B-Dunz, Inc. v. the Bilingual Montessori School of Sharon.

Massachusetts Appeals Court·Decided March 5, 2026·No. 25-P-0012·Unpublished

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

25-P-12

B-DUNZ, INC.1

vs.

THE BILINGUAL MONTESSORI SCHOOL OF SHARON.

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

This action stems from a soured business relationship

between the plaintiff, a landscaping company, and its client,

the defendant school. The plaintiff's claims and the

defendant's counterclaims were tried before a jury in the

Superior Court. The judge entered directed verdicts and

subsequently dismissed certain of the plaintiff's claims and the

defendant's counterclaims, and the jury otherwise returned

verdicts in the plaintiff's favor. After the defendant moved

for judgment notwithstanding the verdict (JNOV) and for a new

trial, the judge allowed the motion, in part, ordering a new

trial unless the plaintiff accepted a remittitur reducing the damages awarded by $2,000. Otherwise, the judge denied the motion. The plaintiff accepted the remittitur, the judge allowed the plaintiff's motion for costs, a new final judgment entered on April 19, 2024, and this appeal followed.

Because we (1) agree with the judge's rulings on the parties' motions for directed verdict and JNOV, (2) discern neither abuse of discretion nor other error in the judge's denial of the defendant's motion for a new trial, (3) are satisfied that the judge acted permissibly in limiting the defendant's use of evidence relating to insurance, (4) conclude that the defendant waived its objections to the judge's failure to give certain of its proposed jury instructions, and (5) are not persuaded that the judge abused her discretion in allowing the plaintiff's posttrial motion for costs, we affirm the judgment dated April 19, 2024.

Background. We briefly summarize relevant procedural history and facts as the jury could have found them, reserving certain details for later discussion. The plaintiff is a landscaping business founded and operated by Brian Donovan. The defendant is a school owned by Linda Valentin. In 2017, the defendant hired the plaintiff to do landscaping work. The parties orally agreed that the plaintiff would perform snow removal for the defendant; Donovan prepared a written proposal

for the work, including a schedule of plowing fees, but no written contract was signed. During the winter of 2017 to 2018, the plaintiff plowed and, at Valentin's instruction, salted the school's parking area and walkways. Although the plaintiff billed the defendant for that work, there was an unpaid balance of $10,778 on the defendant's account by March 2018.

The parties' business relationship was complicated by damage to certain parts of the defendant's premises. In the fall, the plaintiff's employees had displaced the top of an ornamental fountain (fountain damage). While snowplowing during a storm, one of the plaintiff's temporary employees damaged an ornamental tree, hydrangeas, and some boxwoods in a corner of the school's parking lot (plowing damage). Additionally, Valentin claimed that the plaintiff had damaged a number of ornamental boxwoods, which she wanted the plaintiff to replace (boxwood damage). Donovan acknowledged that the plaintiff was responsible for the fountain and plowing damage, which he consistently told Valentin that the plaintiff would fix, but he denied that the plaintiff was responsible for the boxwood damage.

On March 26, 2018, Donovan met with Valentin in an effort to collect the unpaid balance for the plaintiff's landscaping and plowing work. During the meeting, Valentin prepared a written "agreement" (settlement agreement) that she and Donovan

then signed. The settlement agreement documented the balance due to the plaintiff, the defendant's payment of $4,190 on March 26, and the defendant's agreement to pay the remaining amount due2 "upon completion of all repairs and tree replacements." A "List of damages" included in the settlement agreement identified outstanding work: replacement of "perhaps half of the boxwood," repair of areas with gravel and mulch, and replacement of the fountain top. Donovan agreed to the terms of the settlement agreement based on his understanding that the scope of the work was limited to replacement of the fountain top and repair of the plowing damage and that it would cost the plaintiff between $2,000 and $2,500. Donovan and Valentin signed the settlement agreement, and Valentin made the initial payment of $4,190.

Immediately after the initial payment was made, however, Valentin made it clear to Donovan that she expected the plaintiff to make repairs to the defendant's property that were much more expansive and expensive than those to which Donovan had agreed when he signed the settlement agreement. As a result, Donovan abandoned his efforts to negotiate a resolution

with the defendant. On March 28, 2018, the plaintiff filed a small claim action against the defendant in the District Court, seeking the unpaid balance of $6,588 on the defendant's landscaping and plowing bills. The plaintiff's small claim action was transferred to the regular civil docket and then to the Superior Court, where the plaintiff filed an amended complaint alleging breach of contract, breach of the implied covenant of good faith and fair dealing, and violation of G. L. c. 93A. The defendant answered and counterclaimed for breach of contract, negligence, fraud, abuse of process, and violation of G. L. c. 93A.

