Baber v. Ohio Mut. Ins. Co.

2021 Ohio 1625
Ohio Court of Appeals·Decided May 10, 2021·No. 17-20-10·Published·Cited by 2 cases

Opinion

IN THE COURT OF APPEALS OF OHIO THIRD APPELLATE DISTRICT

SHELBY COUNTY

LORMA BABER, PLAINTIFF-APPELLANT, CASE NO. 17-20-10 v.

OHIO MUTUAL INSURANCE COMPANY ET AL., OPINION

DEFENDANTS-APPELLEES.

Appeal from Shelby County Common Pleas Court Trial Court No. 19CV000239

Judgment Affirmed

Date of Decision: May 10, 2021

APPEARANCES:

Stanley R. Evans for Appellant Joseph F. Nicholas and Frank H. Scialdone for Appellee

MILLER, J.

{¶1} Plaintiff-appellant, Lorma Baber, appeals the May 21, 2020 decision of the Shelby County Court of Common Pleas granting the motion for summary judgment of defendant-appellee, Allenbaugh Insurance Agency (“AIA”). For the reasons that follow, we affirm.

I. Facts and Procedural History

{¶2} Baber is the owner of a farm and farmhouse located in Maplewood, Ohio. On October 12, 2017, the farmhouse was severely damaged by a fire. While the fire was still in progress, Baber contacted AIA to report the fire and to file an insurance claim. Baber’s insurance policy, which was underwritten by United Ohio Insurance Company, a subsidiary of Ohio Mutual Insurance Company (“OMIC”), was procured for her by AIA. Under the terms of the insurance policy, Baber could receive either the actual cash value of the damage caused by the fire or the costs to repair or rebuild the farmhouse up to the policy limit of $284,000. However, the policy included the following provision: “We pay no more than the actual cash value of the damage unless and until actual repair or replacement is complete. If repair or replacement of the damage is not completed within 180 days after loss, we pay no more than the actual cash value of the damage.”

{¶3} On December 13, 2017, Baber received a letter from OMIC’s claims adjuster, Leann Wente. Wente explained that OMIC had determined the actual cash

value of the damage caused by the fire to be $201,506.05 and that Baber would be issued a check in that amount. In addition, the letter restated the full text of the 180- day provision. Wente instructed Baber that if Baber did not repair or rebuild the farmhouse within 180 days from the date of the fire as required by the 180-day provision, OMIC would pay no more than the actual cash value. Wente indicated Baber thus had until April 10, 2018, to repair or rebuild the farmhouse. Enclosed with Wente’s letter was an estimate of the costs to rebuild the farmhouse prepared by OMIC’s chosen construction contractor.

{¶4} Shortly after receiving Wente’s letter, Baber contacted Greg Woolley, AIA’s co-owner/insurance agent, to talk about the 180-day provision and to express her concerns about rebuilding the farmhouse by the April 10, 2018 deadline. Although Baber was inclined to rebuild the farmhouse, she was worried the work would not be completed by the deadline, in part because she did not receive OMIC’s estimate until two months after the fire. Baber was also concerned inclement winter weather could delay completion of the rebuild. According to Baber, she communicated these concerns to Woolley, and Woolley responded by telling her OMIC would be “fair” with respect to the 180-day provision and the April 10, 2018 deadline. Baber said she understood Woolley’s statement as an assurance that OMIC would be flexible with the 180-day provision and that she could still recover the full policy limit of $284,000 even if the farmhouse was not rebuilt by the

deadline. However, Woolley denied making any promises to Baber about the 180- day provision or the deadline. Regardless, after Baber and Woolley’s December 2017 conversation, Baber decided to rebuild the farmhouse.

