Bach v. Sarich

445 P.2d 648, 74 Wash. 2d 575, 1968 Wash. LEXIS 799
CourtWashington Supreme Court
DecidedOctober 4, 1968
Docket40103
StatusPublished
Cited by45 cases

This text of 445 P.2d 648 (Bach v. Sarich) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bach v. Sarich, 445 P.2d 648, 74 Wash. 2d 575, 1968 Wash. LEXIS 799 (Wash. 1968).

Opinion

Williams, J.

This appeal arises out of a suit to enjoin further construction of an apartment building which would extend out over the surface of Bitter Lake in Seattle, and to compel removal of the existing structure.

Bitter Lake is a nonnavigable, natural body of water about 19 acres in area, situated in the north section of the city of Seattle. It is unmeandered, which means that in the original federal government survey the surveyors did not locate the shoreline, but merely ran the government section lines across the lake. As a result many shoreline property owners also own subdivided portions of the lake bed. The lake is surrounded principally by single residences, together with a few multiple residences, a public school ground, and a small city park. Residents of the area have long used the entire lake surface for recreational activities.

The plaintiffs are 24 property owners who own upland abutting the lake and, in some instances, parts of the lake bed, or who otherwise have access rights to the lake by reason of an easement to the lake shore. Defendants own a parcel of land abutting on the east side of the lake at the south end, about two-thirds of which is upland and one-third lake bed. Title is traced to an 1872 federal government patent, which made no reference to the lake.

The south end of the lake, including defendants’ property, has been business zoned for many years, and was formerly *577 operated as Playland Amusement Park. The property is currently zoned commercial general (CG) by the city of Seattle. In zoning the land around the lake the city ran its zoning lines across the lake surface so that the entire lake bed is zoned. Defendants’ submerged land is zoned commercial general, while other portions of the lake bed are zoned residential.

In August, 1966 defendants purchased the property in question, after having procured preliminary architectural plans for the construction of four apartment buildings. Apartment buildings Nos. 1 and 2 were to be constructed partly on the upland, but would extend approximately 130 feet out into the lake, supported on two finger-like piers secured by cement pilings. Apartments Nos. 3 and 4 were to be constructed entirely on the upland abutting the lake. Mortgage commitments were obtained based on these plans, and on June 12, 1967, a building permit was issued by the city of Seattle.

On June 5, 1967, excavation of the upland was commenced and on June 8 or 9 dirt was first pushed into the lake about 25 feet in order to form a base or pad. Some of the plaintiffs immediately protested to defendants and began making an investigation to determine the extent of defendants’ construction plans. The protests went unheeded so plaintiffs on July 5, 1967, brought an action to enjoin defendants from filling or building over the surface of the lake. In conjunction with that action they posted a $1,000 bond and obtained an exparte temporary order restraining the defendants from interfering with the surface area and shoreline of Bitter Lake.

The motion for a temporary injunction was heard on July 15, 1967, by a different department of the superior court than that which later heard the case on the merits. The court denied the motion but delayed the effective date of the order so that plaintiffs might petition this court for a writ of review. On July 20, 1967, that petition was denied by this court on procedural grounds. It was understood at *578 the time that the ruling did not reach the merits of the petition.

On July 21, 1967, the temporary restraining order was dissolved. Plaintiffs then made every effort to get the case to trial and in fact secured a substantially earlier trial date than would have been possible through the normal progression of the trial docket in King County. Trial was commenced on October. 10, 1967.

Pending the trial on the merits, defendants proceeded as rapidly as possible with the construction of apartment No. 1 and the concrete slab to support it. The slab projects out into the lake approximately 130 feet and is 77 feet wide. Beneath it the lake is filled with dirt, and pilings of steel beams are used to support it. The slab will be 1.18 feet above high water and 6.18 feet above low water. The apartment constructed on the slab will be three stories in height. At the time of trial it was planned that both apartments Nos. 1 and 2 would extend out over the water. However, in oral argument in this court defendants stated that the plans for apartment No. 2 had been modified so that it would be constructed entirely on upland.

The trial court determined that defendants had no right to build out into Bitter Lake, and enjoined them from further construction over the surface of the lake. In addition, defendants were ordered to remove the existing structure and earth fill, which had been put there during the period prior to the trial.