The case went to trial before a jury. As relevant to this appeal, the judge allowed the plaintiff's motion for a directed verdict in its favor on the defendant's counterclaim for abuse of process, dismissed the plaintiff's claim under G. L. c. 93A with the plaintiff's agreement, and denied the defendant's motion for a directed verdict on its counterclaims for breach of contract.3 The remaining claims and counterclaims were submitted to the jury; the jury found for the plaintiff on all of them, including in an advisory verdict on the G. L. c. 93A

counterclaim, and awarded damages of $6,588 to the plaintiff on its breach of contract claim. The judge adopted the jury's advisory verdict on the G. L. c. 93A counterclaim. Judgment entered accordingly.

The defendant moved timely for JNOV or, in the alternative, for a new trial. See Mass. R. Civ. P. 50 (b), as amended, 428 Mass. 1402 (1998). The plaintiff moved for an award of costs. The judge ordered a new trial unless the plaintiff accepted a remittitur reducing the damages awarded to the plaintiff by $2,000, but otherwise denied the defendant's motion. She allowed the motion for costs. The plaintiff accepted the remittitur, the first judgment was vacated, a new final judgment entered, and this appeal followed.

Discussion. 1. Motions for directed verdict and JNOV. a.

Free access — add to your briefcase to read the full text and ask questions with AI

B-Dunz, Inc. v. the Bilingual Montessori School of Sharon., (Mass. Ct. App. 2026).

B-Dunz, Inc. v. the Bilingual Montessori School of Sharon. (B-Dunz, Inc. v. the Bilingual Montessori School of Sharon.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Quaranto v. Silverman
187 N.E.2d 859 (Massachusetts Supreme Judicial Court, 1963)
Goldstein v. Gontarz
309 N.E.2d 196 (Massachusetts Supreme Judicial Court, 1974)
Alholm v. Town of Wareham
358 N.E.2d 788 (Massachusetts Supreme Judicial Court, 1976)
Commonwealth v. Anolik
542 N.E.2d 327 (Massachusetts Appeals Court, 1989)
Lease-It, Inc. v. Massachusetts Port Authority
600 N.E.2d 599 (Massachusetts Appeals Court, 1992)
Evans v. Multicon Construction Corp.
375 N.E.2d 338 (Massachusetts Appeals Court, 1978)
Turnpike Motors, Inc. v. Newbury Group, Inc.
596 N.E.2d 989 (Massachusetts Supreme Judicial Court, 1992)
W. Oliver Tripp Co. v. American Hoechst Corp.
616 N.E.2d 118 (Massachusetts Appeals Court, 1993)
Millennium Equity Holdings, LLC v. Mahlowitz
925 N.E.2d 513 (Massachusetts Supreme Judicial Court, 2010)
Sparrow v. Demonico
960 N.E.2d 296 (Massachusetts Supreme Judicial Court, 2012)
Psy-Ed Corporation v. KLEIN HIRSCH
947 N.E.2d 520 (Massachusetts Supreme Judicial Court, 2011)
Bucholz v. Green Bros. Co.
172 N.E. 101 (Massachusetts Supreme Judicial Court, 1930)
Situation Management Systems, Inc. v. Malouf, Inc.
724 N.E.2d 699 (Massachusetts Supreme Judicial Court, 2000)
Gath v. M/A-Com, Inc.
440 Mass. 482 (Massachusetts Supreme Judicial Court, 2003)
O'Brien v. Pearson
868 N.E.2d 118 (Massachusetts Supreme Judicial Court, 2007)
Meyer v. Wagner
784 N.E.2d 34 (Massachusetts Appeals Court, 2003)
Prozinski v. Northeast Real Estate Services, LLC
797 N.E.2d 415 (Massachusetts Appeals Court, 2003)
Harris-Lewis v. Mudge
803 N.E.2d 735 (Massachusetts Appeals Court, 2004)
I & R Mechanical, Inc. v. Hazelton Manufacturing Co.
817 N.E.2d 799 (Massachusetts Appeals Court, 2004)
DiBella v. Fiumara
828 N.E.2d 534 (Massachusetts Appeals Court, 2005)