Ayalla v. Unified Gov't of Wyandotte, Co./KCK

CourtCourt of Appeals of Kansas
DecidedJuly 7, 2017
Docket116972
StatusUnpublished

This text of Ayalla v. Unified Gov't of Wyandotte, Co./KCK (Ayalla v. Unified Gov't of Wyandotte, Co./KCK) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ayalla v. Unified Gov't of Wyandotte, Co./KCK, (kanctapp 2017).

Opinion

NOT DESIGNATED FOR PUBLICATION

No. 116,972

IN THE COURT OF APPEALS OF THE STATE OF KANSAS

EVA AYALLA, Appellant,

v.

UNIFIED GOVERNMENT of WYANDOTTE COUNTY/ KANSAS CITY, KANSAS, et al., Appellees.

MEMORANDUM OPINION

Appeal from Wyandotte District Court; ROBERT P. BURNS, judge. Opinion filed July 7, 2017. Appeal dismissed.

Eva Ayalla, appellant pro se.

Ryan P. Haga, assistant counsel, for appellee Unified Government of Wyandotte County/Kansas City, Kansas.

Before GREEN, P.J., POWELL and GARDNER, JJ.

Per Curiam: Eva Ayalla appeals from a judgment of the district court dismissing her claims under the Kansas Consumer Protection Act, K.S.A. 50-623 et seq., against the Unified Government of Wyandotte County/Kansas City, Kansas. On appeal, Ayalla argues that the district court erred in dismissing her claims against the Unified Government. Because we conclude that Ayalla's appeal is premature and interlocutory, we cannot reach her substantive arguments. Accordingly, we dismiss this appeal.

1 On July 11, 2013, the Unified Government of Wyandotte County/Kansas City, Kansas (Unified Government), entered into a contract with MS K-MO Construction, LLC (MS K-MO), for project 6001, an emergency sanitary sewer replacement project to be completed near Ayalla's house. The project initially consisted of modifications to two existing manholes, construction of three new precast concrete manholes, and construction of four new line segments of 8-inch PVC pipe totaling about 352 lineal feet. On September 11, 2013, the contract was amended to add additional work.

On December 2, 2013, Angela Rome-Pyper, Ayalla's niece, signed an affidavit alleging the following facts. On or about July 20, 2013, a man named Bob Terry met with Rome-Pyper. Terry told Rome-Pyper that he was the owner of MS K-MO. Terry also told Rome-Pyper that he had been contracted by the city to replace the main sewer on Ayalla's street and that he was also authorized to replace the immediate residential sewers at a reduced cost. Rome-Pyper told Ayalla about Terry's offer. Ayalla then met with Terry and agreed to have him replace her residential sewer. When Terry was about halfway finished with her sewer replacement, Ayalla paid him $3,200. Because the work was not being completed in a timely manner, Ayalla called Willie Jones, a Unified Government engineer, and left a voicemail on his phone relaying her complaints. About 1 week later, on October 2, 2013, Ayalla filed a written complaint with the Unified Government regarding Terry's work on her residential sewer. Ayalla made the written complaint because work on her residential sewer had completely stopped. Her yard was left without sod, and she was unhappy with the condition of the new sidewalks that Terry had poured. Ayalla's niece also swore that Terry told her that he used to deal drugs and that he knew some people that would "take care of" Ayalla if she continued to complain to Willie Jones and the Unified Government.

