B. M. C. Manufacturing Corp. v. Tarshis

278 A.D. 266, 104 N.Y.S.2d 254
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMay 9, 1951
StatusPublished
Cited by12 cases

This text of 278 A.D. 266 (B. M. C. Manufacturing Corp. v. Tarshis) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
B. M. C. Manufacturing Corp. v. Tarshis, 278 A.D. 266, 104 N.Y.S.2d 254 (N.Y. Ct. App. 1951).

Opinion

Bergan, J.

Defendants, so it is pleaded, agreed to deliver steel to the plaintiff. The steel was to be supplied to the defendants by a third party under an agreement standing independently on its own terms. The third party failed to deliver the steel to defendants who in turn failed to deliver it to the plaintiff and were sued for breach of contract.

Defendants served a third-party summons and complaint claiming a liability over, under the practice authorized by section 193-a of the Civil Practice Act. The Special Term denied a motion by the third party for the dismissal of the defendants’ complaint.

The practice as enlarged in 1946 (L. 1946, ch. 971) seems not yet to have been applied to a series of contractual relationships like those that are here, but we are of opinion that the Special Term was right in the view it took of the question.

This is just the kind of a ease where sequential litigation is to be cut short and decided at one time and place; and the procedure followed seems to us to fall within the language as well as the spirit of section 193-a.

The section now provides that a defendant may join as a party a person who “is or may be ” liable to him for “ all ” or a “ part of ” the plaintiff’s asserted claim. The claim against the added party ‘ must be related ’ ’ to the main claim “ by a question of law or fact common to both controversies ”. It need not rest on the same cause or on the same ground. A jural relationship rather than identity of cause is the requirement of the present statute.

It is not a complete answer to the jural relationship of successive contract liability arising from identical or dependent subject matter, that under one or both breaches of contract resort might have to be taken to the open market to fix damage. Nor is it an answer that the quantum or measure of damage might differ. If the relationship can be seen to exist the actions are properly joined and such a relationship may, indeed, be found in cases where the subject matter is neither identical nor dependent.

But even though the scope of definition has been greatly widened as to what is to be regarded as a related controversy, it must, however, still be shown that the third party will be liable over to the defendant for some part of the claim asserted in the main action, and while this is best demonstrated by a clear case of indemnity, the usefulness of the practice is not limited to indemnity in the classic sense.

[269]*269A sufficient relationship between the controversies is shown where it is asserted that the acts of the third party have presently exposed the defendant to the Idnd of lawsuit in which the third party could be required to answer to the defendant for some of the loss threatened to be adjudicated.

Ill applying this principle to the field of contract there can, of course, be a wide range of sequential relationships. Franklin E. Tyrell, Inc. v. Vahlsing (193 Misc. 454 [1947]) is one of them. A broker sued the owner of real estate for commissions arising from a contract of sale which he had procured but which the buyer breached. The defendant owner was allowed by the Queens Special Term to join the buyer as a third-party defendant, and the opinion of Mr. Justice Cuff is a careful examination of the utility of the amended practice in such a situation.

In contract litigation the obstacles of prejudgment indivisibility of the liability of joint tort-feasors which has so often plagued the procedure on liability over are not present. It was distinctly held in Fox v. Western New York Motor Lines (257 N. Y. 305) that there is no 4 liability over ” to one joint tortfeasor from another within the third-party practice set up by former subdivision 2 of section 193, notwithstanding the right of contribution after judgment made enforcible by former section 211-a. (See, also, Miele v. City of New York, 270 App. Div. 122.)

The principle and consequently the authority of these decisions have survived the enactment of the present third-party practice. (Wolf v. La Rosa & Sons, 272 App. Div. 932 [1947]; Cloud v. Martin, 273 App. Div. 769 [1947]; Green v. Hudson Shoring Co., 191 Misc. 297 [1947]; Van Pelt v. City of New York, 188 Misc. 995 [1947]; Monteverdi v. French Realty Corp., 190 Misc. 304 [1947].)

