AVCO ELECTRIC, INC. v. APC DEVELOPMENT GROUP, INC., & Others.

CourtMassachusetts Appeals Court
DecidedJuly 16, 2026
Docket25-P-0895
StatusUnpublished

This text of AVCO ELECTRIC, INC. v. APC DEVELOPMENT GROUP, INC., & Others. (AVCO ELECTRIC, INC. v. APC DEVELOPMENT GROUP, INC., & Others.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AVCO ELECTRIC, INC. v. APC DEVELOPMENT GROUP, INC., & Others., (Mass. Ct. App. 2026).

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

25-P-895

AVCO ELECTRIC, INC.

vs.

APC DEVELOPMENT GROUP, INC., & others.1

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

The plaintiff, AVCO Electric, Inc. (AVCO), appeals from a

judgment entered in the Superior Court following a bench trial.

We consider whether the trial judge erred in determining that

AVCO is responsible for installing a security system where such

work was not included in the electrical specifications of the

project documents and was not part of AVCO's bid as a

subcontractor on a public works project in Gloucester. We

affirm.2

1 Harriman Associates, Inc., and Merchants National Bonding, Inc.

Following a settlement agreement, Harriman Associates, 2

Inc. is not a party to this appeal. Background. We recite the facts that the judge could have

found, reserving some facts for later discussion. See Spinosa

v. Tufts, 98 Mass. App. Ct. 1, 3 (2020). APC Development Group,

Inc. (APC) entered a valid and binding contract to provide

general contracting services for a public construction project

at 19 Harbor Loop in Gloucester (Project) for the town of

Gloucester. Merchants National Bonding, Inc. (Merchants) served

as surety and Harriman Associates, Inc. (Harriman) was the

project engineer which prepared the architectural plans and

documents for the Project. AVCO submitted a sub-bid for the

Project's electrical work to the City of Gloucester. AVCO

claims that it limited its bid to Division 26 of the

construction documents. On September 25, 2019, AVCO entered a

valid and binding statutory form of subcontract with APC for the

electrical work. On February 8, 2020, AVCO submitted a request

for information to Harriman seeking clarification whether AVCO

was responsible for the Project's security system. Harriman

informed AVCO that it was responsible for the security system.

The security system is not mentioned in Division 26 but is

referenced in the electrical drawings and in Division 28 of the

construction documents. AVCO completed the work on the security

system under protest.

On October 14, 2020, AVCO submitted an invoice for the

additional labor and materials necessary to install the

2 Project's security system. APC claimed that the security system

was within AVCO's scope of work and part of its bid for the

electrical work, and thus refused to pay the invoice.

On October 19, 2020, AVCO filed a complaint against APC,

Merchants, and Harriman in the Superior Court. AVCO brought

breach of contract and payment bond and quantum meruit claims

for failure to pay for the extra work against APC and Merchants.

AVCO also brought claims against Harriman for misrepresentation,

and violation of G. L. c. 93A, relating to the sufficiency of

the Project's specifications. AVCO moved for summary judgment

on its claims against Harriman and Harriman filed cross motions

for summary judgment on those same claims. APC and Merchants

joined in Harriman's opposition to AVCO's motion for summary

judgment and cross-moved for summary judgment against AVCO. The

judge denied all motions and cross motions for summary judgment

except Harriman's cross motion as to the c. 93A claim. On April

30, 2024, AVCO and Harriman executed a confidential settlement

agreement (settlement agreement) disposing of all remaining

claims between the two parties. On March 14, 2025, a bench

trial was held on the remaining claims between AVCO and the

remaining defendants, APC and Merchants. The parties agreed to

waive detailed findings of fact. See Rule 20(2)(h) of the Rules

of the Superior Court (2018). That rule allows the parties to

submit special questions to the judge on the elements of each

3 claim equivalent to that of a jury verdict form. The parties

also agreed to the content of a special verdict slip. The judge

concluded that AVCO was responsible for the Project's security

system and that any claims it had against APC and Merchants were

extinguished by the settlement agreement. AVCO timely appealed

therefrom.

Discussion. Where, as here, the parties agreed to waive

detailed findings of fact under Superior Court Rule 20(2)(h),

"appellate review of the court's decision and of the judgment

entered shall be according to the standard of review that would

apply to a verdict by a jury in a case tried to a jury and to

the judgment entered thereon." Rule 20(8)(b) of the Rules of

the Superior Court. In other words, the verdict, and the

judgment entered thereon, will be upheld so long as "anywhere in

the evidence, from whatever source derived, any combination of

circumstances could be found from which a reasonable inference

could be drawn in favor of the [prevailing party]" (citation

omitted). Rabassa v. Cerasuolo, 97 Mass. App. Ct. 809, 814

(2020).

AVCO argues that the judge erred in concluding that it was

responsible for the security system because G. L. c. 149, § 44F,

the public bidding statute, requires that all electrical work be

4 contained in a single section of the specifications.3 In the

context of the present case, the argument is unavailing.

We agree that Division 26 does not reference the security

system, but this fact alone is not determinative under G. L.

c. 149, § 44F. The test here requires considering "the degree

of obviousness of the omission, error or discrepancy in the

specifications." John F. Miller Co. v. George Fichera Constr.

Corp., 7 Mass. App. Ct. 494, 498 (1979).4 "If the discrepancy is

subtle, so that a person furnishing labor and materials, who

examines the specifications reasonably and conscientiously,

might miss a requirement which is out of sequence or ineptly

expressed, the burden of the error falls on the issuer of the

specifications . . . ." Id. at 498. By contrast, "[w]here a

contractor or subcontractor is presented with an obvious

omission, inconsistency or discrepancy, he should at least ask

for clarification if he intends to 'bridge the crevasse in his

own favor.'" Id. at 499, quoting Beacon Constr. Co. v. United

States, 314 F.2d 501, 504 (Ct. Cl. 1963). Thus, where the

language in Division 26 is silent as to the security system we

3 Section 44F states, in part, that "specifications shall have a separate section for each of the following classes of work if in the estimate of the awarding authority such class of work will exceed $25,000: . . . electrical work."

4 John F. Miller Co. discusses G. L. c. 149, 44C, which is currently codified as G. L. c. 149, 44F.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hardware Specialties, Inc. v. Mishara Construction Co.
311 N.E.2d 564 (Massachusetts Appeals Court, 1974)
John F. Miller Co. v. George Fichera Construction Corp.
388 N.E.2d 1201 (Massachusetts Appeals Court, 1979)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
AVCO ELECTRIC, INC. v. APC DEVELOPMENT GROUP, INC., & Others., Counsel Stack Legal Research, https://law.counselstack.com/opinion/avco-electric-inc-v-apc-development-group-inc-others-massappct-2026.