On August 16, 2014, Schall Engineering Consulting, LLC (Schall), prepared an engineering analysis and report for Ayalla. Ayalla hired Schall to review certain documents that she had requested from the Unified Government relating to project 6001. Schall came to the following conclusions: 2 "I was informed by Ms. Ayalla that while Emergency Repair Project 6001 was being constructed, her neice [sic], Angela Rome-Pyper, was approached by Mr. Bob Terry, foreman of the sewer project, and was informed of an offer by the City to pay half the cost of a homeowner's residential sewer line replacement if they were previously connected to manholes and line segments within Project #6001. This was supported by an affidavit submitted to me by Ms. Ayalla. Ms. Ayalla then contacted Mr. Terry and he repeated to her that the city would pay half the costs for residential sewer line replacement if residents would pay the other half. Ms. Ayalla submitted to me a receipt for $3,200.00 for her residential sanitary sewer line replacement paid on August 5, 2013 and signed as received by Bob Terry. Based on the approved change order to the original bid of MS K-MO Construction, LLC, three (3) private lines were paid for by the City at a price of $3,100 each. It is my opinion that Ms. Ayalla should not have been charged to replace her line if other homeowners in the project, under similar circumstances were not charged. I recommend that Eva ask for reimbursement from the City Engineering Department, starting with a call to Willie Jones who was named as the City contact in the agreement with MS K-MO Construction, LLC.

"SPECIAL NOTE: Project #6001 was awarded to MS K-MO Construction, LLC. However, the permit to replace her private sewer line was obtained by Dove Construction Company, Edwin C. Hill, 400 N. Persimmon Circle, Kansas City, Kansas, 66061. Since no other receipts for payments by residents for private line construction were submitted to Ms. Ayalla by the City with other documents related to the project, Ms. Ayalla believes she was the only resident required to make such a payment to the contractor. It should be noted that Ms. Ayalla's residential sewer line replacement was inspected by the Building Inspection Division in a report dated August 2, 2013. The inspector was Jeffrey Hollinshed and he approved 55 feet of sewer line and 1 clean-out. After this inspection, Ms. Ayalla has experienced the following problems with this construction: 1. Her sidewalk concrete replacement was not level and was not scored properly. There are scorings where they are not needed, and no scorings in some locations where they are needed. 2. The clean-out entrance was built into this sidewalk repair, and thus has concrete covering part of the clean-out lid which will make it difficult to open in case of back-ups. 3 3. There is a depressed hole and a visible void under the new sidewalk where the fill in the private line trench has sunk or disappeared. This may result in a future collapse of the sidewalk if not resolved soon. 4. The landscape restoration on her property was not completed. There is mostly dirt and no grass or sod where equipment disturbed Ms. Ayalla's lawn. This disturbed area covers the entire west side of the property's lawn. 5. Silt fencing was placed at the edge of her yard abutting the public sidewalk. The fencing was never removed and has failed to withstand the weight of the soil sliding away from Ms. Ayalla's yard, and now dirt covers the public sidewalk and creates a slipping and falling hazard which is an [sic] serious public nuisance and a potential future lawsuit for the City.

"In conclusion, there are several remaining private property defects related to poor sewer contractor workmanship including inadequate landscape restoration, poor sidewalk restoration, and a public nuisance on the sidewalk in the street right-of-way. I would recommend Ms. Ayalla contact Inspector Jeffrey Hollinshed in the Building Inspection Division at 913-573-8631 for a re-inspection of the private line construction with the intent of correcting all remaining problems at no expense to Eva."

On November 1, 2013, the Unified Government wrote to Daniel Morris, the owner of MS K-MO, and informed him of a number of outstanding issues relating to project 6001. The Unified Government wrote Daniel Morris again on December 30, 2013, because MS K-MO had still not completed project 6001 and fixed the issues identified in the November 1, 2013, letter. The December 30, 2013, letter gave notice to MS K-MO that it was in default of its contract with the Unified Government for project 6001.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fredricks v. Foltz
557 P.2d 1252 (Supreme Court of Kansas, 1976)
Henderson v. Hassur
562 P.2d 108 (Court of Appeals of Kansas, 1977)
Pioneer Operations Co. v. Brandeberry
789 P.2d 1182 (Court of Appeals of Kansas, 1990)
Honeycutt v. City of Wichita
836 P.2d 1128 (Supreme Court of Kansas, 1992)
Kansas Medical Mutual Insurance v. Svaty
244 P.3d 642 (Supreme Court of Kansas, 2010)
Ullery v. Othick
372 P.3d 1135 (Supreme Court of Kansas, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Ayalla v. Unified Gov't of Wyandotte, Co./KCK, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ayalla-v-unified-govt-of-wyandotte-cokck-kanctapp-2017.