But where it can be made apparent that the unitary liability of the joint tort-feasor is not in issue and there is a possibility of recourse by a passive ” wrongdoer against an active one, the third-party practice is liberally applied to tort Etigation. (Robinson v. Binghamton Constr. Co., 277 App. Div. 468; Monteverdi v. French Realty Corp., 274 App. Div. 945; Clements v. Rockefeller, 189 Misc. 885.) Its wider application is stopped merely by the nature of tort liability.

Some of the objections to joinder of third parties which were regarded as fundamental obstacles in Nichols v. Clark, MacMullen & Riley (261 N. Y. 118 [1933]) under the former practice have been met fully in today’s practice. That case will serve to denote the depth of the changes that have been made by a [270]*270series of amendments. The Judicial Council studies proposing the amendments of 1946 treated this as the leading New York case on the subject (Twelfth Annual Report of N. Y. Judicial Council, 1946, p. 204).

The plaintiffs’ house in New Jersey had burned. Its heating system had been reconstructed under the supervision of the defendant engineers. The engineers were sued for negligence. The negligence, as pleaded in the complaint, was that defendants had recommended ‘ ‘ Celotex ’ ’ as suitable and proper for covering hot-air ducts and warm-air piping and that it was non-inflammable and adequate insulation, whereas it was inflammable, inadequate and dangerous.

The complaint pleaded further, as part of the same cause of action, that defendant engineers were negligent in preparing their plans and specifications and that as a result both of the recommended use of “ Celotex ” and negligence in making the plans, the fire had occurred (pp. 120-122). On motion of defendants the manufacturer of “ Celotex ” was joined as a party and a third-party complaint (then a supplemental answer) was served. Defendants pleaded that the third party by its advertisements had recommended the use of * ‘ Celotex ” as an insulating material for covering hot and cold-air ducts (p. 124).

The court was of opinion that the joinder should not have been made because the third party could not be liable over for the whole of the single cause of action pleaded in the complaint, i.e., that this cause of action was not limited to the negligent use of the material but that it extended also to the design of the heating plant for which the manufacturer of the material could under no theory be ultimately liable over, and since the causes had not been separated in the complaint it would not be possible to separate them in the judgment if there was a general verdict for the plaintiff.

Thus, it was said, there was nothing in the record to show that a judgment would ever be entered “ solely ” based on the use of “ Celotex ” (p. 123) and the statutory test was whether there could be liability over for “ the judgment or part of the judgment ”.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

George Cohen Agency, Inc. v. Donald S. Perlman Agency, Inc.
414 N.E.2d 689 (New York Court of Appeals, 1980)
Northern Lumber Co. v. United States Natural Resources, Inc.
50 A.D.2d 1085 (Appellate Division of the Supreme Court of New York, 1975)
Norman Co. v. County of Nassau
63 Misc. 2d 965 (New York Supreme Court, 1970)
Federation Chemicals, Ltd. v. Chemical Construction Corp.
31 A.D.2d 799 (Appellate Division of the Supreme Court of New York, 1969)
Krause v. American Guarantee & Liability Insurance
239 N.E.2d 175 (New York Court of Appeals, 1968)
New London Instrument Co. v. Taffet
38 Misc. 2d 276 (New York Supreme Court, 1962)
Rogoff v. Scheinberg
33 Misc. 2d 96 (New York Supreme Court, 1961)
Metropolitan Sand & Gravel Corp. v. Lipson
4 Misc. 2d 216 (New York Supreme Court, 1956)
Galka v. City of Albany
285 A.D. 27 (Appellate Division of the Supreme Court of New York, 1954)
Madison Avenue Properties Corp. v. Royal Insurance
281 A.D. 641 (Appellate Division of the Supreme Court of New York, 1953)
Gleason v. Sailer
203 Misc. 227 (New York Supreme Court, 1952)
Carroll Sheet Metal Works, Inc. v. Mechanical Installations, Inc.
201 Misc. 689 (New York Supreme Court, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
278 A.D. 266, 104 N.Y.S.2d 254, Counsel Stack Legal Research, https://law.counselstack.com/opinion/b-m-c-manufacturing-corp-v-tarshis-nyappdiv-1951.