Avanzalia Solar, S.L. and Avanzalia Panama, S.A. v. Goldwind USA, Inc., d/b/a Goldwind Americas

District Court, N.D. Illinois·Decided March 17, 2026·No. 1:20-cv-05035·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF ILLINOIS EASTERN DIVISION

AVANZALIA SOLAR, S.L. and ) AVANZALIA PANAMA, S.A., ) ) Plaintiffs, ) ) vs. ) Case No. 20 C 5035 ) GOLDWIND USA, INC., d/b/a ) GOLDWIND AMERICAS, ) ) Defendant. )

MEMORANDUM OPINION AND ORDER MATTHEW F. KENNELLY, District Judge: Avanzalia Solar, S.L. and Avanzalia Panama, S.A. sued Goldwind USA, Inc. for tortious interference with prospective economic advantage and tortious interference with contract. The Court granted summary judgment to Goldwind on both claims. Avanzalia appealed. The Seventh Circuit affirmed on the prospective economic advantage claim and remanded the case for further consideration of an alternate theory on the interference with contract claim. See Avanzalia Solar, S.L. v. Goldwind USA, Inc., 146 F.4th 553 (7th Cir. 2025). On remand, the Court denied Goldwind's motion for summary judgment on the tortious interference with contract claim. The case is now set for trial in April 2026. In advance of the trial and under Federal Rule of Procedure 44.1, the Court held a two-day hearing regarding a question of foreign law implicated by Avanzalia's remaining claim: whether certain provisions of the Master Agreement and Undertaking between Goldwind and its Panamanian affiliates violate the free access principle of Panamanian law. The Court holds that section 7.2 of the Master Agreement does not violate the free access principle, but section 2.3 of the Undertaking is inconsistent with the free access principle and any actions taken by Goldwind based on that provision would violate the free access principle. A jury must

assess whether Goldwind took such actions and must also decide the remaining elements of Avanzalia's claim. Background A. Factual background Avanzalia Panama is a Panamanian corporation that owns a solar power plant in Panama. Avanzalia Solar, a Spanish energy company, owns Avanzalia Panama and invested in its solar power plant. Goldwind is a Delaware corporation with its headquarters and principal place of business in Chicago. Goldwind manufactures wind turbines. Goldwind and Unión Eólica Panameña (UEP) developed the 336.8 MW Penonomé Wind Project, a Panamanian wind farm employing Goldwind's turbines that

included the El Coco Substation, a facility connecting the electricity produced by the wind farm to the national grid. The project was divided into phases with a different UEP entity (UEP, UEP I, and UEP II) responsible for each phase. UEP I is Goldwind's Panamanian alter ego. Empresa de Transmision Electrica, S.A. (ETESA) is a government-run transmission company that maintains and manages the Panamanian national grid. ETESA must issue a certificate of viability before an entity may connect to the national grid. Autoridad Nacional de los Servicios Publicos (ASEP) is the governmental agency that regulates electricity and other public services in Panama. ASEP issues definitive licenses to entities that wish to build, operate, and generate electricity from power plants. In 2013, the three UEP entities and Goldwind entered into a contract, the Master Agreement. Section 7.2 of the Agreement provided:

