B. Smith Contractors, Inc. v. Olshan Demolishing Co.

877 S.W.2d 460, 1994 Tex. App. LEXIS 1158, 1994 WL 192424
CourtCourt of Appeals of Texas
DecidedMay 19, 1994
DocketNo. 01-91-00784-CV
StatusPublished
Cited by1 cases

This text of 877 S.W.2d 460 (B. Smith Contractors, Inc. v. Olshan Demolishing Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
B. Smith Contractors, Inc. v. Olshan Demolishing Co., 877 S.W.2d 460, 1994 Tex. App. LEXIS 1158, 1994 WL 192424 (Tex. Ct. App. 1994).

Opinion

OPINION ON MOTION FOR REHEARING

HEDGES, Justice.

We withdraw our earlier opinion, substitute the following opinion in its stead, vacate our judgment rendered July 15, 1993, and grant appellees’ motion for rehearing.

In the case before us, we must decide the effect of mutual termination of a contract on the obligations of the parties regarding payment for services rendered before termination. Appellant B. Smith Contractors (B. Smith) appeals a take-nothing judgment in its suit against Olshan Demolishing Co. (Ol-shan) for breach of contract. B. Smith challenges the factual and legal sufficiency of the evidence supporting the jury findings of no breach by Olshan and zero damages to B. Smith. It further asserts that the trial court erred in severing its tortious interference claim, in refusing to admit evidence of 01-shan’s motions to convert appellant’s chapter 11 bankruptcy proceeding to chapter 7, and in striking B. Smith’s eleventh amended petition. We affirm the judgment of the trial court.

In the fall of 1985, the Harris County Hospital District awarded Olshan a contract to clear and prepare the site for the L.B.J. Hospital in Houston. On November 5, 1985, Olshan and B. Smith signed a $348,000 subcontract to be completed in 77 calendar days “after notice to proceed.” The subcontract provided that B. Smith would be liable for $1,000 for each day that B. Smith was “delinquent in failing to complete” its work. The subcontract included all the site work — stone drain; outfall structure; retention pond; grading, compacting, and bringing in selected fill to make the building pads; erosion control; and hydromulch. B. Smith received notice to proceed on December 2, 1985.

Olshan had the initial responsibility of clearing the site. It encountered a number of problems in the removal of an existing structure. A truck terminal was supported by 140 piers with belled bottoms that were about eight feet deeper than anticipated, ending below the water table. As Olshan removed the piers, water seeped into the resulting hole. B. Smith could not properly backfill the hole with field dirt as originally specified and needed additional fill materials.

On February 13, 1986, B. Smith notified Olshan that it could not continue to perform under the terms of the subcontract. On February 14, 1986, Olshan wrote B. Smith, stating:

This letter shall be your written notice that Olshan Demolishing Company shall take possession of the above referenced project and shall terminate the subcontract between Olshan and B. Smith Contractors, Inc., for work at the above referenced project.
You have notified Olshan Demolishing Company that you are no longer able to complete the work and that you wish to terminate this subcontract. As of February 16, 1986 Olshan Demolishing Company shall take over that portion of your work under your subcontract which remains un[462]*462completed and shall finish the work with its own resources.
The termination of this subcontract in no way relieves you of responsibility for payment of any unpayed [sic] bills and you shall be liable to Olshan for the cost to complete your work on this project as per paragraph 4 of the subcontract.

Paragraph four of the subcontract provided:

Should Subcontractor fail to perform his work properly or fail to comply with any provision of this contract or should Subcontractor fail to work on the site for three consecutive days, or more, then Olshan may, upon three (3) days’ written notice to Subcontractor, terminate his contract and take possession of the premises if Subcontractor has failed for whatever reason to correct the discrepancies or errors within such time. In such event Subcontractor shall not be entitled to receive any further payment until the work has been completed, at which time the difference, if any, between the unpaid balance on this contract and the cost to complete the Subcontractor’s work shall be paid to Subcontractor. Olshan shall be the sole judge as to whether the Subcontractor’s work has been properly performed and shall be guided by generally accepted practices among the trade. Should the cost of completion by Olshan exceed the amount remaining due to Subcontractor, Subcontractor will pay Olshan such deficiency.

On February 17, 1986, Olshan and B. Smith signed a letter agreement confirming the discontinuance of B. Smith on the job. The agreement also provided that Olshan would lease two bulldozers and one front-end loader for $42.00 per hour for each machine from B. Smith, would retain two operators at an hourly rate, and would purchase diesel fuel at $0.85 per gallon for the rented equipment. Olshan paid B. Smith approximately $30,000 under this second contract. Olshan completed B. Smith’s original subcontract obligation on March 5, 1986.

In point of error five, B. Smith asserts that there is no legal basis to support the denial of damages. In deciding a no evidence point, we consider only the evidence and inferences tending to support the finding and disregard all evidence and inferences to the contrary. Sherman v. First Nat’l Bank, 760 S.W.2d 240, 242 (Tex.1988); Otis Elevator Co. v. Joseph, 749 S.W.2d 920, 923 (Tex.App.—Houston [1st Dist.] 1988, no writ). If there is more than a scintilla of evidence to support the finding, we must overrule the no evidence point of error. Sherman, 760 S.W.2d at 242.

In point of error six, B. Smith attacks the sufficiency of the evidence to support the jury’s denial of damages. We interpret B. Smith’s point of error and the supporting argument in its brief to amount to an assertion that the jury findings of no breach by Olshan and zero damages to B. Smith are against the great weight and preponderance of the evidence.

In considering a factual insufficiency point of error, we must consider and weigh all the evidence. We should set aside a verdict only if it is so against the great weight and preponderance of the evidence that it is clearly wrong and unjust. Cain v. Bain, 709 S.W.2d 175, 176 (Tex.1986). In order to recover against Olshan for breach of contract, B. Smith must establish 1) the existence of a contract, 2) Olshan’s breach of the contract, and 3) damages.

The parties do not dispute the existence and terms of the initial subcontract dated November 5, 1985. Their disagreement centers on whether, after the cessation of its services in February 1986, B. Smith was entitled to payment for work performed before that date. B. Smith argues that because the jury found (1) the subcontract was mutually terminated, (2) B. Smith did not breach the subcontract, and (3) Olshan’s cost to complete was not in excess of B. Smith’s subcontract, B. Smith was entitled to receive the amount of the accrued billings up to its termination. B. Smith relies on McDonald v. Watkins, 353 S.W.2d 905 (Tex.Civ.App.—Fort Worth 1962, no writ), and Eastman Oil Well Survey Co. v. Hamil, 416 S.W.2d 597 (Tex.Civ.App.—Houston 1967, writ ref'd n.r.e.), for the proposition that because the subcontract was mutually terminated, without breach on its part, B.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coleman, Brenda F. v. Yvette D. Lemons
Court of Appeals of Texas, 2002

Cite This Page — Counsel Stack

Bluebook (online)
877 S.W.2d 460, 1994 Tex. App. LEXIS 1158, 1994 WL 192424, Counsel Stack Legal Research, https://law.counselstack.com/opinion/b-smith-contractors-inc-v-olshan-demolishing-co-texapp-1994.