Automatic Sprinkler Corp. v. Southern California Edison Co.

216 Cal. App. 3d 627, 266 Cal. Rptr. 662, 1989 Cal. App. LEXIS 1363
CourtCalifornia Court of Appeal
DecidedAugust 15, 1989
DocketD009059
StatusPublished
Cited by6 cases

This text of 216 Cal. App. 3d 627 (Automatic Sprinkler Corp. v. Southern California Edison Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Automatic Sprinkler Corp. v. Southern California Edison Co., 216 Cal. App. 3d 627, 266 Cal. Rptr. 662, 1989 Cal. App. LEXIS 1363 (Cal. Ct. App. 1989).

Opinion

Opinion

TODD, Acting P. J.

Automatic Sprinkler Corporation of America, a division of Figgie International, Inc. (Automatic), appeals after the trial court granted a summary judgment for Southern California Edison Company (Edison) in Automatic’s action to enforce a mechanic’s lien and to impose liability on Edison for failing to require its general contractor on the San Onofre Nuclear Generating Station (SONGS) to post a payment bond as required for public entities in the construction of public works pursuant to Civil Code section 3247. 1

Automatic contends the summary judgment was erroneously granted because there are triable issues of material fact concerning (1) whether *630 Edison was a “public entity” engaged in a “public work” for purposes of the payment bond requirement of section 3247, (2) when the completion date of the SONGS project occurred for purposes of determining the timeliness of filing the mechanic’s lien, and (3) whether Edison is estopped to rely on Automatic’s mechanic’s lien misfiled in Orange County rather than San Diego County as a basis for obtaining summary judgment. Automatic asserts legal error alone in the trial court’s application of section 3144 to nullify any lien because of Automatic’s failure to comply with the section’s requirement that an action to foreclose the lien must be commenced in the proper court within 90 days after the recording of the claim of lien.

Concluding that section 3144 precludes recovery in the case thus rendering other asserted factual issues immaterial, and that Edison very clearly is not a public entity for purposes of the payment bond provision of section 3247, we hold the trial court properly granted summary judgment.

Facts

SONGS is private property partially owned by Edison which contracted with C.F. Opel, Inc. (Opel), general contractor for a work of improvement at SONGS. In May 1985 Automatic, as subcontractor, entered a series of written agreements with Opel to furnish labor and material for the work of improvement at SONGS. Opel has since come under the protection of the federal bankruptcy laws.

Under its contract with Opel, Automatic installed a fire sprinkler protection system in the administration and other buildings on the SONGS property. The total amount of $119,369.19 became due Automatic from Opel. A balance of $73,099.89 remains unpaid.

After filing stop notices with Edison and written preliminary notices with Opel and Edison, on June 11, 1986, Automatic recorded with the Orange County Recorder its verified claim of mechanic’s lien. SONGS is in San Diego County which is where the claim of lien was required to be filed.

On August 21, 1986, in the Orange County Superior Court, Automatic filed an action to foreclose its mechanic’s lien, also alleging Edison was negligent in failing to require Opel to file a payment bond before Opel’s commencement of the SONGS work of improvement.

After discovering its filing error, on October 13, 1986, Automatic recorded a mechanic’s lien with the San Diego County Recorder. On October 31, *631 1986, Automatic filed a motion in the Orange County Superior Court for transfer of the action to the San Diego County Superior Court. The motion was set to be heard December 2, 1986.

In the meantime, in a bankruptcy proceeding filed by Opel in Texas, Edison sought and obtained a series of 10-day restraining orders covering the period October 30, 1986, through December 11, 1986. The December 2, 1986, hearing in Orange County Superior Court on Automatic’s motion for transfer to San Diego County Superior Court was taken off calendar.

On January 29, 1987, Automatic refiled its motion for transfer, and on February 23, pursuant to stipulation of the parties, the matter was ordered transferred to San Diego County Superior Court. Notice of the order for change of venue was filed in Orange County on March 17, and San Diego County Superior Court officially received the transferred action on March 30.

Edison’s notice of motion for summary judgment dated April 25, 1988, was set for hearing on June 23, 1988, and actually heard July 19, 1988. An order for entry of summary judgment and the summary judgment were filed September 30, 1988.

Discussion

I

Payment Bond Requirement Inapplicable to the Private Corporation, Edison.

Section 3247, subdivision (a), provides in pertinent part: “Every original contractor to whom is awarded a contract by a public entity, except as provided in subdivision (d) of Section 7103 of the Public Contract Code, involving an expenditure in excess of twenty-five thousand dollars ($25,000) for any public work shall, before entering upon the performance of the work, file a payment bond with and approved by the officer or public entity by whom the contract was awarded.” (Italics added.)

Automatic ignores plain statutory language defining “public entity” and “public work,” and uncontradicted evidence showing the private corporate status of Edison, in seeking to extend the payment bond protection of *632 section 3247 (see §§ 3096, 3181, 3248, 3252) 2 to the SONGS work of improvement in which it participated. Principles of liberal construction favoring laborers and materialmen (see Hutnick v. United States Fidelity & Guaranty Co. (1988) 47 Cal.3d 456, 462 [253 Cal.Rptr. 236, 763 P.2d 1326]) do not aid Automatic in this case. Definitions of “public entity” and “public work” contained in sections 3099 and 3100 govern the construction of section 3247. (§ 3082.)

“ ‘Public entity’ means the state, Regents of the University of California, a county, city, district, public authority, public agency, and any other political subdivision or public corporation in the state.” (§ 3099.)

“ ‘Public work’ means any work of improvement contracted for by a public entity.” (§ 3100.)

It is not disputed that Edison is an investor-owned public utility engaged in the business of generating, transmitting and distributing electrical energy in portions of Southern and Central California by operating an interconnected and integrated electric utility system. Edison is a for-profit corporation having its rates regulated and authorized by the California Public Utilities Commission. Edison’s rates include an authorized rate of return which is part of the profit Edison receives from owning and operating the SONGS plant.

Edison owns and operates an 80 percent interest in SONGS unit No. 1 and a 75.05 percent interest in unit Nos. 2 and 3. Although SONGS is among Edison’s utility properties dedicated to public service for the purpose of generating, transmitting and distributing electrical energy to Edison’s utility customers, the nuclear generating facility is private property.

The fact that Edison is a public utility subject to control by the Legislature (Cal. Const., art.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Virgil Barham v. Southern California Edison Co.
88 Cal. Rptr. 2d 424 (California Court of Appeal, 1999)
Koudmani v. Ogle Enterprises, Inc.
47 Cal. App. 4th 1650 (California Court of Appeal, 1996)
L.A.M. Construction, Inc. v. Kriz
14 Cal. App. Supp. 4th 1 (Appellate Division of the Superior Court of California, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
216 Cal. App. 3d 627, 266 Cal. Rptr. 662, 1989 Cal. App. LEXIS 1363, Counsel Stack Legal Research, https://law.counselstack.com/opinion/automatic-sprinkler-corp-v-southern-california-edison-co-calctapp-1989.