… the Company [UEP] shall not grant access to the Substation and to the current right under the Interconnection Agreement (as defined in the Credit Agreement) to interconnect up to 281.8MW (ie. the remaining interconnection capacity after deducting the 55MW of Phase I from the 336.8 MW total interconnection capacity) to any other market agent . . . to the extent that such access affects or may affect Phase II or the Remainder's capacity to connect to the energy grid and deliver its energy through the Shared Facilities. Master Agreement § 7.2. The Court addresses this provision below. In 2014, a new investor took over UEP II, and the same parties adopted the Undertaking Regarding Shared Assets and Interconnection. It contained a similar provision: "[N]one of the Parties nor the Facilities Company shall grant access to the El Coco Substation, and UEP I shall not transfer its Excess Rights other than as contemplated by Section 2.2 to any other than each owner of the Projects." Undertaking § 2.3. The Court will also address this provision below. The Undertaking remained binding on most of the parties until Goldwind sold the El Coco Substation in 2020. See Pl.'s Mem. of L. at 2 n.1. In 2013, Avanzalia entered the Panamanian energy market to build solar farms. It sought a connection to the El Coco Substation, through which the energy produced on its solar farms could reach consumers. UEP I denied Avanzalia access to the substation. Avanzalia filed a complaint with ASEP. ASEP issued several orders, recognizing UEP I's argument that Avanzalia had submitted outdated electrical studies and an outdated diagram to ETESA in violation of the transmission regulations, requiring Avanzalia to submit updated versions to UEP I along with a renewed request for substation access, and requiring UEP I to grant the access request once Avanzalia had complied with the transmission regulations. In 2017, Avanzalia and UEP I executed an agreement allowing Avanzalia to access the El Coco Substation.

Avanzalia alleges that UEP I then engaged in further misconduct by delaying the issuance of construction contracts and stalling construction. Avanzalia expected to have its plant operational in 2017 and executed power purchase agreements with five entities: Tova S.A., Nuevos Hoteles de Panama, Tamek, S.A., Invesiones Parna, S.A., and Kadima, S.A. In June 2019, ETESA issued a certificate of viability to Avanzalia. Avanzalia claims that the purposes of this agreement and its five power purchase agreements were thwarted by the misconduct of Goldwind (via UEP I). Without a connection to the El Coco Substation, Avanzalia could not access the national grid to perform under its agreement with ETESA or its power purchase agreements.

In May 2020, after UEP I sold the El Coco Substation, Avanzalia finally connected to the substation. It began selling electricity from its plant in January 2021. B. Procedural history Avanzalia sued Goldwind for tortious interference with prospective economic advantage and with contract. As indicated earlier, Goldwind moved for summary judgment, and the Court granted Goldwind's motion. See Avanzalia Solar, S.L. v. Goldwind USA, Inc., No. 20 C 5035, 2023 WL 319135, at *1 (N.D. Ill. Jan. 19, 2023). On appeal, the Seventh Circuit affirmed the Court's decision in part but remanded for consideration of a second theory of tortious interference with contract arising from Restatement (Second) of Torts § 766A that the Court had failed to address. Avanzalia Solar, 146 F.4th at 565–66. The Seventh Circuit directed the Court to address that theory with respect to the June 2019 ETESA contract and the five power purchase agreements. Id. at 566.

A tortious interference claim under section 766A has four elements that the plaintiff must establish: (1) it had a valid and enforceable contract with another party; 2) the defendant was aware of the contractual relationship; 3) the defendant intentionally and unjustifiably prevented the plaintiff from performing the contract; and 4) the plaintiff was damaged as a result. See Scholwin v. Johnson, 147 Ill. App. 3d 598, 607–08, 498 N.E.2d 249, 255–26 (1986); see also Restatement (Second) of Torts § 766A (1979). On remand, the Court denied Goldwind's motion for summary judgment. Avanzalia Solar, S.L. v. Goldwind USA, Inc., No. 20 C 5035, 2025 WL 2972720, at *4–5 (N.D. Ill. Oct. 21, 2025). The Court held that Goldwind failed to establish the absence of a genuine dispute of material fact on any one of the elements

Free access — add to your briefcase to read the full text and ask questions with AI

Avanzalia Solar, S.L. and Avanzalia Panama, S.A. v. Goldwind USA, Inc., d/b/a Goldwind Americas, (N.D. Ill. 2026).

Avanzalia Solar, S.L. and Avanzalia Panama, S.A. v. Goldwind USA, Inc., d/b/a Goldwind Americas (Avanzalia Solar, S.L. and Avanzalia Panama, S.A. v. Goldwind USA, Inc., d/b/a Goldwind Americas) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Scholwin v. Johnson
498 N.E.2d 249 (Appellate Court of Illinois, 1986)