Badger Lumber Co. v. Mayes

57 N.W. 519, 38 Neb. 822, 1894 Neb. LEXIS 577
CourtNebraska Supreme Court
DecidedJanuary 4, 1894
DocketNo. 5056
StatusPublished
Cited by3 cases

This text of 57 N.W. 519 (Badger Lumber Co. v. Mayes) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Badger Lumber Co. v. Mayes, 57 N.W. 519, 38 Neb. 822, 1894 Neb. LEXIS 577 (Neb. 1894).

Opinion

Irvine, O.

This was an action brought by the Badger Lumber Company against Willmer Mayes, George D. Mayes, and a number of other defendants for the purpose of foreclosing a mechanic’s lien upon a lot in the city of Lincoln. The petition states two causes of action. The first alleges the sale and delivery by plaintiff to the two Mayeses between November 16, 1888, and December 13, 1888, of material for the construction of a building upon the premises. The second cause of action alleges the sale and delivery between August 10 and November 15, 1888, of lumber and building material to one D. R. McCurdy for the construction of the same building; this count alleging that the Mayeses were the owners of the land, and that Mc-Curdy was a contractor with them for the inside finish of the building, for which it was alleged that the lumber was furnished. The New Hampshire Fire Insurance Company, by answer, sets up a mortgage upon the premises, [825]*825executed by the Mayeses September 11,1888, and recorded October 2, 1888; and Henry E. Lewis, by answer, sets up another mortgage dated and recorded upon the same days. One Korsmeyer and one Noll seem also to have set up mechanics’ liens upon the premises, although their pleadings do not appear in the transcript. L. B. Treman and F. A. Cropsey seem also to have set up mortgages upon the premises, but their pleadings do not appear in the transcript. The decree established the lien of the plaintiff upon its second cause of action, and the lien of Korsmeyer, as mechanics’ liens of equal priority and senior to all others. It establishes the liens of the New Hampshire Fire Insurance Cqmpany and Lewis, under their mortgages, as of equal priority, and next junior to the mechanics’ liens of plaintiff and Korsmeyer; the lien of the plaintiff upon its first cause of action, and that of Noll, as mechanics’ liens of equal priority and next in order; and the liens of Treman and Cropsey as junior to the others; and ordered foreclosure accordingly. The Mayeses appeal, and the New Hampshire Fire Insurance Company also asks that the decree be modified in so far as it establishes a lien on behalf of the plaintiff, superior to that of its . mortgage.

It appears by inference from the pleadings, and seems to be conceded in the briefs, that such material as was furnished by the plaintiff to McCurdy, and which forms the basis of the second cause of action alleged by plaintiff, consisted of lumber delivered not at the premises, but at the planing mill of McCurdy, where it is claimed it was worked up into finishing material for the building. Mayes Brothers, in support of their pleadings, urge first, that the claim, or lien of plaintiff upon its second cause of action was not filed within time, and this because the evidence fails to show any delivery of material within sixty days of the filing; it being claimed that the single item of the account bringing the furnishing within that time is unsupported by the [826]*826evidence. It is next claimed that the law does not provide for any lien for materifls furnished at a place other than where the building is constructed, or for the purpose of being worked over into other articles in which the original material is not distinguishable; and, finally, that there was failure of proof as to the amount and value of the lumber bought by McCurdy and actually used by him in the construction of this building. We think only the second of these points is properly presented to us for review. The bill of exceptions is in such a condition that it is exceedingly difficult, if not absolutely impossible, to ascertain just what the evidence was, and give it its due force; and we frankly state that after a conscientious and laborious effort to study the ease upon this bill, that effort, was abandoned as fruitless. The bill opens with an intelligible and intelligent stipulation as to certain material facts, and thereupon follows a record of certain objections and rulings upon questions and answers appearing in depositions at the end of the record; then follows the testimony of certain witnesses, which, from certain objections made, seems to be testimony in rebuttal. Next comes a group of original instruments offered in evidence, with no intelligible marks of identification. Then follows a great mass of testimony, type written, in all parts trying to the eyes, for the most part appearing to be a “carbon copy,” in some parts illegible, and, in one place at least, showing that a portion has been omitted. Under the rule established in Dawson v. Williams, 37 Neb., 1, this palpable omission will be in itself sufficient reason for not considering any exceptions based upon the insufficiency of the evidence. But we think, in addition to this, that some consideration is due to the court, and that appellants should at least be required to present to this court a record written in a legible manner and arranged in such a way that the court may ascertain upon whose part the different portions of the evidence were offered, if not the order in which they were received, [827]*827and also without the difficulty of solving an enigma determine what evidence was before the trial court, and what excluded. If the appellants fail to do this, this court should presume, in matters not clearly appearing, that there was evidence justifying the trial court in its findings. We shall, therefore, presume, for the reasons just stated, that there was evidence before the trial court justifying its findings upon the controverted issues. It does appear from the •pleadings, and is admitted in the briefs, that the material furnished by plaintiff, which forms the basis of its second cause of action, was not delivered where the building was erected, but at the planing mill of McCurdy, and we are by this brought to a consideration óf the contention that no lien can be claimed on account of such delivery.

In Great Western Mfg. Co. v. Hunter, 15 Neb., 32, the court, speaking through Cobb, J., said: “I have no doubt that under the provisions of our statute then in force,-lumber or other building material, sold on general book account without regard to any particular building, if used by the purchaser in the erection or reparation of a building upon land of which he is the owner, the vendor of such lumber or other building material may have his lien.” And in Foster v. Dohle, 17 Neb., 631, it was said by Maxwell, J.: This liability of the owner of a building which is being erected or repaired is not placed on the ground of a contract made with the owner by the person performing the labor or furnishing the material; because usually there is no such contract between them, and when there is, the right of the party to a lien is unquestioned; but upon the ground that as the labor or material contributed to the erection or reparation of the building of which the owner receives the benefit, the law imposes upon him the responsibility, for sixty days at least, of seeing that the claims are paid. * * * So far as it may be necessary to carry this purpose into effect, the law should be liberally construed.’,’ In Marrener v. Paxton, 17 Neb., 634, it is [828]*828said: “We have no doubt that in a proper case one furnishing materials in good faith for the erection of a building under an agreement with a contractor for that purpose, may file a mechanic’s lien upon the structure and the lots on which it stands. The lien is given, however, not upon the ground that a contract was made by the owner with such subcontractor, but because -the material so furnished was used in the erection of the building.” In Irish v. Pheby, 28 Neb., 231, the court, commenting upon Foster v. Dohle, supra,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Finn v. Whitten
109 N.W.2d 376 (Nebraska Supreme Court, 1961)
Stearns-Roger Manufacturing Co. v. Aztec Gold Mining & Milling Co.
14 N.M. 300 (New Mexico Supreme Court, 1908)
Grand Island Banking Co. v. Koehler
78 N.W. 265 (Nebraska Supreme Court, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
57 N.W. 519, 38 Neb. 822, 1894 Neb. LEXIS 577, Counsel Stack Legal Research, https://law.counselstack.com/opinion/badger-lumber-co-v-mayes-neb-1894.