Avanzalia Solar, S.L. v. Goldwind USA, Inc.

CourtCourt of Appeals for the Seventh Circuit
DecidedJuly 25, 2025
Docket23-1345
StatusPublished

This text of Avanzalia Solar, S.L. v. Goldwind USA, Inc. (Avanzalia Solar, S.L. v. Goldwind USA, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Avanzalia Solar, S.L. v. Goldwind USA, Inc., (7th Cir. 2025).

Opinion

In the

United States Court of Appeals For the Seventh Circuit ____________________ No. 23-1345 AVANZALIA SOLAR, S.L., et al., Plaintiffs-Appellants, v.

GOLDWIND USA, INC., Defendant-Appellee. ____________________

Appeal from the United States District Court for the Northern District of Illinois, Eastern Division. No. 1:20-cv-05035 — Matthew F. Kennelly, Judge. ____________________

ARGUED NOVEMBER 8, 2023 — DECIDED JULY 22, 2025 ____________________

Before ROVNER, JACKSON-AKIWUMI, and PRYOR, Circuit Judges. JACKSON-AKIWUMI, Circuit Judge. Appellants, Avanzalia Panamá and its indirect parent company Avanzalia Solar, in- vested in and built a solar plant in Panama. For years, they endeavored to connect that solar plant to an electrical substa- tion needed to sell electricity. Their quest took them from Pan- ama’s administrative agencies to our federal courts, where their cause was lost on summary judgment. On appeal, they 2 No. 23-1345

ask us to resolve three questions: one, whether the district court was correct to afford comity to a Panamanian adminis- trative agency decision; two, whether the district court properly applied collateral estoppel to bar claims related to that decision; and three, whether the district court erred in disposing of their tortious interference claims as a matter of Illinois state law. We affirm on the first two questions and re- mand for further proceedings on the third. I We recount the facts in the light most favorable to the solar plant owners as the party opposing summary judgment. See Johnson v. Edward Orton, Jr. Ceramics Found., 71 F. 4th 601, 609 (7th Cir. 2023). A. Avanzalia’s Conflict with Goldwind 1. The Parties & Their Projects The plaintiffs (together “Avanzalia”) are Avanzalia Pan- amá, S.A., a Panamanian corporation that owns a large solar power plant, and Avanzalia Solar, S.L., its Spanish affiliate that invested in the construction of the plant. The defendant is Goldwind USA, Inc., a Chinese-owned Delaware corpora- tion that sells wind turbines and is headquartered in Chicago, Illinois. In 2010, Unión Eólica Panameña (“UEP”) began develop- ing a large Panamanian wind farm, part of which would one day include the El Coco substation (substations are facilities that serve as a junction between electricity-generating stations and consumers). Starting in 2012, UEP subdivided the wind project into parcels owned by UEP, UEPI, and UEPII. That process involved transferring UEP’s ownership of the planned El Coco substation parcel to UEP Penonomé I No. 23-1345 3

(“UEPI”), Goldwind’s Panamanian affiliate and alter-ego. UEPI was established as a special-purpose vehicle to con- struct the El Coco substation. In 2014, after the parcels were split up, UEP, UEPI, and UEPII entered an agreement to limit the access of other market agents, such as Avanzalia, to the El Coco substation if that access would affect the substation’s ca- pacity available to their own projects. To broadly summarize the controversy here: In 2015, Avanzalia sought to connect its own recently developed power plant to the El Coco substation, which was the closest and only authorized substation through which the plant could connect to the national grid. To do so, it contacted UEP under the assumption that UEP still owned the substation. As alleged in Avanzalia’s complaint, Goldwind then tortiously blocked Avanzalia’s access to the substation by directing UEPI from Chicago to act in ways that violated Panamanian law and prevented Avanzalia from selling electricity on the open market and performing its own contractual obligations as an electricity provider. 2. Panama’s Framework for the Provision of Electricity Services Autoridad de Servicios Públicos (“ASEP”) is the adminis- trative agency that regulates public services, including elec- tricity, in Panama. Panamanian law empowers ASEP to issue regulations, manage regulation compliance, impose sanc- tions, resolve conflicts, and issue orders and resolutions. ASEP also issues “definitive licenses” to providers wishing to build, operate, and generate electricity from power plants. Empresa de Transmisión Eléctrica (“ETESA”) is Panama’s government-run utility company tasked with managing the 4 No. 23-1345