{¶5} In the months following Baber and Woolley’s December 2017 conversation, Baber arranged to have the farmhouse rebuilt. Baber hired her own contractor, Nathan Persinger, to prepare an estimate for the construction work required to rebuild the farmhouse. Baber had used Persinger for other projects, and he was at the farmhouse a few days after the fire as he had previously been hired to do repairs to the barn. The record does not indicate when Baber requested Persinger to prepare the estimate, but it was not until March 7, 2018, that Baber received Persinger’s estimate. Persinger proposed to rebuild the farmhouse for $331,620. On March 9, 2018, Baber accepted Persinger’s proposal. Construction on the farmhouse commenced shortly thereafter.

{¶6} On or about March 13, 2018, Wente sent a second letter to Baber. In this letter, Wente indicated that the April 10, 2018 deadline had been extended and that “the 180 day replacement cost clause [would] expire May 26, 2018.” While Baber acknowledged the topic of extending the April 10, 2018 deadline had been raised during previous conversations with Wente, Baber insisted she did not specifically request an extension. Once she received Wente’s second letter, Baber talked to Persinger and asked him whether the work on the farmhouse could be

completed by the new May 26, 2018 deadline. Persinger told Baber it would be impossible to finish rebuilding the farmhouse by May 26, 2018. Although Persinger continued working on the farmhouse after Baber informed him of the new deadline, construction was not completed by May 26, 2018.

{¶7} On or about May 31, 2018, Wente sent a third and final letter to Baber.

In this letter, Wente confirmed that “because the repairs were not completed by May 26, 2018, [OMIC would] be unable to pay the replacement cost difference and therefore there [would] be no further payments for the dwelling.” Thus, Baber received only the $201,506.05 check for the actual cash value of the damage caused by the fire. Baber has used most of the money she received from OMIC to pay Persinger for his work on the farmhouse, which remains unfinished.

{¶8} On October 11, 2019, Baber filed a complaint against OMIC and AIA.

Baber’s complaint stated a cause of action for breach of contract against OMIC and a cause of action for promissory estoppel against both OMIC and AIA.1 In her complaint, Baber alleged Woolley had represented that she was not required to completely rebuild the farmhouse on or before April 10, 2018, in order to receive the full policy limit of $284,000. Baber further alleged she relied to her detriment on Woolley’s representations because she failed to negotiate a contract with

1 On March 18, 2020, all “existing and potential claims” against OMIC were dismissed with prejudice by agreement of the parties.

Persinger requiring Persinger to rebuild the farmhouse on or before April 10, 2018. On November 14, 2019, AIA filed its answer to Baber’s complaint.

{¶9} On March 13, 2020, AIA filed a motion for summary judgment on Baber’s claim of promissory estoppel. Thereafter, Baber filed her memorandum in opposition to AIA’s motion for summary judgment, and AIA filed a reply brief in support of its motion for summary judgment.

{¶10} On May 21, 2020, the trial court granted AIA’s motion for summary judgment. The trial court concluded that even if Woolley did promise Baber that OMIC would be “fair” concerning the 180-day provision and the April 10, 2018 deadline, Woolley’s promise was not clear and unambiguous. The trial court found that Woolley’s alleged promise was not sufficiently specific to induce the reliance necessary to sustain a claim for promissory estoppel.

II. Issue Raised on Appeal

{¶11} On June 19, 2020, Baber timely filed a notice of appeal asserting one assignment of error:

The trial court erred in awarding summary judgment against Appellant, Lorma Baber, and in favor of Appellee, Allenbaugh Insurance Agency.

Free access — add to your briefcase to read the full text and ask questions with AI

Baber v. Ohio Mut. Ins. Co., 2021 Ohio 1625 (Ohio Ct. App. 2021).

2021 Ohio 1625 (Baber v. Ohio Mut. Ins. Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bless v. HomeWAV, L.L.C.
Ohio Court of Appeals, 2026
Basford v. Butler
2025 Ohio 2829 (Ohio Court of Appeals, 2025)
Maynard v. Barkley
2025 Ohio 1890 (Ohio Court of Appeals, 2025)