LEXIS 862
CourtSupreme Court of Missouri
DecidedOctober 7, 1925
StatusPublished
Cited by1 cases

This text of 275 S.W. 957 (Badger Lumber Co. v. Mullins) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Badger Lumber Co. v. Mullins, 275 S.W. 957, 310 Mo. 602, 1925 Mo. LEXIS 862 (Mo. 1925).

Opinion

BLAIR, J.

Suit in equity to cancel certain special tax bills issued in payment for a sewer in Kansas City. From a judgment for defendants, plaintiffs have appealed.

By Ordinance 45305, passed and approved May 2, 1923, sewer districts 457, 458 and 459 were constituted *607 a joint sewer district. Snch ordinance provided for the construction of a joint district sewer to care for storm water and sanitary sewage, and provided that such joint district sewer might be constructed as a unit or in sections. It was to be paid for by special tax bills issued against each lot or parcel of land within such joint sewer district. Said sewer districts had been previously created and were served by a sanitary sewer sufficient at the time to care for the sanitary sewage of the districts, but not to take care of the storm water. Such water followed a natural drain or watercourse. The joint district sewer here involved comprised 340 feet of 72-inch sewer, 1220 feet of 84-inch sewer and 660 feet of double-box reinforced concrete sewer 5' 3" x 5' 3" with catch basins, manholes, interceptor, etc. The 72-inch’and 84-inch portions were circular. Said joint district sewer was constructed almost entirely in sewer district 4'59 along said natural drain, which carried the surface water of that and the other sewer districts comprising the joint sewer district. As constructed the joint district sewer extended from Sixty-eighth and Oak streets to Seventy-first Street and Grand Avenue. There is no contention that the construction contract was not substantially complied with.

The joint district sewer was built by W. G. Mullins Construction Company as contractor. Defendant W. C. Mullins is president of that company. Defendant Heim-Overly Realty Company is the owner of the tax bills here sought to be canceled. Defendants W. C. Mullins and W. C. Mullins Construction Company filed answers disclaiming any interest in said tax bills. Defendant Heim-Overly Realty Company purchased the tax 'bills after the work was performed and before this suit was instituted.

The petition alleged a number of grounds for cancellation of the tax bills, hut it will not be necessary to notice them all. As appears in the appellants’ brief and as stated in oral argument here, appellants now rely *608 •upon only three grounds for such .cancellation. The facts will be further developed in connection with our consideration of the several contentions.

I. The assault upon the tax bills, which appears to be most earnestly pressed here, is that plaintiffs’ Exhibits 6 and 7, which were the original tracings from which blue prints were furnished to prospective bidders, did not •contain detailed plans for the reinforced monolithic concrete type of sewer, for which the contract was let, and that such plans and accompanying* specifications (Exhibit 8) did not contain sufficient data and information upon their face to enable a bidder to make an intelligent bid upon such type of construction and that they connot be pieced out by plans on file in the office of the city engineer covering the use of such material. Because of such alleged omissions, the contract let by the Board of Public Works is said to be void.

Upon Exhibit 7 there appear cross sections of the double-box sewer and also cross sections of the 72-inch and 84-inch sewers calling for the use of brick and plain monolithic concrete. There are no cross sections shown of either the 72-inch or 84-inch sewers, to be built of reinforced monolithic concrete or of segment blocks. Notice to contractors was published which called for bids upon 340 lineal feet of 72-inch sewers and 1220 lineal feet of 84-inch sewer, based upon the use of plain monolithic concrete, reinforced monolithic concrete or segment blocks. Brick construction was not called for. A contractor could submit his bid based upon either or all of said materials. Upon Exhibit 6 appéared the following note: “If contract is let for Reinforced Monolithic Concrete Sewer, Supplementary Plans will be furnished. ’ ’

Defendants offered in evidence Exhibit B, which was the plan of a standard section of reinforced monolithic concrete sewer which had been used wherever sewers had been built of that material by Kansas City since 1917, *609 when such plan was made. Blue prints of Eixhibit B were on file in the office of the city engineer and could be obtained by prospective bidders or the public upon application. Some of the contractors kept such plan on file in their offices. Mr. Mullins testified that his company had the same in its office and that it was before his' company when its bid was prepared and submitted.

Only Exhibits 6, 7 and 8 were delivered to prospective bidders who called for the plans and specifications in response to the notice to contractors. Exhibit 9 showed that blue prints and specifications had been delivered to nine prospective bidders. The notice to contractors stated that the plans 'and specifications could be seen at the office of the Secretary of the Board of Public Works. Both the specifications and the notice to contractors provided that reinforced monolithic concrete might be used in the construction of the sewer.

Upon the 72-inch and 84-inch circular sewer, four bids for plain monolithic concrete, two bids for reinforced monolithic concrete and four bids for segment blocks were received. T. M. Walsh and W. C. Mullins Construction Company were the only bidders submitting bids based upon the use of all three materials. The Mullins Construction Company bid was the lowest bid on all three. The contract was awarded to that company for reinforced monolithic concrete construction.

It is the contention of plaintiffs that bidders did not have sufficient information from Exhibits 6, 7 and 8, which were the plans and specifications (including a proposed form of contract), to bid intelligently upon the use of reinforced monolithic concrete construction. They offered the testimony of a number of witnesses to the effect that the use of Exhibit B was necessary in order to bid upon that material. Sonne testimony to the contrary was offered by defendants. We think plaintiffs are correct in this and that an intelligent bid upon the work, using reinforced monolithic concrete for the circular portion of the sewer, could not be made without *610 studying Exhibit B or being familiar with its requirements because of former examination or use of that plan. There is no cross section for a sewer of that material, either on Exhibit 6 or Exhibit 7. The specifications refer to the plans for details thereon. As there was nothing on Exhibits 6 and 7 to furnish such details, they could only be obtained by following up the suggestions in the note on Exhibit 6 and going to the Board of Public Works or the city engineer for (Exhibit B.

The question then is whether such situation restricted the bidding and rendered the contract illegal and void. Plaintiffs contend that this is true.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Giers Improvement Corp. v. Investment Service, Inc.
235 S.W.2d 355 (Supreme Court of Missouri, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
275 S.W. 957, 310 Mo. 602, 1925 Mo. LEXIS 862, Counsel Stack Legal Research, https://law.counselstack.com/opinion/badger-lumber-co-v-mullins-mo-1925.