Aviation Constructors v. Federal Express Corp.

814 F. Supp. 710, 25 Fed. R. Serv. 3d 860, 1993 U.S. Dist. LEXIS 1221, 1993 WL 51320
CourtDistrict Court, N.D. Illinois
DecidedFebruary 2, 1993
Docket91 C 2835
StatusPublished
Cited by2 cases

This text of 814 F. Supp. 710 (Aviation Constructors v. Federal Express Corp.) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aviation Constructors v. Federal Express Corp., 814 F. Supp. 710, 25 Fed. R. Serv. 3d 860, 1993 U.S. Dist. LEXIS 1221, 1993 WL 51320 (N.D. Ill. 1993).

Opinion

MEMORANDUM OPINION AND ORDER

ASPEN, District Judge:

The plaintiff in this contract dispute, a joint venture consisting of Aviation Constructors Inc., Alex Munoz General Contractor, Inc., and Castle Construction Corp., (collectively “ACI”), has moved for partial summary judgment on the complaint, 1 summary judgment on defendant Federal Express Corporation’s (“Federal Express”) counterclaim, and for sanctions. For the following reasons, we deny plaintiffs motions for partial summary judgment on the complaint, deny in part and grant in part its motion for summary judgment on the counterclaim, and grant its motion for sanctions.

I. Factual Background

In 1988, Federal Express began work on the design and construction of a 287,000 square foot Metroplex Terminal at O’Hare International Airport. Having hired Teng & Associates to design the facility, the project proceeded on a fast track, with some portions of the project being built while others were still being designed. Federal Express divided the construction work into five bid packages, and entered into separate agreements with different contractors on each of them.

In June 1988, ACI agreed with Federal Express to perform Bid Package No. 3. The relevant contract contained three parts. First, ACI was to construct the foundation walls and underground utilities for the cargo facility. Federal Express agreed to pay $2,420,783 for the work, which was to be completed by December 2, 1988. Second, ACI agreed to provide administrative and coordinating services. Under the contract, Federal Express reserved the right to assign bid packages and subcontractors to ACI. For a fee, ACI would then administer or coordinate the subcontractors’ activities. The fee was to be based on the value of the assigned subcontracts and was to be calculated on a sliding scale. ACI was to receive a maximum fee of $1,400,000 for subcontracts exceeding $35 million. Finally, ACI was to provide general conditions and coordination from December 2,1988 through April 1,1990 (the projected completion date for the entire *712 Metroplex) for work subsequent to the construction specified in Bid Package No. 3. Federal Express was to pay $49,224 per month for this service, with the total fee for the general conditions not to exceed $787,-584.

Under the contract, ACI was to furnish a performance bond in the amount of its fees. For its part, Federal Express was to reimburse the contractor for the cost of the bond.

On December 26, 1989, Federal Express took partial occupancy of the facility. In 1990, after disagreements had erupted between the parties, ACI filed suit against Federal Express to recover on the contract. Federal Express answered the complaint and counterclaimed for over $1 million dollars. 2 $885,960 of the counterclaim stemmed from Federal Express’ allegation that the project should have been completed prior to December 26, 1989.

In April, 1991, ACI served a request for “[a]ll reports, diaries, logs or other such documents, including site studies, test reports, daily and weekly reports, supervisor’s diary, periodic status reports, internal status report memoranda, informal notes, and meeting minutes.” Federal Express did not turn over any project status reports at that time.

In February, 1992, ACI deposed James E. Gibson, a Federal Express employee, who testified that monthly project status reports were issued on the Metroplex project. In March, six such status reports were turned over to plaintiff, three of which (September, November, and December, 1989) indicated that partial occupancy would occur on December 23, 1989, and stated that this was six months ahead of schedule. On April 3, 1992, defendant voluntarily dismissed those counterclaims relating to the alleged delay.

II. Discussion

A. First Motion for Partial Summary Judgment on the Complaint

In its first motion for partial summary judgment on the complaint, ACI seeks judgment on the amounts due it under the contract for (1) administration of subcontracts, (2) provision of general conditions, and (3) payment of performance bonds. We address each of these issues in turn.

(i) Fee for Administration

ACI claims that it is due $1,400,000 for its administration of subcontracts, since total subcontracts exceeded $35 million. While Federal Express concedes that total subcontracts exceeded $35 million, it contends that plaintiff was to be compensated only for the value of assigned subcontracts — that is, subcontracts which Federal Express entered into and then assigned to plaintiff, or subcontracts that Federal Express asked ACI to enter into directly. Defendant further asserts that the value of the assigned subcontracts only amounts to $22,693,353.50. At bottom, then, this is a question of contract interpretation: was plaintiffs fee to be based on the value of all subcontracts, regardless of their assignment, or was the fee only to cover the value of subcontracts directly assigned to ACI.

When a contract is clear on its face, the plain language of the document controls, and the agreement must be enforced as written. Federal Deposit Insurance Corp. v. Zaborac, 773 F.Supp. 137, 140 (C.D.Ill.1991). Where the contract is ambiguous, however, the court must resort to extrinsic evidence to interpret the meaning of the documents and the intent of the parties. Lumpkin v. Envirodyne Industries, Inc., 933 F.2d 449, 456 (7th Cir.1991), cert. denied, — U.S. -, 112 S.Ct. 373, 116 L.Ed.2d 324 (1991). A contract is ambiguous if it is susceptible to more than one meaning. MacDonald-Smith v. FMC Corp., 713 F.Supp. 264, 268 n. 2 (N.D.Ill.1989), aff'd, 902 F.2d 37 (7th Cir.1990). In Illinois, ambiguity exists when either the agreement itself is unclear, or when, despite clear language, “anyone familiar with the real-world context of the agreement would wonder what it meant with reference to the particular question that has arisen.” Federal Deposit Insurance Co. v. W.R. Grace & Co., 877 F.2d 614, 620 (7th Cir.1989), cert. *713 denied, 494 U.S. 1056, 110 S.Ct. 1524, 108 L.Ed.2d 764 (1990).

The contract between ACI and Federal Express is susceptible to more than one interpretation. Exhibit A-8 to the contract provides for a “[g]eneral construction fee for administration of sub-contractors.” Exh. A-8, Part II. The exhibit also states that “Federal may enter directly into a construction agreement with subcontractors,” and that “Federal, at its option, may assign the administration of its contracts to the General Contractor [Aviation Construction] for a fee in accordance with Part II of Exhibit A-8.” Exh. A-8, E(i). Finally, Federal Express’ Project Manager was to inform Aviation Construction in writing of any subcontract assignments.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bateman v. Federal Deposit Insurance
112 F. Supp. 2d 89 (D. Massachusetts, 2000)
McNulty v. Travel Park
853 F. Supp. 144 (E.D. Pennsylvania, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
814 F. Supp. 710, 25 Fed. R. Serv. 3d 860, 1993 U.S. Dist. LEXIS 1221, 1993 WL 51320, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aviation-constructors-v-federal-express-corp-ilnd-1993.