nation’s power grid. Any entity seeking to connect to Pan- ama’s grid must seek a “certificate of viability” from ETESA. Entities seeking to connect to the grid through a substation not owned by ETESA must complete the following process to obtain a certificate: (i) send the substation owner electrical studies showing the impact of the proposed connection on the substation and grid, and execute a contract (an “access agree- ment”) with the substation owner; (ii) submit the electrical studies and the executed access agreement to ETESA; and (iii) wait for ETESA to send the electrical studies to the substation owner for comment. Panamanian regulations state that sub- station owners with “remaining capacity” cannot reject a re- quest for access, “except [when the requesting entity is] in breach of the requirements set out in [the] [r]egulation[s].” 3. Avanzalia Endeavors to Establish a Power Plant After a year spent consulting with an electrical engineer and gathering the necessary paperwork, Avanzalia finally ob- tained everything that it thought was necessary to operate its power plant. That included a definitive license from ASEP and a certificate of viability from ETESA. ETESA’s certificate of viability required Avanzalia to connect its power plant to the nation’s grid through the El Coco substation. So, in August 2015, with those documents in hand, Avanzalia reached out to UEP hoping to negotiate an access agreement. 4. Avanzalia’s Endeavors Hit a Snag That same month, UEP informed Avanzalia that it would not grant the solar plant an access agreement because certain regulatory requirements had been violated. Specifically, UEP asserted that Avanzalia’s viability certificate was issued in er- ror because ETESA failed to first confirm that Avanzalia No. 23-1345 5

successfully obtained an access agreement from UEPI and failed to send Avanzalia’s electrical studies to UEPI for com- ment. Avanzalia countered that those requirements were not necessary because ETESA had concluded that the substation had “remaining capacity.” The following month, UEPI told Avanzalia that it would need to provide UEPI with copies of the missing electrical studies to move forward with an access agreement. B. Administrative Recourse and Ensuing Litigation 1. Foreign Administrative Proceedings In early 2016, Avanzalia filed a complaint with ASEP seek- ing the agency’s intervention in the brewing conflict. Avanzalia and UEPI filed documents, ASEP held a hearing, and UEPI argued that the diagram and electrical studies sub- mitted by Avanzalia were outdated. UEPI also informed ASEP that the substation was already using 270 of its 280- megawatt capacity, which meant that the substation would need new infrastructure and equipment to accommodate Avanzalia’s 120-megawatt plant. After nearly a year and a half of administrative arbitration, ASEP issued an order in June 2017. The order required Avanzalia to submit to UEPI a renewed request for substation access, an updated diagram, and updated electrical studies. The order also required UEPI to grant Avanzalia an access agreement once Avanzalia met these requirements. One month later, in July 2017, ASEP issued another order setting deadlines for the parties to comply with its directives. In this second order, ASEP concluded that regulations had in- deed been violated because Avanzalia had not sent UEPI the required electrical studies and had not obtained an access 6 No. 23-1345

agreement with UEPI before seeking a certificate from ETESA. After further objections from the parties, ASEP issued a fi- nal order in October 2017. Two months later, in December 2017, Avanzalia and UEPI finally executed an access agree- ment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hilton v. Guyot
159 U.S. 113 (Supreme Court, 1895)
Pierce v. Underwood
487 U.S. 552 (Supreme Court, 1988)
Koon v. United States
518 U.S. 81 (Supreme Court, 1996)
Ingersoll Milling MacHine Co. v. John P. Granger
833 F.2d 680 (Seventh Circuit, 1987)
United States v. Kashamu
656 F.3d 679 (Seventh Circuit, 2011)
Puffer v. Allstate Insurance
675 F.3d 709 (Seventh Circuit, 2012)
Darrell Williams v. Shell Oil Company
18 F.3d 396 (Seventh Circuit, 1994)
F: AJ KIKSON v. Underwriters Laboratories, Inc.
492 F.3d 794 (Seventh Circuit, 2007)
Fred Olson Motor Service v. Container Corp. of America
401 N.E.2d 1098 (Appellate Court of Illinois, 1980)
American Family Mutual Insurance v. Savickas
739 N.E.2d 445 (Illinois Supreme Court, 2000)
Nowak v. St. Rita High School
757 N.E.2d 471 (Illinois Supreme Court, 2001)
Scholwin v. Johnson
498 N.E.2d 249 (Appellate Court of Illinois, 1986)
Schuler v. Abbott Laboratories
639 N.E.2d 144 (Appellate Court of Illinois, 1993)
Town of Greece v. Galloway
134 S. Ct. 1811 (Supreme Court, 2014)
Aaron McCoy v. Iberdrola Renewables, Inc.
760 F.3d 674 (Seventh Circuit, 2014)
Till Derr v. Thomas Swarek
766 F.3d 430 (Fifth Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Avanzalia Solar, S.L. v. Goldwind USA, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/avanzalia-solar-sl-v-goldwind-usa-inc-ca7-2025.