Azusa Land Partners v. Department of Industrial Relations

191 Cal. App. 4th 1, 120 Cal. Rptr. 3d 27, 2010 Cal. App. LEXIS 2135
CourtCalifornia Court of Appeal
DecidedDecember 21, 2010
DocketNo. B218275
StatusPublished
Cited by25 cases

This text of 191 Cal. App. 4th 1 (Azusa Land Partners v. Department of Industrial Relations) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Azusa Land Partners v. Department of Industrial Relations, 191 Cal. App. 4th 1, 120 Cal. Rptr. 3d 27, 2010 Cal. App. LEXIS 2135 (Cal. Ct. App. 2010).

Opinion

Opinion

JOHNSON, J.

Azusa Land Partners (ALP) appeals from a judgment denying its petition for writ of mandate. (Code Civ. Proc., § 1085.) ALP seeks to vacate a determination by respondent Department of Industrial Relations (Department) that a planned community project is a “public work,” as defined [10]*10by Labor Code section 1720,1 and subject to prevailing wage laws applicable to public improvement work performed by private contractors as a condition of regulatory approval for their construction projects. We affirm.

FACTUAL AND PROCEDURAL BACKGROUND

Factual background

Petitioner and appellant ALP is the owner and developer of a master planned community known as the “Rosedale Project” (Project). The Project is located on over 500 acres of land in the City of Azusa (City) previously owned by the Monrovia Nursery Company (Monrovia Nursery), ALP’s predecessor in interest. The Project involves the potential development of over 1,200 homes, about 50,000 square feet of commercial construction, and public infrastructure and improvement work. To obtain approval for the Project,' Monrovia Nursery agreed to conditions imposed by the City to perform certain public infrastructure and improvement work, including the construction of a public school and adjoining park, freight undercrossings, sanitation district facilities, and backbone and in-tract street, bridge, storm drain, sewer, water/reservoir, dry utilities, park and landscaping improvements for the Cities of Glendora and Azusa. These conditions are memorialized in a May 27, 2004 development agreement between the City and Monrovia Nursery.

In August 2005, the City and ALP entered into a funding and acquisition agreement (Acquisition Agreement), to provide for partial funding of required public facilities through Mello-Roos bonds (Mello-Roos Community Facilities Act.of 1982; Gov. Code, § 53311 et seq.). Pursuant to the Acquisition Agreement, the City agreed to establish a community facilities district to sell special (Mello-Roos) tax bonds to be used to pay for the design, planning, engineering, installation and construction of certain facilities eligible for public financing (the Eligible Facilities). ALP was to construct the Eligible Facilities, which would be owned, operated and maintained by the City of Azusa or Glendora, the Azusa Unified School District or the Los Angeles [11]*11County Metropolitan Transportation Authority, pursuant to a series of agreements (the Funding Agreements) between ALP and these public entities.2 The Eligible Facilities are identified in exhibit A to the Acquisition Agreement.

The Funding Agreements refer to “Publicly Financed Facilities,” as the subset of Eligible Facilities which will actually be built using proceeds of Mello-Roos bonds. According to ALP, the Publicly Financed Facilities were not identified in the Acquisition Agreement because it was not known at the time that agreement was executed specifically which Eligible Facilities would be constructed using Mello-Roos bonds. The Publicly Financed Facilities were subsequently identified in a modification to the Acquisition Agreement (exhibit B), executed between the City and ALP in 2007, after the Mello-Roos bonds were issued.

On June 5, 2006, after consolidated special elections, the City authorized the creation of Community Facilities District No. 2005-1, Rosedale (CFD), approved a bond indebtedness of up to $120 million to be incurred by the CFD, and authorized the city clerk to record a notice of a special tax lien on real property located within the CFD.3 The county collects special taxes in the same manner as ad valorem property taxes, and the proceeds are transferred to CFD’s fiscal agent, Wells Fargo Bank. All public infrastructure and facilities required as a condition of approval of the Project (the Eligible Facilities) were eligible for CFD funds. The fiscal agent distributes the funds. The city manager and finance director must approve payment to ALP of any Mello-Roos bond proceeds.

