Avalon Test Equip. Leasing, Inc. v. Emerald Design Constr., L.L.C.

2023 Ohio 1375
Ohio Court of Appeals·Decided April 27, 2023·No. 112186·Published

Opinion

[Cite as Avalon Test Equip. Leasing, Inc. v. Emerald Design Constr., L.L.C., 2023-Ohio-1375.]

COURT OF APPEALS OF OHIO

EIGHTH APPELLATE DISTRICT COUNTY OF CUYAHOGA

AVALON TEST EQUIPMENT : LEASING, INC., :

Plaintiff-Appellee,

: No. 112186 v.

:

EMERALD DESIGN & CONSTRUCTION, LLC, :

Defendant-Appellant. :

JOURNAL ENTRY AND OPINION

JUDGMENT: AFFIRMED IN PART, REVERSED IN PART AND REMANDED

RELEASED AND JOURNALIZED: April 27, 2023

Civil Appeal from the Cuyahoga County Court of Common Pleas Case No. CV-22-959627

Appearances:

Clark Hill PLC and Anthony A. Agosta, for appellee.

Forbes Law LLC and Glenn E. Forbes, for appellant.

EILEEN A. GALLAGHER, P.J.:

This appeal is before the court on the accelerated docket pursuant to App.R. 11.1 and Loc.App.R. 11.1. The purpose of an accelerated appeal is to allow an appellate court to render a brief and conclusory decision. E.g., Univ. Hts. v. Johanan, 8th Dist. Cuyahoga No. 110887, 2022-Ohio-2578, ¶ 1; State v. Trone, 8th

Dist. Cuyahoga Nos. 108952 and 108966, 2020-Ohio-384, ¶ 1, citing State v. Priest, 8th Dist. Cuyahoga No. 100614, 2014-Ohio-1735, ¶ 1; see also App.R. 11.1(E).

Defendant-appellant Emerald Design & Construction, LLC (“Emerald”) appeals the default judgment entered against it on plaintiff-appellee Avalon Test Equipment Leasing, Inc.’s (“Avalon”) complaint and the denial of Emerald’s motion to dismiss that complaint. For the reasons that follow, we affirm the denial of Emerald’s motion to dismiss and reverse the default judgment. I. Factual Background and Procedural History On February 15, 2022, Avalon filed a complaint “for entry of consent judgment,” alleging that Emerald breached a settlement agreement the parties had executed to terminate previous litigation in which they were involved, that being Cuyahoga C.P. No. CV-20-932105. Avalon further alleged that the settlement agreement required Emerald to make ten monthly payments of $7,500 starting in June 2021 and that Emerald had failed to make all but the first payment. Avalon alleged that the settlement agreement provided that if Emerald failed to abide by the payment terms, Avalon “would have the right to enter a consent judgment in the full amount” of Avalon’s original claim in the previous litigation — $129,926.95 — less any payments made under the settlement agreement. Avalon requested that the trial court enter a consent judgment in the amount of $122,426.95.

Avalon filed a U.S. Postal Service certified mail receipt documenting that its complaint was delivered to Emerald on February 22, 2022. Emerald did not answer the complaint.

On April 6, 2022, Avalon filed an application for default judgment.

On June 8, 2022, the trial court entered an order setting a default hearing for June 23, 2022. The entry informed the parties that “if Defendant(s) answer before this date or appear at the default hearing, the default hearing will be converted into a case management conference” and warned that “the failure of any defendant to call [into the hearing on time] will result in the court proceeding with default judgment * * *.” The entry also ordered Avalon to file additional information, including an affidavit and proof regarding damages and a “copy of letter to defendant(s) re hearing and that judgment may be rendered.”

On June 14, 2022, Avalon filed a revised motion for default judgment attaching the additional information the court had ordered be presented.

On June 22, 2022 — the day before the default hearing — Emerald filed a motion to dismiss the complaint pursuant to Civ.R. 12(B)(6), arguing that there is no cause of action for “entry of [a] [c]onsent [j]udgment” and that the trial court lacked jurisdiction to enforce the settlement agreement. Avalon filed an opposition to the motion.

On November 2, 2022, the trial court denied Emerald’s motion to dismiss and granted Avalon’s motion for default judgment. The court’s journal entry stated as follows, in relevant part:

The case before the court is an independent action for breach of contract related to the settlement agreement. It is appropriate for the court to consider the merits. See, in part, William Silverman & Co. v.

Robert Carter & Assocs., 8th Dist. Cuyahoga Nos. 49307 and 49491, 1985 Ohio App. LEXIS 8200 (June 27, 1985). As such, Defendant’s

motion to dismiss is denied. The court grants plaintiff’s motion for default judgment and enters judgment as follows: Judgment is entered in favor of Plaintiff and against Defendant in the amount of $122,426.95 plus statutory interest from the date of judgment and costs. Final.

Emerald appealed and raises the following two assignments of error for review:

First Assignment of Error: The Trial Court erred in denying Emerald’s Motion to Dismiss.

Second Assignment of Error: The Trial Court erred in granting Default Judgment without setting a hearing under Civil Rule 55.

