Avent v. Mississippi Power & Light Co.

94 So. 3d 1199, 2011 WL 6056446, 2011 Miss. App. LEXIS 750
CourtCourt of Appeals of Mississippi
DecidedDecember 6, 2011
DocketNo. 2010-CA-00865-COA
StatusPublished
Cited by2 cases

This text of 94 So. 3d 1199 (Avent v. Mississippi Power & Light Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Avent v. Mississippi Power & Light Co., 94 So. 3d 1199, 2011 WL 6056446, 2011 Miss. App. LEXIS 750 (Mich. Ct. App. 2011).

Opinions

GRIFFIS, P.J.,

for the Court:

¶ 1. This case considers whether the circuit court was in error to dismiss Glen Avent’s complaint against Entergy Mississippi, Inc. for failure to prosecute under [1200]*1200Mississippi Rule of Civil Procedure 42(b), or to grant summary judgment in favor of Sheraton Tunica Corporation under Mississippi Rule of Civil Procedure 56. We find no error and affirm.

FACTS

¶ 2. Avent was employed by Andy Bland Construction Company. On July 3, 1994, Avent was working at a construction site in Tunica County, Mississippi. He operated a man-lift that became stuck in wet sand. There was an effort to free the lift and pull it out of the sand. The lift came into contact with an overhead electrical line. As a result, Avent was injured.

¶3. Sheraton owned the property that was the construction work site. Sheraton contracted with W.G. Yates and Son Construction Co., as the general contractor. Entergy had installed the electrical line. Andy Bland was a subcontractor of Yates.

¶ 4. On November 8, 1996, Avent filed a lawsuit. The complaint named several defendants, including Mississippi Power & Light (now known as Entergy Mississippi, Inc.) Yates, Sheraton, and several John Does. After the defendants were served, they responded to the complaint, and the parties engaged in discovery.

¶ 5. Sheraton filed a motion for summary judgment on May 21, 1997. Avent promptly responded to Sheraton’s motion.

¶ 6. The circuit court entered an “Agreed Scheduling Order” on April 18, 1997, requiring all discovery completed by August 30, 1997; plaintiff’s experts to be designated by June 15, 1997; defendant’s experts by July 30, 1997; and all motions filed by September 30, 1997. On August 28, 1997, the circuit court entered an “Agreed Amended Scheduling Order,” requiring all discovery completed by November 30, 1997; plaintiffs experts designated by August 30, 1997; defendant’s experts by September 30, 1997; and all motions filed by December 30, 1997. On November 13, 1997, the circuit court entered another “Agreed Amended Scheduling Order,” requiring all discovery completed by March 30, 1998; plaintiffs experts designated by December 30, 1997; defendant’s experts designated by January 30, 1998; and all motions filed by April 30, 1998.

¶ 7. Yates filed a motion for summary judgment on May 1, 1998. After the circuit court heard the summary-judgment motions, the court granted Sheraton’s motion, which was filed on May 21, 1997, and dismissed Sheraton as a party on October 6, 1998. A week later, the circuit court granted Yates’s motion for summary judgment and dismissed Yates as a party.

¶ 8. Several filings were entered on the docket from the time of the final judgment through August 10, 1999, when the clerk filed a letter from Entergy’s counsel that gave notice that the name of his law firm had changed. None of the filings were significant.

¶ 9. For almost six years, according to the clerk’s docket, this case was dormant.1 The clerk’s docket sheet does not indicate that any further pleadings were filed or action taken until February 14, 2005, when the plaintiffs attorney filed a designation of experts.

¶ 10. Almost another year passed with no action on this case. On January 11, [1201]*12012006, Avent filed a supplemental response to Entergy’s interrogatories. After this, the docket indicates the parties’ filings as follows:

March 29, 2006: Avent mailed a letter to Entergy, investigating whether the case could be disposed of through mediation.

April 5,2006: Entergy responded by mail to Avent’s March letter.

April 10, 2006: Entergy sent a follow-up letter to Avent regarding mediation.

April 12,2006: Avent set mediation for May 30,2006.

April 12,2006: Entergy confirmed mediation dates, but questioned the value of mediation due to the length of time that the case had been dormant.

April 18,2006: Entergy filed a notice of service of its third set of interrogatories.

April 25, 2006: Entergy sent a letter to Avent cancelling mediation, requesting a new deposition, and expressing concern about the likelihood of finding crucial witnesses given the age of the case.

May 9,2006: Avent sent Entergy a letter with potential deposition dates.

June 6, 2006: Entergy filed its motion to dismiss based on want of prosecution; at the same time, Entergy filed an affidavit explaining its inability to locate witnesses.

February 9, 2009: Avent filed a motion for a pretrial conference.

February 10, 2009: Entergy filed a response to Avent’s pretrial-conference motion.

May 26, 2009: Entergy filed a supplemental motion to dismiss.

September 23, 2009: Avent sent Entergy a proposed pretrial statement.

February 18,2010: Entergy filed a notice of hearing on its motion to dismiss.

March 15, 2010: Entergy supplemented its motion to dismiss, detailing its inability to locate certain witnesses.

April 30, 2010: The circuit court dismissed Entergy from Avent’s lawsuit.

¶ 11. The circuit court held a hearing on Entergy’s motion to dismiss on April 20, 2010. At the conclusion of the hearing, the circuit judge ruled:

The question arises as to how long is too long? How much prejudice constitutes undue prejudice? In considering this matter, and [sic] I did give attention to it prior to my coming here today, there was a lot of inactivity during the middle age of this case. And then there was very nominal activity between 2006 and today.
If this case were to be continued, we still would not be complete. We still would not have completed the discovery in this case. If I would allow this case to continue, when would I ever be able to dismiss any other case? I know that each case stands on its own feet. But considering the length of delay, the reason for the delay, the facts having be[1202]*1202come dim due to delay, witnesses who cannot be found, the increased cost of discovery, the time that it would take to replace experts and the numerous periods of inactivity, the Court finds that this case is imminently ripe for a dismissal. And if I would not dismiss this case, I would be remiss in the performance of my duties.
Therefore, the case is dismissed, finally dismissed.
I’m soiry, but I don’t see how I could ever dismiss a case in the future if I did not dismiss this case.

(Emphasis added).

¶ 12. On April 30, 2010, the circuit judge signed a final judgment granting Entergy’s motion to dismiss. It is from this judgment that Avent now appeals.

ANALYSIS

A. The Dismissal of Claims Against Entergy

¶ 13. Rule 41(b) of the Mississippi Rules of Civil Procedure states:

For failure of the plaintiff to prosecute ..., a defendant may move for dismissal of an action or of any claim against him.... Unless the court in its order for dismissal otherwise specifies, a dismissal under this subdivision ..., operates as an adjudication upon the merits.

M.R.C.P. 41(b).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

David McKean v. Yates Engineering Corporation
210 So. 3d 1037 (Court of Appeals of Mississippi, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
94 So. 3d 1199, 2011 WL 6056446, 2011 Miss. App. LEXIS 750, Counsel Stack Legal Research, https://law.counselstack.com/opinion/avent-v-mississippi-power-light-co-missctapp-2011.