Under the Acquisition and Funding Agreements, ALP is obligated to perform the public improvement work required by the City as a condition of approval of the Project even if the actual cost of that infrastructure construction exceeds the amount of bond funds authorized to pay for the public improvement work performed. That scenario has been borne out. The total cost of construction of all the Eligible Facilities is approximately $146 million. The CFD issued approximately $71 million in Mello-Roos bonds, the proceeds of which were used to fund construction of the Publicly Financed Facilities. The remaining $76 million in required public improvements must be constructed at private expense.

[12]*12 Administrative proceeding

In October 2005, an administrative inquiry was filed requesting the Department to investigate and issue a determination as to whether the entire Project constituted a “public work” under section 1720, subject to the prevailing wage mandates of section 1771.4 In response, ALP argued the Project was not a public work, but simply a private development project as to which the City lacked a proprietary interest, but as to which it required construction of certain public improvements as a condition of approval. ALP also asserted that although it was obligated and intended to pay prevailing wages for the public improvements actually financed with the proceeds of Mello-Roos bonds, it was not required to do so for the construction of any infrastructure improvement for which it did not receive Mello-Roos financing.

In October 2007, the Department issued a public works coverage determination (Determination). The Determination found that the entire Project constituted a public work within the meaning of section 1720, subdivision (a)(1). According to the Determination, payment of Mello-Roos bond proceeds to ALP, a private developer, for the construction of public facilities and infrastructure improvements constituted a payment of public funds. (§ 1720, subd. (b)(1).) Because the Project was funded, in part, through public funds, it satisfied the definition of a “public work” under subdivision (a)(1). However, the Determination also found the Project satisfied the exemption of subdivision (c)(2), which provides that only those public infrastructure improvements required as a condition of regulatory approval are subject to the prevailing wage requirements, so long as the public funds contributed to the Project do not exceed the cost of construction of the required public improvements. Accordingly, the Determination held that ALP was required to comply with prevailing wage laws only as to that portion of the Project involving construction of public improvements required as a condition of the City’s approval of the Project.

ALP filed an administrative appeal as to the portion of the Determination that held that all public infrastructure improvements required as a condition of approval are subject to prevailing wage requirements, even if those improvements are not funded through the proceeds of Mello-Roos bonds.

In July 2008, the Department affirmed its initial Determination by a decision on administrative appeal. The decision held that (1) the proceeds of [13]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brinsmead v. Elk Grove Unified Sch. Dist.
California Court of Appeal, 2023
Busker v. Wabtec
California Supreme Court, 2021
Lungin v. Ulta Salon Cosmetics & Fragrance CA4/1
California Court of Appeal, 2021
Kaanaana v. Barrett Business Services, Inc.
California Supreme Court, 2021
Moustafa v. Bd. of Registered Nursing
240 Cal. Rptr. 3d 873 (California Court of Appeals, 5th District, 2018)
Kaanaana v. Barrett Business Services, Inc.
California Court of Appeal, 2018
Kaanaana v. Barrett Bus. Servs., Inc.
240 Cal. Rptr. 3d 636 (California Court of Appeals, 5th District, 2018)
Baker v. WCAB
California Court of Appeal, 2017
Baker v. Workers' Comp. Appeals Bd.
220 Cal. Rptr. 3d 761 (California Court of Appeals, 5th District, 2017)
Cinema West v. Baker
California Court of Appeal, 2017
Cinema W., LLC v. Baker
220 Cal. Rptr. 3d 415 (California Court of Appeals, 5th District, 2017)
Boling v. Public Employment Relations Board
10 Cal. App. 5th 853 (California Court of Appeal, 2017)
Ammari v. Union Pacific Railroad Co. CA4/3
California Court of Appeal, 2016
Golden State Water Co. v. Casitas Municipal Water District
235 Cal. App. 4th 1246 (California Court of Appeal, 2015)
Sheet Metal Workers' International Ass'n, Local 104 v. Duncan
229 Cal. App. 4th 192 (California Court of Appeal, 2014)
Soroush-Azar v. Palmer CA4/1
California Court of Appeal, 2013
Housing Partners I, Inc. v. Duncan
206 Cal. App. 4th 1335 (California Court of Appeal, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
191 Cal. App. 4th 1, 120 Cal. Rptr. 3d 27, 2010 Cal. App. LEXIS 2135, Counsel Stack Legal Research, https://law.counselstack.com/opinion/azusa-land-partners-v-department-of-industrial-relations-calctapp-2010.