Defendants’ 12 assignments of error are directed to (1) the trial court’s determination that defendants had no right to build out into Bitter Lake, (2) the remedy granted in view of hardship caused to defendants relative to hardship plaintiffs would suffer if the mandatory injunction were denied, (3) prejudice of the trial judge in view of his personal experience as attorney in a prior case which dealt with surface rights of lake shore owners, (4) the trial court’s findings that defendants disregarded protests of plaintiffs and the pendency of this suit, and its failure to include a specific finding on defendants’ good faith, and (5) the trial *579 court’s failure to find adverse possession of the area in question by defendants’ predecessor in title.

In the challenge to the trial court’s determination that defendants had no right to build out into Bitter Lake, defendants emphasize the effect of the commercial zoning imposed on their property. Defendants contend that their apartment is a riparian use, and that reasonableness is the test for its permissibility. They further contend that reasonableness in this case is a legislative determination expressed in the city zoning ordinance. In other words, the Seattle City Council, by conferring a commercial general zoning classification on this property, and issuing a building permit, determined that an apartment is a reasonable and proper use of this tract, which includes lake bed property.

Riparian rights and privileges are conferred upon a property owner by virtue of the contiguity of his property to a body of water. Mayer v. Grueber, 29 Wis. 2d 168, 138 N.W.2d 197 (1965). Although we have never promulgated an all-inclusive definition of riparian rights, we have previously recognized as riparian rights on nonnavigable lakes the rights of swimming, fishing, boating, and bathing. Snively v. Jaber, 48 Wn.2d 815, 296 P.2d 1015, 57 A.L.R.2d 560 (1956). Further, these rights have been characterized as vested property interests, included in the protection afforded by Const, art. 1 § 16, which provides that private property shall not be taken or damaged for public or private use without just compensation. In re Clinton Water Dist.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lester And Susan Riley v. David And Susan Valaer
Court of Appeals of Washington, 2020
Proctor v. Huntington
238 P.3d 1117 (Washington Supreme Court, 2010)
Bauman v. Turpen
160 P.3d 1050 (Court of Appeals of Washington, 2007)
Green v. Normandy Park Riviera Section Community Club, Inc.
137 Wash. App. 665 (Court of Appeals of Washington, 2007)
Green v. Normandy Park
151 P.3d 1038 (Court of Appeals of Washington, 2007)
Wimberly v. Caravello
149 P.3d 402 (Court of Appeals of Washington, 2006)
Peterson v. Koester
92 P.3d 780 (Court of Appeals of Washington, 2004)
Pinecrest Homeowners Ass'n v. GLEN A. CLONINGER ASS'N
62 P.3d 938 (Court of Appeals of Washington, 2003)
Pinecrest Homeowners Ass'n v. Glen A. Cloninger & Associates
115 Wash. App. 611 (Court of Appeals of Washington, 2003)
PUBLIC UTILITY DIST. v. State, Dept. of Ecology
51 P.3d 744 (Washington Supreme Court, 2002)
Public Utility District No. 1 v. Department of Ecology
146 Wash. 2d 778 (Washington Supreme Court, 2002)
Wilhelm v. Beyersdorf
100 Wash. App. 836 (Court of Appeals of Washington, 2000)
Hollis v. Garwall, Inc.
974 P.2d 836 (Washington Supreme Court, 1999)
Hollis v. Garwall, Inc.
945 P.2d 717 (Court of Appeals of Washington, 1997)
Responsible Urban Growth Group v. City of Kent
868 P.2d 861 (Washington Supreme Court, 1994)
Franco-American Charolaise, Ltd. v. Oklahoma Water Resources Board
1990 OK 44 (Supreme Court of Oklahoma, 1990)
Mid-America Pipeline Co. v. Wietharn
787 P.2d 716 (Supreme Court of Kansas, 1990)
Brown v. Voss
715 P.2d 514 (Washington Supreme Court, 1986)
Department of Ecology v. Abbott
694 P.2d 1071 (Washington Supreme Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
445 P.2d 648, 74 Wash. 2d 575, 1968 Wash. LEXIS 799, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bach-v-sarich-wash-1968.