AWI Sec. & Investigators, Inc. v. Whitestone Constr. Corp.

2018 NY Slip Op 5907
CourtAppellate Division of the Supreme Court of the State of New York
DecidedAugust 23, 2018
Docket303759/14 6724
StatusPublished

This text of 2018 NY Slip Op 5907 (AWI Sec. & Investigators, Inc. v. Whitestone Constr. Corp.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AWI Sec. & Investigators, Inc. v. Whitestone Constr. Corp., 2018 NY Slip Op 5907 (N.Y. Ct. App. 2018).

Opinion

AWI Sec. & Investigators, Inc. v Whitestone Constr. Corp. (2018 NY Slip Op 05907)
AWI Sec. & Investigators, Inc. v Whitestone Constr. Corp.
2018 NY Slip Op 05907
Decided on August 23, 2018
Appellate Division, First Department
Mazzarelli, J., J.
Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431.
This opinion is uncorrected and subject to revision before publication in the Official Reports.


Decided on August 23, 2018 SUPREME COURT, APPELLATE DIVISION First Judicial Department
Dianne T. Renwick,J.P.
Sallie Manzanet-Daniels
Angela M. Mazzarelli
Ellen Gesmer
Jeffrey K. Oing,JJ.

303759/14 6724

[*1]AWI Security and Investigators, Inc., Plaintiff-Appellant,

v

Whitestone Construction Corp., Defendant-Respondent.


Plaintiff appeals from the order of the Supreme Court, Bronx County (Douglas E. McKeon, J.), entered on or about May 1, 2017, which granted defendant's motion to dismiss the action as time-barred pursuant to a contractual period of limitations.



David H. Singer & Associates LLP, New York (Christopher S. McCann of counsel), for appellant.

Goetz Fitzpatrick, LLP, New York (Michael R. Fleishman of counsel), for respondent.



MAZZARELLI, J.

Defendant Whitestone Construction Corp., a general contractor (Whitestone), hired plaintiff AWI Security and Investigations, Inc. (AWI) to provide security services at four different construction sites, pursuant to four separate subcontracts. Each subcontract involved a public construction project, three by the New York City School Construction Authority (SCA) and one by the New York City Housing Authority (NYCHA). The subcontracts were identical and contained the following relevant provision, in pertinent part:

"Article 33 — CLAIMS AND DISPUTE RESOLUTION

Paragraph 33.5 Limitation on Suit

"No claim or action by [AWI] arising out of or related to th[e] [contract] shall lie or be maintained against [Whitestone] unless such action is commenced no later than six (6) months after either: [a] the cause of action accrued, [b] the termination or conclusion of th[e] [contract], or [c] the last day [AWI] performed any physical work at the [project site], whichever of the proceeding [sic] events shall occur first."

The complaint alleges that "[b]eginning in 2011 through April 2012, at the specific instance and request of [Whitestone], AWI was required to perform" the work at issue, although, as discussed below, AWI maintains that the record is unclear when it actually completed the work. In any case, the parties were both named as defendants in a prevailing wage class action commenced in 2012 by AWI workers (the Wage Action). In a letter dated May 24, 2012, counsel for AWI informed counsel for Whitestone that it considered the Wage Action to be frivolous and that it intended to move for summary judgment dismissing it. In the same letter, however, it asserted that a total amount of $232,213.13 was due and owing it for its work under the subcontracts and demanded payment of same. In a responsive letter dated June 5, 2012, counsel for Whitestone informed counsel for AWI that it was relying upon an indemnity provision in the subcontracts that entitled it to withhold money due and owing to AWI pending the outcome of the Wage Action, stating that

"[w]hile it may be ultimately determined that the [Wage Action] Plaintiffs' claims are frivolous and/or without merit, be advised that Whitestone will continue to enforce the indemnity provisions contained in the contract

s with your client until such determination is made by the [Wage Action] Court."