II. Law and Analysis1 A. Motion to Dismiss We review rulings on Civ.R. 12(B)(6) motions to dismiss under a de novo standard. “A motion to dismiss for failure to state a claim upon which relief can be granted is procedural and tests the sufficiency of the complaint. Under a de novo analysis, we must accept all factual allegations of the complaint as true and all reasonable inferences must be drawn in favor of the nonmoving party.” (Citation omitted.) NorthPoint Properties, Inc. v. Petticord, 179 Ohio App.3d 342, 2008- Ohio-5996, 901 N.E.2d 869, ¶ 11 (8th Dist.). “For a trial court to grant a motion to

1 Avalon attached ten exhibits to its appellate brief, largely consisting of documents

filed in the trial court during the course of the two litigation matters involving the parties. Emerald did not move to strike the exhibits but we note that we considered only the record on appeal in reaching our decision in this matter; we did not consider the exhibits attached to Avalon’s appellate brief. See App.R. 9(A); see also Green v. Zep Inc., 10th Dist. Franklin No. 19AP-477, 2020-Ohio-3896, ¶ 25. (“[R]eviewing courts are not to consider information that is not part of the trial court record and does not meet the requirements of App.R. 9(A).”).

dismiss for failure to state a claim upon which relief can be granted, it must appear ‘beyond doubt from the complaint that the plaintiff can prove no set of facts entitling [the plaintiff] to relief.’” Graham v. Lakewood, 2018-Ohio-1850, 113 N.E.3d 44, ¶ 47 (8th Dist.), quoting Grey v. Walgreen Co., 197 Ohio App.3d 418, 2011-Ohio- 6167, 967 N.E.2d 1249, ¶ 3 (8th Dist.). A court’s factual review is generally confined to the four corners of the complaint. See, e.g., Dabney v. Metro Appraisal Group, Inc., 8th Dist. Cuyahoga No. 106917, 2018-Ohio-4601, ¶ 15.

Emerald contends that there is no cause of action for “entry of [a]

[c]onsent [j]udgment” and that the trial court lacked jurisdiction to enforce the settlement agreement because the settlement agreement was not incorporated into the entry in the original litigation dismissing the case with prejudice. Stated differently, Emerald’s position is that no trial court can enforce the settlement agreement between the parties because the agreement was not incorporated into the original trial court’s dismissal entry terminating the previous litigation between them. That position is meritless.

A trial court’s retention of jurisdiction to enforce a settlement agreement “provides the most efficient means of enforcing the agreement” by “keep[ing] the matter in the court most familiar with the parties’ claims” and “keep[ing] the parties from having to file another action.” Infinite Sec. Solutions, L.L.C. v. Karam Properties II, Ltd., 143 Ohio St.3d 346, 2015-Ohio-1101, 37 N.E.3d 1211, ¶ 25. But, as Avalon correctly points out, a settlement agreement may also “be enforced through a separate action for breach of contract.” E.g., Superior Piping

Contrs., Inc. v. Reilly Industries, 8th Dist. Cuyahoga No. 90751, 2008-Ohio-4858, ¶ 14.

Free access — add to your briefcase to read the full text and ask questions with AI

Avalon Test Equip. Leasing, Inc. v. Emerald Design Constr., L.L.C., 2023 Ohio 1375 (Ohio Ct. App. 2023).

2023 Ohio 1375 (Avalon Test Equip. Leasing, Inc. v. Emerald Design Constr., L.L.C.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bass v. Hoagland
172 F.2d 205 (Fifth Circuit, 1949)
State v. Priest
2014 Ohio 1735 (Ohio Court of Appeals, 2014)
Grey v. Walgreen Co.
2011 Ohio 6167 (Ohio Court of Appeals, 2011)
Superior Piping Contractors v. Reilly Indus., 90751 (9-25-2008)
2008 Ohio 4858 (Ohio Court of Appeals, 2008)
Reese v. Proppe
443 N.E.2d 992 (Ohio Court of Appeals, 1981)
Thomas v. City of Cleveland
892 N.E.2d 454 (Ohio Court of Appeals, 2008)
State v. Musleh
2017 Ohio 8166 (Ohio Court of Appeals, 2017)
Bank of Am., N.A. v. Smith
2018 Ohio 3638 (Ohio Court of Appeals, 2018)
Dabney v. Metro Appraisal Group, Inc.
2018 Ohio 4601 (Ohio Court of Appeals, 2018)
State v. Trone
2020 Ohio 384 (Ohio Court of Appeals, 2020)
Green v. Zep Inc.
2020 Ohio 3896 (Ohio Court of Appeals, 2020)
Granite City Ctr. v. Champion Twp. Bd. of Trustees
2021 Ohio 1458 (Ohio Court of Appeals, 2021)
Cleveland v. Wanton
2021 Ohio 1951 (Ohio Court of Appeals, 2021)
State ex rel. Davidson v. Beathard (Slip Opinion)
2021 Ohio 3125 (Ohio Supreme Court, 2021)
Johnson v. Abdullah (Slip Opinion)
2021 Ohio 3304 (Ohio Supreme Court, 2021)
Northpoint Properties, Inc. v. Petticord
901 N.E.2d 869 (Ohio Court of Appeals, 2008)
Blakemore v. Blakemore
450 N.E.2d 1140 (Ohio Supreme Court, 1983)
Funk v. Rent-All Mart, Inc.
742 N.E.2d 127 (Ohio Supreme Court, 2001)