The letter further noted that, in connection with one of the jobs, payment was not yet due since the SCA had not yet approved a change order. AWI did move for summary judgment in the Wage Action. However, after the summary judgment motion was denied and the Wage Action became protracted, it decided it could no longer wait to be paid. Accordingly, it commenced this action, in July 2014.

Whitestone moved to dismiss the complaint pursuant to CPLR 3211(a). It specifically argued that the action was time-barred by the contractual limitations provision, which required AWI to commence suit within six months of April 2012, the last time it performed physical work under any of the subcontracts. Whitestone asserted that, in accordance with the limitations clause, this was the earliest of the three possible dates for measuring the time to commence suit, the others being the "accrual date" and termination of the subcontracts.

In opposition to the motion, AWI asserted that Whitestone had been paid in full by NYCHA and the SCA on all four of the projects for which it provided security services, so Whitestone could not rely on certain provisions in the subcontracts making AWI's right to payment contingent on payment to Whitestone by the owners. It argued that the contractual limitations period did not bar the claim because Whitestone, pursuant to General Municipal Law section 106-b(2), which requires a contractor who receives any payment from a public owner to make prompt payment to its subcontractors for their work, imposed upon it a continuing and ongoing obligation to pay AWI. AWI also relied on the June 5, 2012 letter from Whitestone's counsel, claiming that it constituted an acknowledgment of the debt as contemplated by General Obligations Law section 17-101, thus defeating any statute of limitations claim.

In reply, Whitestone submitted the affidavit of its Vice President, who denied that it had been paid in full by the SCA and NYCHA. She asserted that for two of the four jobs, SCA was retaining funds in connection with the Wage Action. With respect to the other two jobs, [*2]Whitestone's Vice President acknowledged it had been paid, but claimed that it was holding the money in case it were later determined that AWI had to indemnify it as the result of an adverse judgment in the Wage Action.

The court granted the motion. It held that, according to the complaint, AWI last performed physical work under any of the subcontracts in April 2012, more than six months before July 2014 when it initiated this action, thus violating the clear terms of the contractual limitations period. The court rejected the argument made by AWI under General Municipal Law section 106-b(2), finding that nothing in that statute indicates that a contractor has a continuing obligation to pay which obviates the effect of any applicable statute of limitations. The court further found that the June 5, 2012 letter did not extend the statute of limitations since it did not recognize an existing debt, or contain matter inconsistent with the intention to pay a debt.

On appeal, AWI first argues that Whitestone failed to satisfy its burden of establishing a date on which the limitations period began to run, since nothing in the record indicates that April 2012, the date which Whitestone maintains is the applicable one, was actually the date on which AWI last performed physical work under the subcontracts. It is true that the complaint is somewhat ambiguous in its description of when the work was actually completed. However, the June 5, 2012 letter on which AWI so heavily relies is in response to a May 24, 2012 letter that AWI placed in the record, in which its counsel demanded from Whitestone's counsel the full amount sought in this action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

D&S Restoration, Inc. v. Wenger Constr. Co., Inc.
2018 NY Slip Op 2768 (Appellate Division of the Supreme Court of New York, 2018)
Executive Plaza, LLC v. Peerless Insurance
5 N.E.3d 989 (New York Court of Appeals, 2014)
West-Fair Electric Contractors v. Aetna Casualty & Surety Co.
661 N.E.2d 967 (New York Court of Appeals, 1995)
Action Interiors, Inc. v. Component Assembly Systems Inc.
144 A.D.2d 606 (Appellate Division of the Supreme Court of New York, 1988)
Otis Elevator Co. v. George A. Fuller Co.
172 A.D.2d 732 (Appellate Division of the Supreme Court of New York, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
2018 NY Slip Op 5907, Counsel Stack Legal Research, https://law.counselstack.com/opinion/awi-sec-investigators-inc-v-whitestone-constr-corp-nyappdiv-2018.